List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.
Elements describe the essential outcomes. | Performance criteria describe the performance needed to demonstrate achievement of the element. Where bold italicised text is used, further information is detailed in the range of conditions. |
1. | Prepare for complex engineering set-out survey. | 1.1. | Organisational priorities are determined to identify project objectives and specifications. |
| 1.2. | Project specifications are presented to appropriate persons. |
| 1.3. | Characteristics of the operating environment and any special equipment or resource requirements are identified according to organisational requirements. |
| 1.4. | Surveying equipment is selected and checked to ensure correct operation and functionality according to manufacturer specifications. |
| | | |
2. | Plan complex engineering set-out survey. | 2.1. | Design is interpreted to identify surveying data components required for set-out. |
| 2.2. | Plan is developed detailing objectives, constraints, work activities, technologies and techniques to be used for set-out according to project specifications and client requirements. |
| 2.3. | Project management mechanisms are implemented to schedule, measure, record and report progress of activities in relation to agreed schedule and plans. |
| 2.4. | Agreed communication processes between client and other appropriate persons are implemented and maintained. |
| 2.5. | Risk management and contingency strategies are devised and followed to ensure project complies with legal and statutory standards and organisational requirements. |
| 2.6. | Work responsibilities are allocated and supervisory processes and problem-solving techniques implemented to ensure work is completed within time available. |
| | | |
3. | Manage complex engineering set-out survey. | 3.1. | Identified project components are accurately set out according to project specifications. |
| 3.2. | Set-out measurements and calculations are conducted, validated and recorded using control network according to project specifications. |
| 3.3. | Project progress is reviewed and agreed changes are implemented to ensure consistency with project scope, objectives and constraints. |
| 3.4. | Problems are identified and resolved, and contingencies managed according to organisational requirements. |
| | | |
4. | Finalise complex engineering set-out survey. | 4.1. | Project is finalised and checked for compliance with project and organisational requirements. |
| 4.2. | Appropriate persons are notified of project results according to organisational requirements. |
| 4.3. | Documentation is completed and spatial data archived according to project and organisational requirements. |
| | | |
5. | Review project. | 5.1. | Project achievements are reviewed against organisational strategic goals. |
| 5.2. | Recommendations are made on possible links between project achievements and future organisational goals. |
A person demonstrating competency in this unit must satisfy the requirements of the elements, performance criteria, foundation skills and range of conditions of this unit. The person must also conduct a complex engineering set-out survey for two different projects.
While conducting the above complex engineering set-out surveys, the person must:
analyse survey set-out specifications, including:
cross-sections and plans
technical descriptions of surveying data and set-out requirements
develop a project plan, including detail of:
project objectives and deliverables
constraints
risk management and contingency strategies
work activities
technologies and techniques to be used
interpret engineering design information and specifications to identify components to be measured
plan and document data collection methodologies that allow for contingencies
schedule work tasks and organise resources and equipment
apply industry-accepted standards for performing surveying measurements and computations
communicate clearly with others to clarify and report work information and negotiate completion of tasks
comply with industry-accepted standards for validating accuracy of surveying data and identifying errors and discrepancies
comply with organisational, legal and statutory requirements for:
completing records and documentation
recording, storing and filing data
using, checking and storing surveying equipment
working safely and using personal protective equipment (PPE)
conduct set-out measurements and calculations to meet engineering specifications using two of the following pieces of surveying equipment:
current meter
global navigation satellite system (GNSS)
level
tape
theodolite
total station
implement project management mechanisms to ensure the survey is completed within required timeframes and complies with specifications
review project outcomes against strategic organisational goals to identify links to future goals
supervise staff to complete work tasks on time.
A person demonstrating competency in this unit must demonstrate knowledge of:
accuracy and precision requirements for setting out surveying data
data capture, set-out and reduction techniques
industry-accepted methods for validating data to identify errors and discrepancies
legislative, statutory and industry requirements and standards relating to work tasks associated with set-out surveys
methods for calculating surveying data and verifying its accuracy using primary and secondary controls
methods for establishing a control network that meets specified tolerances
methods for setting up, levelling and calibrating surveying equipment
organisational policies and procedures relating to:
health and safety relating to surveying activities
reporting and documentation
using and allocating resources
using the surveying equipment specified in the performance evidence
project management techniques for scheduling, measuring and monitoring work progress and planning for contingencies
reference and coordinate systems for surveying data, including Australian Height Datum and Map Grid of Australia.
The following must be present and available to learners during assessment activities:
equipment:
as specified in the performance evidence, including PPE
materials:
paper for printing reports, documents and data
specifications:
organisational policies, procedures and documentation relating to work health and safety
survey specifications, including relevant engineering plans and drawings
relationships with team members and supervisor:
lead role in a team.
Timeframe:
as specified by project requirements.
Assessor requirements
As a minimum, assessors must satisfy the assessor requirements in the Standards for Registered Training Organisations (RTOs) current at the time of assessment.