This unit describes skills and knowledge required to construct underground telecommunications infrastructure made up of conduits and enclosures for cabling provisioning.

It applies to individuals in technical roles in civil construction whose work involves the installation of pits and pre-built enclosures with connecting pipes for underground telecommunications infrastructure.

No licensing, legislative or certification requirements apply to this unit at the time of publication.

You may want to include more information here about the target group and the purpose of the assessments (eg formative, summative, recognition)



Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

ELEMENT

PERFORMANCE CRITERIA

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1. Prepare to construct underground work

1.1 Obtain construction design plan from appropriate personnel to scope work and arrange for site access

1.2 Notify appropriate personnel of identified safety hazards and other services

1.3 Obtain plant, tools and safety equipment to perform tasks safely and efficiently

1.4 Determine type of underground enclosure specified in construction design plan required for project

2. Install enclosure

2.1 Use tools according to enterprise guidelines and work health and safety (WHS) regulations

2.2 Place foundation of suitable material to provide safe and stable footing prior to installing underground enclosure in excavation

2.3 Place recognised barrier over construction where enclosure is to be installed over power cables according to enterprise requirements or agreements with other authorities

2.4 Install earth mat facility under enclosure where specified and required by enterprise

2.5 Install enclosure specified in construction design plan to manufacturer’s specifications using specified materials

3. Install connecting pipe works

3.1 Install conduit in trench to enterprise specifications

3.2 Connect conduit to enclosure according to manufacturer’s specifications and industry practice

4. Complete project

4.1 Complete reports according to enterprise policy and record alterations to plans using appropriate symbols

4.2 Recover obsolete materials and equipment, and return to appropriate point for disposal

4.3 Restore site according to requirements of enterprise or approving authority and to client satisfaction

4.4 Notify appropriate personnel of job completion and obtain sign off

Evidence of the ability to:

interpret and apply design plans and prepare for construction

install enclosures including pipe, pit and prefabricated manhole

construct in two different soil types: sand, rock, soil or combination soil types

shore an excavation site to meet enterprise and regulatory requirements

demonstrate use of specialised hand or power tools and equipment normally used for excavation, pipe, conduit installation and site restoration safely

complete the works and documentation

apply related work health and safety (WHS) requirements and work practices associated with excavation, enclosure installation and site restoration.

Note: If a specific volume or frequency is not stated, then evidence must be provided at least once.

To complete the unit requirements safely and effectively, the individual must:

describe the following elements of civil construction:

construction plant, tools and equipment operation

enclosure construction methods

foundations

plans

identify legislation, codes of practice and other formal agreements that impact on the work activity

identify the manufacturer’s requirements for safe operation of equipment

identify specific WHS requirements relating to the activity and site conditions

identify typical issues and challenges that occur on site.

Gather evidence to demonstrate consistent performance in conditions that are safe and replicate the workplace. Noise levels, production flow, interruptions and time variances must be typical of those experienced in the telecommunications – cabling field of work and include access to:

sites where enclosure construction may be conducted

construction equipment currently used in industry

relevant regulatory and equipment documentation that impacts on construction.

Assessors of this unit must satisfy the requirements for assessors in applicable vocational education and training legislation, frameworks and/or standards.


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assingnment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

ELEMENT

PERFORMANCE CRITERIA

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1. Prepare to construct underground work

1.1 Obtain construction design plan from appropriate personnel to scope work and arrange for site access

1.2 Notify appropriate personnel of identified safety hazards and other services

1.3 Obtain plant, tools and safety equipment to perform tasks safely and efficiently

1.4 Determine type of underground enclosure specified in construction design plan required for project

2. Install enclosure

2.1 Use tools according to enterprise guidelines and work health and safety (WHS) regulations

2.2 Place foundation of suitable material to provide safe and stable footing prior to installing underground enclosure in excavation

2.3 Place recognised barrier over construction where enclosure is to be installed over power cables according to enterprise requirements or agreements with other authorities

2.4 Install earth mat facility under enclosure where specified and required by enterprise

2.5 Install enclosure specified in construction design plan to manufacturer’s specifications using specified materials

3. Install connecting pipe works

3.1 Install conduit in trench to enterprise specifications

3.2 Connect conduit to enclosure according to manufacturer’s specifications and industry practice

4. Complete project

4.1 Complete reports according to enterprise policy and record alterations to plans using appropriate symbols

4.2 Recover obsolete materials and equipment, and return to appropriate point for disposal

4.3 Restore site according to requirements of enterprise or approving authority and to client satisfaction

4.4 Notify appropriate personnel of job completion and obtain sign off

Evidence of the ability to:

interpret and apply design plans and prepare for construction

install enclosures including pipe, pit and prefabricated manhole

construct in two different soil types: sand, rock, soil or combination soil types

shore an excavation site to meet enterprise and regulatory requirements

demonstrate use of specialised hand or power tools and equipment normally used for excavation, pipe, conduit installation and site restoration safely

complete the works and documentation

apply related work health and safety (WHS) requirements and work practices associated with excavation, enclosure installation and site restoration.

Note: If a specific volume or frequency is not stated, then evidence must be provided at least once.

To complete the unit requirements safely and effectively, the individual must:

describe the following elements of civil construction:

construction plant, tools and equipment operation

enclosure construction methods

foundations

plans

identify legislation, codes of practice and other formal agreements that impact on the work activity

identify the manufacturer’s requirements for safe operation of equipment

identify specific WHS requirements relating to the activity and site conditions

identify typical issues and challenges that occur on site.

Gather evidence to demonstrate consistent performance in conditions that are safe and replicate the workplace. Noise levels, production flow, interruptions and time variances must be typical of those experienced in the telecommunications – cabling field of work and include access to:

sites where enclosure construction may be conducted

construction equipment currently used in industry

relevant regulatory and equipment documentation that impacts on construction.

Assessors of this unit must satisfy the requirements for assessors in applicable vocational education and training legislation, frameworks and/or standards.

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Obtain construction design plan from appropriate personnel to scope work and arrange for site access 
Notify appropriate personnel of identified safety hazards and other services 
Obtain plant, tools and safety equipment to perform tasks safely and efficiently 
Determine type of underground enclosure specified in construction design plan required for project 
Use tools according to enterprise guidelines and work health and safety (WHS) regulations 
Place foundation of suitable material to provide safe and stable footing prior to installing underground enclosure in excavation 
Place recognised barrier over construction where enclosure is to be installed over power cables according to enterprise requirements or agreements with other authorities 
Install earth mat facility under enclosure where specified and required by enterprise 
Install enclosure specified in construction design plan to manufacturer’s specifications using specified materials 
Install conduit in trench to enterprise specifications 
Connect conduit to enclosure according to manufacturer’s specifications and industry practice 
Complete reports according to enterprise policy and record alterations to plans using appropriate symbols 
Recover obsolete materials and equipment, and return to appropriate point for disposal 
Restore site according to requirements of enterprise or approving authority and to client satisfaction 
Notify appropriate personnel of job completion and obtain sign off 

Forms

Assessment Cover Sheet

ICTCBL213 - Construct underground telecommunications infrastructure
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

ICTCBL213 - Construct underground telecommunications infrastructure

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: