This unit describes the skills and knowledge required to produce complex folded product, monitor and adjust machinery, maintain transportation of the substrate, identify and rectify faults, and correctly clean and shut down equipment.

No licensing, legislative or certification requirements apply to this unit at the time of publication.

You may want to include more information here about the target group and the purpose of the assessments (eg formative, summative, recognition)



Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

ELEMENT

PERFORMANCE CRITERIA

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1. Maintain delivery system

1.1 Delivery systems are monitored and adjusted to ensure continuous and efficient operation

1.2 Substrate is added to the process according to job specifications

2. Maintain production process

2.1 Registration and squareness of fold are monitored and adjusted to ensure product quality meets the approved sample standard

2.2 Basic in-line printing/converting/binding/finishing process(es) are monitored and adjusted to ensure product quality meets the approved sample standard

2.3 Production process is operated in association with fellow workers and according to enterprise procedures and planned daily schedule

2.4 Production is maintained according to work health and safety (WHS) requirements, manufacturer’s specifications and enterprise procedures

2.5 Manual and/or automatic control is used according to job specifications

2.6 Performance is monitored and verified using the process control system according to enterprise procedures

2.7 Production difficulties are anticipated and preventive action is taken to prevent occurrence by timely intervention

2.8 Process adjustments to eliminate problems are reported according to enterprise procedures

2.9 Faulty performance of equipment is identified and reported according to enterprise procedures

2.10 Waste is sorted according to enterprise procedures

3. Identify and rectify problems and faults

3.1 Problems in folding (sequenced/multiple) machine operation are identified and reported according to enterprise procedures

3.2 Adjustments or corrections are carried out according to specified procedures, and are consistent with operator’s skill level

3.3 Folding (sequenced/multiple) machine operation is checked to ensure correct operation

3.4 Machine faults requiring repair are identified and reported to designated person according to enterprise procedures

3.5 Repair/adjustment is verified prior to resumption of operations

4. Conduct shutdown of production process

4.1 Correct shutdown sequence is followed according to manufacturer’s specifications and enterprise procedures

4.2 Shutdown is conducted in association with fellow workers and in compliance with WHS requirements

4.3 Substrate waste is removed from operating area and recycled or disposed of, where required, according to regulatory requirements and enterprise procedures

5. Clean folding (single/ continuous) machine at end of run

5.1 Folding units are disengaged and cleaned ready for next run

5.2 In-line printing/converting/binding/finishing units are cleaned ready for next run

5.3 Reel feed and transportation systems are disengaged and cleaned ready for next run

5.4 Production records or other documentation are accurately completed where required by enterprise procedures

Evidence of the ability to:

complete TWO jobs (if possible, using different sizes and weights of substrate) with:

a single fold to run continuously,

OR

a single quire fold on a sheet gather/stitch/fold/trim machine,

OR

an automatic web-fed machine to achieve a single fold,according to manufacturer’s and job specifications, enterprise procedures and listed performance criteria

demonstrate use of computerised control, monitoring and data entry systems if available and appropriate.

Note: If a specific volume or frequency is not stated, then evidence must be provided at least once.

To complete the unit requirements safely and effectively, the individual must:

All Systems

identify work health and safety factors for:

setting up and/or operating machine transport systems

setting up and/or operating machine delivery systems

using the folding machine

adjusting/correcting the machine

cleaning the machine

list checks to make when substrate is removed from the machine

list areas of the in-line process to monitor to ensure product quality

determine causes of out-of-square folding and explain how each can be corrected

determine segments of quality assurance inspected at sample run completion as well as in a completed folded job

explain communication to instigate if the:

job is out-of-square

ink is too wet for production

job does not coincide with the sample

identify important tasks to correctly shut down the machine

explain requirements to prepare finished work for dispatch

identify areas of the machine to clean regularly and materials to clean from the machine

explain requirements to keep the machine clear of surface rust (condensation)

determine production alterations needed to meet client requirements

identify machine manuals, safety and other documentation relevant to this task, where they are kept, and the information included in them

Reel Systems Only

identify areas of the reel stand to monitor to ensure trouble-free operation

list part(s) of the machine to adjust if the sheet is creasing

Sheet Systems Only

identify areas of the sheet-fed feeder to monitor to ensure trouble-free operation.

Gather evidence to demonstrate consistent performance in conditions that are safe and replicate the workplace. Noise levels, production flow, interruptions and time variances must be typical of those experienced in the converting, binding and finishing field of work and include access to relevant facilities, equipment and materials.

Assessors must satisfy NVR/AQTF assessor requirements.


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assingnment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

ELEMENT

PERFORMANCE CRITERIA

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1. Maintain delivery system

1.1 Delivery systems are monitored and adjusted to ensure continuous and efficient operation

1.2 Substrate is added to the process according to job specifications

2. Maintain production process

2.1 Registration and squareness of fold are monitored and adjusted to ensure product quality meets the approved sample standard

2.2 Basic in-line printing/converting/binding/finishing process(es) are monitored and adjusted to ensure product quality meets the approved sample standard

2.3 Production process is operated in association with fellow workers and according to enterprise procedures and planned daily schedule

2.4 Production is maintained according to work health and safety (WHS) requirements, manufacturer’s specifications and enterprise procedures

2.5 Manual and/or automatic control is used according to job specifications

2.6 Performance is monitored and verified using the process control system according to enterprise procedures

2.7 Production difficulties are anticipated and preventive action is taken to prevent occurrence by timely intervention

2.8 Process adjustments to eliminate problems are reported according to enterprise procedures

2.9 Faulty performance of equipment is identified and reported according to enterprise procedures

2.10 Waste is sorted according to enterprise procedures

3. Identify and rectify problems and faults

3.1 Problems in folding (sequenced/multiple) machine operation are identified and reported according to enterprise procedures

3.2 Adjustments or corrections are carried out according to specified procedures, and are consistent with operator’s skill level

3.3 Folding (sequenced/multiple) machine operation is checked to ensure correct operation

3.4 Machine faults requiring repair are identified and reported to designated person according to enterprise procedures

3.5 Repair/adjustment is verified prior to resumption of operations

4. Conduct shutdown of production process

4.1 Correct shutdown sequence is followed according to manufacturer’s specifications and enterprise procedures

4.2 Shutdown is conducted in association with fellow workers and in compliance with WHS requirements

4.3 Substrate waste is removed from operating area and recycled or disposed of, where required, according to regulatory requirements and enterprise procedures

5. Clean folding (single/ continuous) machine at end of run

5.1 Folding units are disengaged and cleaned ready for next run

5.2 In-line printing/converting/binding/finishing units are cleaned ready for next run

5.3 Reel feed and transportation systems are disengaged and cleaned ready for next run

5.4 Production records or other documentation are accurately completed where required by enterprise procedures

This section specifies different work environments and conditions that may affect performance. Essential operating conditions that may be present (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) are included.

Delivery systems MUST could include EITHER:

reel

OR

sheet.

Monitoring and adjusting MUST include EITHER:

reel stand

web control systems

OR

feeder and delivery systems

sheet pick-up and transport systems

transfer systems.

Evidence of the ability to:

complete TWO jobs (if possible, using different sizes and weights of substrate) with:

a single fold to run continuously,

OR

a single quire fold on a sheet gather/stitch/fold/trim machine,

OR

an automatic web-fed machine to achieve a single fold,according to manufacturer’s and job specifications, enterprise procedures and listed performance criteria

demonstrate use of computerised control, monitoring and data entry systems if available and appropriate.

Note: If a specific volume or frequency is not stated, then evidence must be provided at least once.

To complete the unit requirements safely and effectively, the individual must:

All Systems

identify work health and safety factors for:

setting up and/or operating machine transport systems

setting up and/or operating machine delivery systems

using the folding machine

adjusting/correcting the machine

cleaning the machine

list checks to make when substrate is removed from the machine

list areas of the in-line process to monitor to ensure product quality

determine causes of out-of-square folding and explain how each can be corrected

determine segments of quality assurance inspected at sample run completion as well as in a completed folded job

explain communication to instigate if the:

job is out-of-square

ink is too wet for production

job does not coincide with the sample

identify important tasks to correctly shut down the machine

explain requirements to prepare finished work for dispatch

identify areas of the machine to clean regularly and materials to clean from the machine

explain requirements to keep the machine clear of surface rust (condensation)

determine production alterations needed to meet client requirements

identify machine manuals, safety and other documentation relevant to this task, where they are kept, and the information included in them

Reel Systems Only

identify areas of the reel stand to monitor to ensure trouble-free operation

list part(s) of the machine to adjust if the sheet is creasing

Sheet Systems Only

identify areas of the sheet-fed feeder to monitor to ensure trouble-free operation.

Gather evidence to demonstrate consistent performance in conditions that are safe and replicate the workplace. Noise levels, production flow, interruptions and time variances must be typical of those experienced in the converting, binding and finishing field of work and include access to relevant facilities, equipment and materials.

Assessors must satisfy NVR/AQTF assessor requirements.

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Delivery systems are monitored and adjusted to ensure continuous and efficient operation 
Substrate is added to the process according to job specifications 
Registration and squareness of fold are monitored and adjusted to ensure product quality meets the approved sample standard 
Basic in-line printing/converting/binding/finishing process(es) are monitored and adjusted to ensure product quality meets the approved sample standard 
Production process is operated in association with fellow workers and according to enterprise procedures and planned daily schedule 
Production is maintained according to work health and safety (WHS) requirements, manufacturer’s specifications and enterprise procedures 
Manual and/or automatic control is used according to job specifications 
Performance is monitored and verified using the process control system according to enterprise procedures 
Production difficulties are anticipated and preventive action is taken to prevent occurrence by timely intervention 
Process adjustments to eliminate problems are reported according to enterprise procedures 
Faulty performance of equipment is identified and reported according to enterprise procedures 
Waste is sorted according to enterprise procedures 
Problems in folding (sequenced/multiple) machine operation are identified and reported according to enterprise procedures 
Adjustments or corrections are carried out according to specified procedures, and are consistent with operator’s skill level 
Folding (sequenced/multiple) machine operation is checked to ensure correct operation 
Machine faults requiring repair are identified and reported to designated person according to enterprise procedures 
Repair/adjustment is verified prior to resumption of operations 
Correct shutdown sequence is followed according to manufacturer’s specifications and enterprise procedures 
Shutdown is conducted in association with fellow workers and in compliance with WHS requirements 
Substrate waste is removed from operating area and recycled or disposed of, where required, according to regulatory requirements and enterprise procedures 
Folding units are disengaged and cleaned ready for next run 
In-line printing/converting/binding/finishing units are cleaned ready for next run 
Reel feed and transportation systems are disengaged and cleaned ready for next run 
Production records or other documentation are accurately completed where required by enterprise procedures 

Forms

Assessment Cover Sheet

ICPCBF342 - Produce complex sequenced or multiple folded product
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

ICPCBF342 - Produce complex sequenced or multiple folded product

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: