List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.
ELEMENT | PERFORMANCE CRITERIA |
Elements describe the essential outcomes. | Performance criteria describe the performance needed to demonstrate achievement of the element. |
1. Prepare to commission electronic unit | 1.1 Prepare for work following work health and safety (WHS) requirements 1.2 Organise resources based on existing and potential site hazards 1.3 Notify customer or network operations personnel to gain site access and network specifications 1.4 Determine the type and complexity of electronic unit from specifications 1.5 Verify installed electronic unit and associated cabling conform to specifications 1.6 Establish commissioning dates and confirm with all parties 1.7 Determine commissioning parameters according to specification, and establish planned outage if required 1.8 Obtain test equipment and check suitability and calibration status 1.9 Produce a preliminary commissioning plan according to manufacturer's instructions and enterprise guidelines for discussion with customer 1.10 Inform affected customers of impending action and likely timing and impact of the work |
2. Organise planned outages | 2.1 Negotiate outage times with appropriate groups and affected customers to minimise disruptions 2.2 Refer to contingency plans and arrange for emergency communications if required 2.3 Notify alarm management centre of planned action 2.4 Obtain authority to proceed from relevant control centre and notify customers affected by the outage |
3. Perform commissioning procedures | 3.1 Program equipment or install software according to manufacturer's specifications 3.2 Set electronic unit parameters according to manufacturer’s specifications and customer requirements 3.3 Set up test equipment and conduct tests according to manufacturer’s specifications and industry practice 3.4 Connect and test network access facilities for correct performance 3.5 Conduct cut over according to project design and industry practice in consultation with appropriate personnel 3.6 Check remote alarm and monitoring features are functional, if applicable |
4. Finalise commissioning documentation | 4.1 Update relevant databases according to enterprise and network guidelines 4.2 Notify appropriate personnel of commissioning results and work completion 4.3 Complete administrative tasks according to industry practice and enterprise guidelines |
Evidence of ability to:
commission an electronic unit according to specifications
communicate effectively with stakeholders
negotiate arrangements for commissioning
deal with faults and problems and provide solutions.
Note: If a specific volume or frequency is not stated, then evidence must be provided at least once.
To complete the unit requirements safely and effectively, the individual must:
explain electrical and/or optical properties to be measured
identify common networking equipment
outline legislation and licensing requirements surrounding installation of telecommunications equipment
summarise network operation procedures
explain power requirements and electrical safety
describe test equipment types
outline transmission type and signals that may be encountered.
Gather evidence to demonstrate consistent performance in conditions that are safe and replicate the workplace. Noise levels, production flow, interruptions and time variances should be typical of those experienced in the telecommunications networks engineering field of work and include access to:
sites on which installation and commissioning procedures can be conducted
relevant regulatory and equipment documentation that impact commissioning
testing equipment currently used in industry.
Assessors of this unit must satisfy the requirements for assessors in applicable vocational education and training legislation, frameworks and/or standards.