This unit of competency covers the development and implementation of a plan to address existing erosion problems and to prevent further erosion and sediment problems. The development of the plan will address the relevant legislation and issues associated with land disturbing projects. It requires the ability to identify and establish suitable strategies to develop, implement and monitor an erosion and sediment strategy and manage the project from implementation through to completion to achieve required outcomes.

Planning and managing erosion and sediment control measures requires a knowledge of relevant environmental, planning and ground water legislation, erosion and sediment control techniques, setting work specifications and objectives for the property or catchment system.

This unit is applicable to persons who have a role in the managing of the following land based business:

Agricultural related industries

Production Horticulture

Agro- Forestry

Natural resource management

Roadside management and civil construction

Extractive mining industries

All work must be carried out to comply with workplace procedures, work health and safety legislation and codes, and sustainability practices.

This unit will require consultation with external experts such as land management consultants, planning authorities, Catchment Management Authority, Landcare, State and Federal Government Departments who provide advice, contractors, neighbours and other interested groups.

No occupational licensing, legislative, regulatory or certification requirements apply to this unit at the time of publication.

You may want to include more information here about the target group and the purpose of the assessments (eg formative, summative, recognition)



Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

Element

Performance criteria

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1. Conduct a property or catchment audit and identify areas with erosion and sediment problems

1.1 Identify soils susceptible to erosion and sediment loss and relationship to land classes for erosion potential

1.2 Conduct a property or site audit and document details using appropriate methodology

1.3 Identify and classify types of erosion and sediment loss

1.4 Identify the environmental and man made factors that influence rates and effects of erosion and sediment

1.5 Estimate the economic and environmental losses caused by erosion and sediment losses

1.6 Identify appropriate external sources of support to assist in the planning processes

1.7 Identify relevant regulatory planning authorities or environmental legislation for current project and future planning developments

2. Develop erosion and sediment control plan

2.1 Investigate erosion and sediment control measures consistent with industry principles

2.2 Develop erosion and sediment control strategy/s for project area and record in co-operation with land owner, relevant government and planning authorities and any other key stakeholders

2.3 Identify potential problems that may require future rectification and modification to original strategies

2.4 Develop erosion and sediment control plan to meet design specifications including environmental concerns, physical impacts, land use, production systems and key personnel

2.5 Develop monitoring processes for evaluating and reporting performance against erosion and sediment control plan for achieving short and long-term outcomes

2.6 Determine roles and responsibilities to all key personnel and stakeholders

3. Implement and manage the erosion and sediment control plan

3.1 Implement tasks in accordance with erosion and sediment control plan and structure specification

3.2 Manage the communication process including strategies for conflict resolution and problem solving

3.3 Monitor progress to ensure time, performance, cost and quality of work is achieved

3.4 Investigate and negotiate proposed variations in consultation with all key stakeholders

4. Evaluate the erosion and sediment control plan

4.1 Conduct inspection to review work completion and collate monitoring data

4.2 Identify alterations or modifications to the development plan and report to industry sector personnel, developer or consenting authority

4.3 Review outcomes of completed erosion and sediment control plan against agreed short and long term objectives and report to all key stakeholders

The candidate must be assessed on their ability to integrate and apply the performance requirements of this unit in a workplace setting. Performance must be demonstrated consistently over time and in a suitable range of contexts.

The candidate must provide evidence that they can:

identify appropriate erosion and sediment control strategy methods

prepare plans and reports on erosion and sediment control plans

develop an erosion and sediment control plan

communicate and collaborate effectively with all stakeholders for planning and conflict resolution

implement work health and safety control measures at site work operations

monitor, evaluate and analyse effectiveness of erosion and sediment plan outcomes

organise required resources and key stakeholders

The candidate must demonstrate knowledge of:

environment sustainability as a whole farm system approach

environmental issues with regard to water catchment, ecosystems, habitats and waste minimisation

relevant environmental, planning and groundwater legislation including licences and permits to implement erosion and sediment control activities

erosion control and design principles

planning processes for erosion and sediment control

project and risk management techniques and tools for the management of erosion and sediment control

soils and soil formation

earthmoving principles

work health and safety obligations and "Duty of Care"

subsurface and surface drainage principles and systems

Competency is to be assessed in the workplace or simulated environment that accurately reflects performance in a real workplace setting.

Assessors must satisfy current standards for RTOs.


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assingnment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

Element

Performance criteria

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1. Conduct a property or catchment audit and identify areas with erosion and sediment problems

1.1 Identify soils susceptible to erosion and sediment loss and relationship to land classes for erosion potential

1.2 Conduct a property or site audit and document details using appropriate methodology

1.3 Identify and classify types of erosion and sediment loss

1.4 Identify the environmental and man made factors that influence rates and effects of erosion and sediment

1.5 Estimate the economic and environmental losses caused by erosion and sediment losses

1.6 Identify appropriate external sources of support to assist in the planning processes

1.7 Identify relevant regulatory planning authorities or environmental legislation for current project and future planning developments

2. Develop erosion and sediment control plan

2.1 Investigate erosion and sediment control measures consistent with industry principles

2.2 Develop erosion and sediment control strategy/s for project area and record in co-operation with land owner, relevant government and planning authorities and any other key stakeholders

2.3 Identify potential problems that may require future rectification and modification to original strategies

2.4 Develop erosion and sediment control plan to meet design specifications including environmental concerns, physical impacts, land use, production systems and key personnel

2.5 Develop monitoring processes for evaluating and reporting performance against erosion and sediment control plan for achieving short and long-term outcomes

2.6 Determine roles and responsibilities to all key personnel and stakeholders

3. Implement and manage the erosion and sediment control plan

3.1 Implement tasks in accordance with erosion and sediment control plan and structure specification

3.2 Manage the communication process including strategies for conflict resolution and problem solving

3.3 Monitor progress to ensure time, performance, cost and quality of work is achieved

3.4 Investigate and negotiate proposed variations in consultation with all key stakeholders

4. Evaluate the erosion and sediment control plan

4.1 Conduct inspection to review work completion and collate monitoring data

4.2 Identify alterations or modifications to the development plan and report to industry sector personnel, developer or consenting authority

4.3 Review outcomes of completed erosion and sediment control plan against agreed short and long term objectives and report to all key stakeholders

The candidate must be assessed on their ability to integrate and apply the performance requirements of this unit in a workplace setting. Performance must be demonstrated consistently over time and in a suitable range of contexts.

The candidate must provide evidence that they can:

identify appropriate erosion and sediment control strategy methods

prepare plans and reports on erosion and sediment control plans

develop an erosion and sediment control plan

communicate and collaborate effectively with all stakeholders for planning and conflict resolution

implement work health and safety control measures at site work operations

monitor, evaluate and analyse effectiveness of erosion and sediment plan outcomes

organise required resources and key stakeholders

The candidate must demonstrate knowledge of:

environment sustainability as a whole farm system approach

environmental issues with regard to water catchment, ecosystems, habitats and waste minimisation

relevant environmental, planning and groundwater legislation including licences and permits to implement erosion and sediment control activities

erosion control and design principles

planning processes for erosion and sediment control

project and risk management techniques and tools for the management of erosion and sediment control

soils and soil formation

earthmoving principles

work health and safety obligations and "Duty of Care"

subsurface and surface drainage principles and systems

Competency is to be assessed in the workplace or simulated environment that accurately reflects performance in a real workplace setting.

Assessors must satisfy current standards for RTOs.

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Identify soils susceptible to erosion and sediment loss and relationship to land classes for erosion potential 
Conduct a property or site audit and document details using appropriate methodology 
Identify and classify types of erosion and sediment loss 
Identify the environmental and man made factors that influence rates and effects of erosion and sediment 
Estimate the economic and environmental losses caused by erosion and sediment losses 
Identify appropriate external sources of support to assist in the planning processes 
Identify relevant regulatory planning authorities or environmental legislation for current project and future planning developments 
Investigate erosion and sediment control measures consistent with industry principles 
Develop erosion and sediment control strategy/s for project area and record in co-operation with land owner, relevant government and planning authorities and any other key stakeholders 
Identify potential problems that may require future rectification and modification to original strategies 
Develop erosion and sediment control plan to meet design specifications including environmental concerns, physical impacts, land use, production systems and key personnel 
Develop monitoring processes for evaluating and reporting performance against erosion and sediment control plan for achieving short and long-term outcomes 
Determine roles and responsibilities to all key personnel and stakeholders 
Implement tasks in accordance with erosion and sediment control plan and structure specification 
Manage the communication process including strategies for conflict resolution and problem solving 
Monitor progress to ensure time, performance, cost and quality of work is achieved 
Investigate and negotiate proposed variations in consultation with all key stakeholders 
Conduct inspection to review work completion and collate monitoring data 
Identify alterations or modifications to the development plan and report to industry sector personnel, developer or consenting authority 
Review outcomes of completed erosion and sediment control plan against agreed short and long term objectives and report to all key stakeholders 

Forms

Assessment Cover Sheet

AHCSOL503 - Manage erosion and sediment control
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

AHCSOL503 - Manage erosion and sediment control

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: