Assessor Resource

ICTTCR301
Build a telecommunications radio structure

Assessment tool

Version 1.0
Issue Date: May 2024


This unit describes the skills and knowledge required to build a foundation, and assemble and mount a telecommunications radio structure.

It applies to individuals who have a dual specialist classification as rigger installers and who may install radio structures for Worldwide Interoperability for Microwave Access (WiMAX) wireless broadband access networks, antenna installation for radio and television broadcasting, and cellular mobile communications.

Work functions in the occupational areas where this unit may be used are subject to regulatory requirements. Refer to the ICT Implementation Guide Companion Volume or the relevant regulator for details of licensing, legislative or certification requirements.

You may want to include more information here about the target group and the purpose of the assessments (eg formative, summative, recognition)



Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

Elements

Performance Criteria

Elements describe the essential outcomes

Performance criteria describe the performance needed to demonstrate achievement of the element.

1. Prepare materials and secure site

1.1 Notify appropriate personnel and take necessary precautions to minimise, control or eliminate hazards that may exist during work activities

1.2 Determine nature and location of structure from construction design plans, relevant legislation, codes, regulations and standards

1.3 Determine materials, tools and equipment required from construction design plans

1.4 Check steel for assembly against construction design plans to ensure no parts are missing

1.5 Secure and clean site according to site security instructions for public safety

2. Construct foundations for radio structure

2.1 Locate other services according to industry practice, and arrange for relocation of services if required

2.2 Oversee excavation of foundation according to engineering specifications, and construction of foundations according to construction design plans

2.3 Install earthing according to construction design plans, enterprise work health and safety (WHS) guidelines and industry practice

2.4 Provide samples of concrete for analysis according to enterprise guidelines and manufacturer’s specifications, relevant standards and regulations

3. Assemble and mount telecommunications radio structure

3.1 Select area free of interference and close to construction site suitable for structure assembly

3.2 Assemble radio structure in sections on ground according to engineering specifications, using personal protective equipment and following safety guidelines

3.3 Mount and secure preassembled sections to tower construction according to plans, specifications and enterprise WHS guidelines

3.4 Maintain vertical positioning of structure within twist tolerances during construction phase

3.5 Secure and tension guy wires according to construction design plans, enterprise WHS guidelines and industry practice

4. Complete administrative duties

4.1 Update original design plan with approved amendments and return to design section

4.2 Secure and clean up site to original condition in environmentally safe manner

4.3 Notify client and obtain sign off

Evidence of the ability to:

undertake pre-construction checks to ensure a safe working environment

construct foundations according to engineering specifications

select site for hoisting equipment, ensuring location is safe for the operator and the construction

preassemble the structure at ground level, ensuring completion of each assembled component

assemble and mount a telecommunications radio structure, including temporary and permanent guy anchors

install functional and protective earthing systems, following security and safety procedures.

Note: If a specific volume or frequency is not stated, then evidence must be provided at least once.

To complete the unit requirements safely and effectively, the individual must:

summarise the impact that weather conditions impose on the constructions and installation of telecommunications structures

describe the safety risks associated with the installation of telecommunications equipment in remote areas including:

hypothermia symptoms and methods of prevention and treatment

electromagnetic radiation (EMR) safety practices

personal protective equipment for rigging projects

working-at-heights safety practices

discuss the features and operating requirements of:

construction equipment

rigging equipment

identify the information required to build a telecommunications radio structure

describe rigging practices and systems for telecommunications radio structures

list legislation, codes of practice and other formal agreements that impact on the work activity

summarise licensing and regulatory issues applying to rigging practices and systems on telecommunications radio structures

describe manufacturer’s requirements for safe operation of equipment

discuss the following work health and safety (WHS) requirements:

WHS legislation and regulations

company procedures relating to the activity and site conditions

discuss typical issues and challenges that can occur on an installation site.

Gather evidence to demonstrate consistent performance in conditions that are safe and replicate the workplace. Noise levels, production flow, interruptions and time variances must be typical of those experienced in the telecommunications ‒ telecommunications rigging installation field of work and include access to special purpose tools, equipment and materials.

Assessors of this unit must satisfy the requirements for assessors in applicable vocational education and training legislation, frameworks and/or standards.


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assingnment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

Elements

Performance Criteria

Elements describe the essential outcomes

Performance criteria describe the performance needed to demonstrate achievement of the element.

1. Prepare materials and secure site

1.1 Notify appropriate personnel and take necessary precautions to minimise, control or eliminate hazards that may exist during work activities

1.2 Determine nature and location of structure from construction design plans, relevant legislation, codes, regulations and standards

1.3 Determine materials, tools and equipment required from construction design plans

1.4 Check steel for assembly against construction design plans to ensure no parts are missing

1.5 Secure and clean site according to site security instructions for public safety

2. Construct foundations for radio structure

2.1 Locate other services according to industry practice, and arrange for relocation of services if required

2.2 Oversee excavation of foundation according to engineering specifications, and construction of foundations according to construction design plans

2.3 Install earthing according to construction design plans, enterprise work health and safety (WHS) guidelines and industry practice

2.4 Provide samples of concrete for analysis according to enterprise guidelines and manufacturer’s specifications, relevant standards and regulations

3. Assemble and mount telecommunications radio structure

3.1 Select area free of interference and close to construction site suitable for structure assembly

3.2 Assemble radio structure in sections on ground according to engineering specifications, using personal protective equipment and following safety guidelines

3.3 Mount and secure preassembled sections to tower construction according to plans, specifications and enterprise WHS guidelines

3.4 Maintain vertical positioning of structure within twist tolerances during construction phase

3.5 Secure and tension guy wires according to construction design plans, enterprise WHS guidelines and industry practice

4. Complete administrative duties

4.1 Update original design plan with approved amendments and return to design section

4.2 Secure and clean up site to original condition in environmentally safe manner

4.3 Notify client and obtain sign off

Evidence of the ability to:

undertake pre-construction checks to ensure a safe working environment

construct foundations according to engineering specifications

select site for hoisting equipment, ensuring location is safe for the operator and the construction

preassemble the structure at ground level, ensuring completion of each assembled component

assemble and mount a telecommunications radio structure, including temporary and permanent guy anchors

install functional and protective earthing systems, following security and safety procedures.

Note: If a specific volume or frequency is not stated, then evidence must be provided at least once.

To complete the unit requirements safely and effectively, the individual must:

summarise the impact that weather conditions impose on the constructions and installation of telecommunications structures

describe the safety risks associated with the installation of telecommunications equipment in remote areas including:

hypothermia symptoms and methods of prevention and treatment

electromagnetic radiation (EMR) safety practices

personal protective equipment for rigging projects

working-at-heights safety practices

discuss the features and operating requirements of:

construction equipment

rigging equipment

identify the information required to build a telecommunications radio structure

describe rigging practices and systems for telecommunications radio structures

list legislation, codes of practice and other formal agreements that impact on the work activity

summarise licensing and regulatory issues applying to rigging practices and systems on telecommunications radio structures

describe manufacturer’s requirements for safe operation of equipment

discuss the following work health and safety (WHS) requirements:

WHS legislation and regulations

company procedures relating to the activity and site conditions

discuss typical issues and challenges that can occur on an installation site.

Gather evidence to demonstrate consistent performance in conditions that are safe and replicate the workplace. Noise levels, production flow, interruptions and time variances must be typical of those experienced in the telecommunications ‒ telecommunications rigging installation field of work and include access to special purpose tools, equipment and materials.

Assessors of this unit must satisfy the requirements for assessors in applicable vocational education and training legislation, frameworks and/or standards.

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Notify appropriate personnel and take necessary precautions to minimise, control or eliminate hazards that may exist during work activities 
Determine nature and location of structure from construction design plans, relevant legislation, codes, regulations and standards 
Determine materials, tools and equipment required from construction design plans 
Check steel for assembly against construction design plans to ensure no parts are missing 
Secure and clean site according to site security instructions for public safety 
Locate other services according to industry practice, and arrange for relocation of services if required 
Oversee excavation of foundation according to engineering specifications, and construction of foundations according to construction design plans 
Install earthing according to construction design plans, enterprise work health and safety (WHS) guidelines and industry practice 
Provide samples of concrete for analysis according to enterprise guidelines and manufacturer’s specifications, relevant standards and regulations 
Select area free of interference and close to construction site suitable for structure assembly 
Assemble radio structure in sections on ground according to engineering specifications, using personal protective equipment and following safety guidelines 
Mount and secure preassembled sections to tower construction according to plans, specifications and enterprise WHS guidelines 
Maintain vertical positioning of structure within twist tolerances during construction phase 
Secure and tension guy wires according to construction design plans, enterprise WHS guidelines and industry practice 
Update original design plan with approved amendments and return to design section 
Secure and clean up site to original condition in environmentally safe manner 
Notify client and obtain sign off 

Forms

Assessment Cover Sheet

ICTTCR301 - Build a telecommunications radio structure
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

ICTTCR301 - Build a telecommunications radio structure

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature: