Assessor Resource

ICTCBL238
Install, maintain and modify customer premises communications cabling: ACMA Lift Rule

Assessment tool

Version 1.0
Issue Date: April 2024


This unit describes the skills and knowledge required to safely install, maintain and modify communications cabling required on a customer's premises, according to Australian Communications and Media Authority (ACMA) Lift Cabling Provider Rule.

It applies to individuals who are qualified licensed electricians working in technical roles for lift installations on new or upgrade installations for an existing network or subsystem for convergence to next generation network (NGN) applications.

All customer cabling work in the telecommunications, fire, security and data industries must be performed by a registered cabler. All cablers are required to register with an ACMA accredited registrar.

You may want to include more information here about the target group and the purpose of the assessments (eg formative, summative, recognition)



Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

ELEMENT

PERFORMANCE CRITERIA

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1. Work within constraints imposed by customer premises and ACMA regulatory environment

1.1 Prepare for lift cabling work according to regulatory environment, cabling environment, cable type, cable identification, termination systems, earthing and protection, records and relevant legislation, codes, regulations and standards

1.2 Identify building infrastructure that places critical constraints on cabling when undertaking typical lift cabling installation from local distributor (LD) to lift car socket

1.3 Develop strategies to manage other infrastructure in relation to cabling

1.4 Notify appropriate personnel of identified safety hazards at cabling worksite

2. Manage remote power feed

2.1 Identify and avoid risks posed by contact with remote power feeding services when performing cabling activity

2.2 Make site safe by identifying remote power feeding services that operate at above telecommunications network voltage (TNV) inside customer premises

3. Install and modify cable support, earthing and termination infrastructure

3.1 Install fixings and cable support structures of adequate strength safely and align with environment according to manufacturer’s and customer’s specifications

3.2 Secure catenary supports to building structure and tension where necessary to ensure cable weight can be carried in operating conditions with interference and safety segregation maintained, including adherence to current Australian Standards

3.3 Install protective earthing of metal work to industry standards where required

3.4 Inspect installed support structure to ensure cable will not be exposed to damage during installation and general operation

3.5 Position terminating equipment and fixing to accepted industry codes of practice, current Australian Standards and customer requirements

3.6 Inspect control cubicles, travelling cable supports, junction boxes, line isolator units, backmount and outlet layout, to ensure compliance with manufacturer’s specifications, allow adequate work space for ease of access and avoid overlaying

3.7 Segregate incoming and outgoing cables to ensure ease of access, and avoid overlaying

4. Install cables and earth wires

4.1 Install lift communications cable from LD to lift car socket

4.2 Install cables according to manufacturer's application specifications, including tension and bending stress requirements

4.3 Identify and avoid sources of possible damage to cable, including hot pipes, sharp edges, cable burn, kinks and stretching

4.4 Allow sufficient excess at cable ends to facilitate termination

4.5 Place and secure cable to maintain safety and interference segregation according to legislative and industry standards

4.6 Install cable fasteners with correct tension to prevent cable sheath damage or transmission impairment, and trim flush to prevent risk of personal damage

4.7 Install aerial cables supported by catenaries in external environment to meet minimum above ground clearances and clearances from hazardous electrical services according to current Australian Standards

4.8 Install and secure travelling cables to maintain safety and according to relevant legislative, industry and manufacturer’s standards

4.9 Install local isolation units (LIU) as required according to current Australian Standards

4.10 Install over-voltage protection devices to all cable pairs, where required, to suppress voltage surges, with devices protectively earthed and according to current Australian Standards

4.11 Protect earth wire insulation against damage with protective earths segregated according to relevant industry and legislative standards

5. Terminate and test cables and earth wires

5.1 Remove cable sheath to allow for correct termination length and without damage to underlying conductors and their insulation

5.2 Install terminating modules according to manufacturer’s specifications, ensuring cable pairs are neatly and sequentially fanned for termination

5.3 Terminate conductors according to recommended colour code sequence using appropriate termination tools in manufacturer’s specified manner

5.4 Earth cable shield, if applicable, to manufacturer’s specifications and relevant industry codes of practice, including current Australian Standards

5.5 Undertake visual inspection to confirm termination colour code sequence has been followed, prior to end to end testing of wire and pair termination integrity

5.6 Terminate earth wires with connectors recommended by manufacturer according to relevant industry codes of practice, including current Australian Standards

5.7 Maintain earth wire continuity throughout to meet interface requirements with electrical systems

5.8 Test earthing installation for continuity, insulation resistance and conductive resistance according to relevant industry standards, including current Australian Standards

5.9 Confirm compatibility of alterations with existing systems and test new work both in isolation and when integrated with existing systems

6. Inspect cable route to ensure correct separations

6.1 Inspect separations along entire cable route and rectify separations that do not comply with regulations

6.2 Install barriers to achieve separations where sufficient spatial separation cannot be met

7. Evaluate earthing needs for cable systems on customer premises

7.1 Locate existing customer earthing systems and analyse earthing needs of cable systems

7.2 Calculate upper and lower limits of resistance for variety of cable system earths using relevant cable characteristics

8. Label earthing systems

8.1 Identify label requirements for all types of earthing systems

8.2 Attach label to earthing systems according to industry regulations

9. Create or update cable plans and records

9.1 Document installation details on record sheets and plans, and store according to customer requirements

9.2 Label cable pairs clearly to provide accurate identification according to manufacturer's, industry and customer standards

9.3 Record cabling details in cable pair record books to provide accurate record according to industry codes of practice and current Australian Standards

9.4 Complete Telecommunications Cabling Advice (TCA) form

10. Monitor work activity

10.1 Maintain close supervision of cablers not holding appropriate registration for task to ensure installation and maintenance activity is strictly according to legislative requirements and industry standards for safety and network integrity, including all current Australian Standards

Evidence of the ability to:

install a lift cabling system from local distributor (LD) via a traveling cable to a lift car socket, including accurate completion of installation records, drawing alterations and compliance forms

read and interpret cable drawings and plans for locations and terminations

apply cable conductor identification codes

conduct and interpret cable test results

interpret and apply related regulations and industry codes

comply with all related work health and safety (WHS) requirements and work practices.

Note: If a specific volume or frequency is not stated, then evidence must be provided at least once.

To complete the unit requirements safely and effectively, the individual must:

identify Australian Communications and Media Authority (ACMA) competency requirements for Telecommunications Cabling Provider Rules

describe the features and operating requirements of test equipment

describe the information required to operate equipment according to a test specification

identify legislation, codes of practice and other formal agreements that impact on the work activity

identify the manufacturer’s requirements for safe operation of equipment

explain protection earthing

describe the features of lift construction and the types of cables required

describe the types of cable used for manual controlled fire services

identify and describe cables and the types of cabling

identify and describe common distributors

outline specific WHS requirements relating to the activity and site conditions

identify typical issues and challenges that occur on site.

Gather evidence to demonstrate consistent performance in conditions that are safe and replicate the workplace. Noise levels, production flow, interruptions and time variances must be typical of those experienced in the telecommunications – cabling field of work and include access to:

a site on which lift communications cabling activities may be carried out

cabling and field equipment currently used in industry

licensing requirements and other site related documentation.

Note: All client cabling work in the telecommunications, fire, security and data industries must be performed by a registered cabler. All cablers are required to register with an Australian Communications and Media (ACMA) accredited registrar. Assessment by a Telecommunications Industry Training Advisory Board (TITAB) registered assessor is recommended for this unit.

Assessors of this unit must satisfy the requirements for assessors in applicable vocational education and training legislation, frameworks and/or standards.


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assingnment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

ELEMENT

PERFORMANCE CRITERIA

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1. Work within constraints imposed by customer premises and ACMA regulatory environment

1.1 Prepare for lift cabling work according to regulatory environment, cabling environment, cable type, cable identification, termination systems, earthing and protection, records and relevant legislation, codes, regulations and standards

1.2 Identify building infrastructure that places critical constraints on cabling when undertaking typical lift cabling installation from local distributor (LD) to lift car socket

1.3 Develop strategies to manage other infrastructure in relation to cabling

1.4 Notify appropriate personnel of identified safety hazards at cabling worksite

2. Manage remote power feed

2.1 Identify and avoid risks posed by contact with remote power feeding services when performing cabling activity

2.2 Make site safe by identifying remote power feeding services that operate at above telecommunications network voltage (TNV) inside customer premises

3. Install and modify cable support, earthing and termination infrastructure

3.1 Install fixings and cable support structures of adequate strength safely and align with environment according to manufacturer’s and customer’s specifications

3.2 Secure catenary supports to building structure and tension where necessary to ensure cable weight can be carried in operating conditions with interference and safety segregation maintained, including adherence to current Australian Standards

3.3 Install protective earthing of metal work to industry standards where required

3.4 Inspect installed support structure to ensure cable will not be exposed to damage during installation and general operation

3.5 Position terminating equipment and fixing to accepted industry codes of practice, current Australian Standards and customer requirements

3.6 Inspect control cubicles, travelling cable supports, junction boxes, line isolator units, backmount and outlet layout, to ensure compliance with manufacturer’s specifications, allow adequate work space for ease of access and avoid overlaying

3.7 Segregate incoming and outgoing cables to ensure ease of access, and avoid overlaying

4. Install cables and earth wires

4.1 Install lift communications cable from LD to lift car socket

4.2 Install cables according to manufacturer's application specifications, including tension and bending stress requirements

4.3 Identify and avoid sources of possible damage to cable, including hot pipes, sharp edges, cable burn, kinks and stretching

4.4 Allow sufficient excess at cable ends to facilitate termination

4.5 Place and secure cable to maintain safety and interference segregation according to legislative and industry standards

4.6 Install cable fasteners with correct tension to prevent cable sheath damage or transmission impairment, and trim flush to prevent risk of personal damage

4.7 Install aerial cables supported by catenaries in external environment to meet minimum above ground clearances and clearances from hazardous electrical services according to current Australian Standards

4.8 Install and secure travelling cables to maintain safety and according to relevant legislative, industry and manufacturer’s standards

4.9 Install local isolation units (LIU) as required according to current Australian Standards

4.10 Install over-voltage protection devices to all cable pairs, where required, to suppress voltage surges, with devices protectively earthed and according to current Australian Standards

4.11 Protect earth wire insulation against damage with protective earths segregated according to relevant industry and legislative standards

5. Terminate and test cables and earth wires

5.1 Remove cable sheath to allow for correct termination length and without damage to underlying conductors and their insulation

5.2 Install terminating modules according to manufacturer’s specifications, ensuring cable pairs are neatly and sequentially fanned for termination

5.3 Terminate conductors according to recommended colour code sequence using appropriate termination tools in manufacturer’s specified manner

5.4 Earth cable shield, if applicable, to manufacturer’s specifications and relevant industry codes of practice, including current Australian Standards

5.5 Undertake visual inspection to confirm termination colour code sequence has been followed, prior to end to end testing of wire and pair termination integrity

5.6 Terminate earth wires with connectors recommended by manufacturer according to relevant industry codes of practice, including current Australian Standards

5.7 Maintain earth wire continuity throughout to meet interface requirements with electrical systems

5.8 Test earthing installation for continuity, insulation resistance and conductive resistance according to relevant industry standards, including current Australian Standards

5.9 Confirm compatibility of alterations with existing systems and test new work both in isolation and when integrated with existing systems

6. Inspect cable route to ensure correct separations

6.1 Inspect separations along entire cable route and rectify separations that do not comply with regulations

6.2 Install barriers to achieve separations where sufficient spatial separation cannot be met

7. Evaluate earthing needs for cable systems on customer premises

7.1 Locate existing customer earthing systems and analyse earthing needs of cable systems

7.2 Calculate upper and lower limits of resistance for variety of cable system earths using relevant cable characteristics

8. Label earthing systems

8.1 Identify label requirements for all types of earthing systems

8.2 Attach label to earthing systems according to industry regulations

9. Create or update cable plans and records

9.1 Document installation details on record sheets and plans, and store according to customer requirements

9.2 Label cable pairs clearly to provide accurate identification according to manufacturer's, industry and customer standards

9.3 Record cabling details in cable pair record books to provide accurate record according to industry codes of practice and current Australian Standards

9.4 Complete Telecommunications Cabling Advice (TCA) form

10. Monitor work activity

10.1 Maintain close supervision of cablers not holding appropriate registration for task to ensure installation and maintenance activity is strictly according to legislative requirements and industry standards for safety and network integrity, including all current Australian Standards

Evidence of the ability to:

install a lift cabling system from local distributor (LD) via a traveling cable to a lift car socket, including accurate completion of installation records, drawing alterations and compliance forms

read and interpret cable drawings and plans for locations and terminations

apply cable conductor identification codes

conduct and interpret cable test results

interpret and apply related regulations and industry codes

comply with all related work health and safety (WHS) requirements and work practices.

Note: If a specific volume or frequency is not stated, then evidence must be provided at least once.

To complete the unit requirements safely and effectively, the individual must:

identify Australian Communications and Media Authority (ACMA) competency requirements for Telecommunications Cabling Provider Rules

describe the features and operating requirements of test equipment

describe the information required to operate equipment according to a test specification

identify legislation, codes of practice and other formal agreements that impact on the work activity

identify the manufacturer’s requirements for safe operation of equipment

explain protection earthing

describe the features of lift construction and the types of cables required

describe the types of cable used for manual controlled fire services

identify and describe cables and the types of cabling

identify and describe common distributors

outline specific WHS requirements relating to the activity and site conditions

identify typical issues and challenges that occur on site.

Gather evidence to demonstrate consistent performance in conditions that are safe and replicate the workplace. Noise levels, production flow, interruptions and time variances must be typical of those experienced in the telecommunications – cabling field of work and include access to:

a site on which lift communications cabling activities may be carried out

cabling and field equipment currently used in industry

licensing requirements and other site related documentation.

Note: All client cabling work in the telecommunications, fire, security and data industries must be performed by a registered cabler. All cablers are required to register with an Australian Communications and Media (ACMA) accredited registrar. Assessment by a Telecommunications Industry Training Advisory Board (TITAB) registered assessor is recommended for this unit.

Assessors of this unit must satisfy the requirements for assessors in applicable vocational education and training legislation, frameworks and/or standards.

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Prepare for lift cabling work according to regulatory environment, cabling environment, cable type, cable identification, termination systems, earthing and protection, records and relevant legislation, codes, regulations and standards 
Identify building infrastructure that places critical constraints on cabling when undertaking typical lift cabling installation from local distributor (LD) to lift car socket 
Develop strategies to manage other infrastructure in relation to cabling 
Notify appropriate personnel of identified safety hazards at cabling worksite 
Identify and avoid risks posed by contact with remote power feeding services when performing cabling activity 
Make site safe by identifying remote power feeding services that operate at above telecommunications network voltage (TNV) inside customer premises 
Install fixings and cable support structures of adequate strength safely and align with environment according to manufacturer’s and customer’s specifications 
Secure catenary supports to building structure and tension where necessary to ensure cable weight can be carried in operating conditions with interference and safety segregation maintained, including adherence to current Australian Standards 
Install protective earthing of metal work to industry standards where required 
Inspect installed support structure to ensure cable will not be exposed to damage during installation and general operation 
Position terminating equipment and fixing to accepted industry codes of practice, current Australian Standards and customer requirements 
Inspect control cubicles, travelling cable supports, junction boxes, line isolator units, backmount and outlet layout, to ensure compliance with manufacturer’s specifications, allow adequate work space for ease of access and avoid overlaying 
Segregate incoming and outgoing cables to ensure ease of access, and avoid overlaying 
Install lift communications cable from LD to lift car socket 
4.2 Install cables according to manufacturer's application specifications, including tension and bending stress requirements 
Identify and avoid sources of possible damage to cable, including hot pipes, sharp edges, cable burn, kinks and stretching 
Allow sufficient excess at cable ends to facilitate termination 
Place and secure cable to maintain safety and interference segregation according to legislative and industry standards 
Install cable fasteners with correct tension to prevent cable sheath damage or transmission impairment, and trim flush to prevent risk of personal damage 
Install aerial cables supported by catenaries in external environment to meet minimum above ground clearances and clearances from hazardous electrical services according to current Australian Standards 
Install and secure travelling cables to maintain safety and according to relevant legislative, industry and manufacturer’s standards 
Install local isolation units (LIU) as required according to current Australian Standards 
Install over-voltage protection devices to all cable pairs, where required, to suppress voltage surges, with devices protectively earthed and according to current Australian Standards 
Protect earth wire insulation against damage with protective earths segregated according to relevant industry and legislative standards 
Remove cable sheath to allow for correct termination length and without damage to underlying conductors and their insulation 
Install terminating modules according to manufacturer’s specifications, ensuring cable pairs are neatly and sequentially fanned for termination 
Terminate conductors according to recommended colour code sequence using appropriate termination tools in manufacturer’s specified manner 
Earth cable shield, if applicable, to manufacturer’s specifications and relevant industry codes of practice, including current Australian Standards 
Undertake visual inspection to confirm termination colour code sequence has been followed, prior to end to end testing of wire and pair termination integrity 
Terminate earth wires with connectors recommended by manufacturer according to relevant industry codes of practice, including current Australian Standards 
Maintain earth wire continuity throughout to meet interface requirements with electrical systems 
Test earthing installation for continuity, insulation resistance and conductive resistance according to relevant industry standards, including current Australian Standards 
Confirm compatibility of alterations with existing systems and test new work both in isolation and when integrated with existing systems 
Inspect separations along entire cable route and rectify separations that do not comply with regulations 
Install barriers to achieve separations where sufficient spatial separation cannot be met 
Locate existing customer earthing systems and analyse earthing needs of cable systems 
Calculate upper and lower limits of resistance for variety of cable system earths using relevant cable characteristics 
Identify label requirements for all types of earthing systems 
Attach label to earthing systems according to industry regulations 
Document installation details on record sheets and plans, and store according to customer requirements 
9.2 Label cable pairs clearly to provide accurate identification according to manufacturer's, industry and customer standards 
Record cabling details in cable pair record books to provide accurate record according to industry codes of practice and current Australian Standards 
Complete Telecommunications Cabling Advice (TCA) form 
Maintain close supervision of cablers not holding appropriate registration for task to ensure installation and maintenance activity is strictly according to legislative requirements and industry standards for safety and network integrity, including all current Australian Standards 

Forms

Assessment Cover Sheet

ICTCBL238 - Install, maintain and modify customer premises communications cabling: ACMA Lift Rule
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

ICTCBL238 - Install, maintain and modify customer premises communications cabling: ACMA Lift Rule

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: