The unit includes identification and confirmation of work requirement, preparation for work, dismantling of engines, repair, assembly and final checking of engines and completion of work finalisation processes, including clean-up and documentation.

This unit of competence should be contextualised to the qualification it is being applied.

For overhaul of outdoor power equipment engines and associated components see AURP401245B Overhaul engines and associated engine components (outdoor power equipment).

Work requires individuals to demonstrate some judgement and problem-solving skills in managing own work activities and contributing to a productive team environment.

Work is carried out in accordance with award provisions.

This unit covers the competence required to overhaul engines and associated engine components on an engine removed from its chassis.

You may want to include more information here about the target group and the purpose of the assessments (eg formative, summative, recognition)

Employability Skills

This unit contains employability skills.




Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.

Overview of assessment

Critical aspects for assessment and evidence required to demonstrate competency in this unit

It is essential that competence in this unit signifies ability to transfer competence to changing circumstances and to respond to unusual circumstances in the critical aspects of:

observing safety procedures and requirements

communicating effectively with others involved in or affected by the work

selecting methods and techniques appropriate to the circumstances

completing preparatory activity in a systematic manner

dismantling, evaluating, assembling, adjustment, measuring and testing engines in accordance with workplace and manufacturer/component supplier requirements

completing overhaul of a range of engines and associated components within workplace guidelines and timeframes

engine presentation to customer in compliance with workplace requirements

Context of, and specific resources for assessment

Application of competence is to be assessed in the workplace or simulated worksite

Assessment is to occur using standard and authorised work practices, safety requirements and environmental constraints

Assessment is to comply with regulatory requirements, including Australian Standards

The following resources should be made available:

workplace location or simulated workplace

materials relevant to the overhaul of engines

equipment, hand and power tooling appropriate to the overhaul of engines

activities covering mandatory task requirements

specifications and work instructions

Method of assessment

Assessment must satisfy the endorsed assessment guidelines of the automotive industry's RS&R Training Package

Assessment methods must confirm consistency and accuracy of performance together with application of underpinning knowledge

Assessment must be by direct observation of tasks, with questioning on underpinning knowledge and it must also reinforce the integration of key competencies

Assessment may be applied under project related conditions (real or simulated) and require evidence of process

Assessment must confirm a reasonable inference that competence is able not only to be satisfied under the particular circumstance, but is able to be transferred to other circumstances

It is preferable assessment reflects a process rather than an event and occurs over a period of time to cover varying quality circumstances. Evidence of performance may be provided by customers, team leaders/members or other appropriate persons subject to agreed authentication arrangements

Competence in this unit may be assessed in conjunction with other functional units which together form part of the holistic work role

Guidance information for assessment


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assingnment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

Required skills

apply research and interpretive skills sufficient to locate, interpret and apply manufacturer/component supplier procedures, workplace policies and procedures

apply analytical skills required for identification and analysis of technical information

apply plain English literacy and communication skills in relation to dealing with customers and team members

apply questioning and active listening skills for example when obtaining information from customers

apply oral communication skills sufficient to convey information and concepts to customers

apply planning and organising skills to work activities, including making good use of time and resources, sorting out priorities and monitoring own performance

interact effectively with other persons both on a one-to-one basis and in groups, including understanding and responding to the needs of a customer and working effectively as a member of a team to achieve a shared goal

establish safe and effective work processes which anticipate and/or resolve problems and downtime, to systematically develop solutions to avoid or minimise reworking and avoid wastage

use mathematical ideas and techniques to calculate time, assess tolerances, apply accurate measurements, calculate material requirements and establish quality checks

use workplace technology related to overhaul of engines, including use of specialist tooling and equipment, measuring equipment, computerised technology and communication devices and reporting/documenting of results

Required knowledge

A working knowledge of:

OH&S and environmental regulations/requirements, equipment, material and personal safety requirements

types, characteristics and operating processes of engines

types and layout of service/repair manuals (hard copy and electronic)

engine overhaul procedures

dismantling, assembling and adjustment methods

measuring and testing procedures

relevant technical information

component safety requirements

relevant enterprise policies

manual handling techniques

The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Engines

Engines may be:

4-stroke spark ignition engines for light vehicles, motorcycles and marine craft

2-stroke spark ignition for motorcycles and marine craft

4-stroke compression ignition engines for light vehicles, heavy vehicles, mobile plant and marine craft

2-stroke compression ignition for heavy vehicles, mobile plant and marine craft

Overhaul methods and sequences

Overhaul methods and sequences are to include the complete dismantling of component parts, measuring and evaluation of wear, the replacement, repair, rebuilding or reconditioning of parts comparable to original parts, the assembly of parts, performance of functional testing and the completion of records

OH&S

OH&S requirements are to be in accordance with legislation/regulations/codes of practice and enterprise safety policies and procedures. This may include protective clothing and equipment, use of tooling and equipment, workplace environment and safety, handling of materials, use of fire fighting equipment, enterprise first aid, hazard control and hazardous materials and substances

Personal protective equipment

Personal protective equipment is to include that prescribed under legislation/regulations/codes of practice and workplace policies and practices

Safe operating procedures

Safe operating procedures are to include, but are not limited to operational risk assessment and treatments associated with vehicular movement, toxic substances, electrical safety, machinery movement and operation, manual and mechanical lifting and shifting, working in proximity to others and site visitors

Emergency procedures

Emergency procedures related to this unit are to include, but are not limited to emergency shutdown and stopping of equipment, extinguishing fires, enterprise first aid requirements and site evacuation

Environmental requirements

Environmental requirements are to include but are not limited to waste management, noise, dust and clean-up management

Quality requirements

Quality requirements are to include, but are not limited to regulations, including Australian Standards, internal company quality policy and standards and enterprise operations and procedures

Statutory/regulatory authorities

Statutory/regulatory authorities may include Federal, State/Territory and local authorities administering acts, regulations and codes of practice

Tooling and equipment

Tooling and equipment may include hand tooling, power tooling, lifting and jacking equipment, specialist tooling, measuring equipment and tensioning equipment

Materials

Materials may include engine oils, moving parts lubricants, replacement parts, gaskets, sealants and cleaning materials

Communications

Communications are to include, but are not limited to verbal and visual instructions and fault reporting and may include site specific instructions, written instructions, plans or instructions related to job/task, telephones and pagers

Information/documents

Sources of information/documents may include:

verbal or written and graphical instructions, signage, work schedules/plans/specifications, work bulletins, memos, material safety data sheets, diagrams or sketches

safe work procedures related to the overhaul of engines

regulatory/legislative requirements pertaining to the automotive industry, including Australian Design Rules, Environment Protection Regulations (Diesel Fuels), National Environment Protection For Diesel Vehicle Guidelines

engineer's design specifications and instructions

organisation work specifications and requirements

instructions issued by authorised enterprise or external persons

Australian Standards

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Nature and scope of work requirements are identified and confirmed 
OH&S requirements, including individual State/Territory regulatory requirements and personal protection needs are observed throughout the work 
National Environmental Protection Measure for Diesel Vehicles (Guidelines) is sourced and observed throughout the work as applicable to tasks 
Technical and tooling requirements for overhaul are identified and support equipment is identified and prepared 
SWL rating of lifting devices, engine cradles, slings and shackles is confirmed against the load to be lifted 
Engine is dismantled in a logical sequence 
Dismantling of engine and relevant components is completed without causing damage to any component or system 
Components are cleaned ready for inspection 
Information is accessed and interpreted from manufacturer/component supplier specifications and repair/reclaim methods 
Components are measured and compared against manufacturer/component supplier specifications and tolerances 
Decisions are made as to serviceability and repair method of each component 
Replacement parts are sourced 
Rebuild or replacement of engine and/or engine components is carried out in accordance with manufacturer/component supplier specifications and tolerances 
Overhaul activities are carried out according to industry regulations/guidelines, OH&S legislation and enterprise procedures/policies 
Engine is assembled following manufacturer/component supplier procedures 
Running clearances are measured against manufacturer/component supplier specifications and necessary adjustments are made 
Assembly of engine is are completed within established industry guidelines and timeframes 
Assembly is completed without causing damage to any component or system 
Engine is securely mounted in preparation for starting 
Engine fluid levels, including lubrication and coolant are checked 
Gauges and warning devices are checked for operation prior to starting 
Engine is started and checked for leaks and abnormal noises 
Engine orifices are sealed against ingress of foreign matter 
Work completion documentation is finalised and processed to appropriate persons 
Final inspection is made to ensure protective features are in place 
Engine is cleaned to workplace expectations 
Job card is processed in accordance with workplace procedures 

Forms

Assessment Cover Sheet

AURT401145A - Overhaul engines and associated engine components
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

AURT401145A - Overhaul engines and associated engine components

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature: