• MSACMT421A - Facilitate a Just in Time (JIT) system

Assessor Resource

MSACMT421A
Facilitate a Just in Time (JIT) system

Assessment tool

Version 1.0
Issue Date: April 2024


In a typical scenario, the person will need to monitor the operation of the JIT system and facilitate its working. This will involve liaison with stakeholders as well as examining the data generated. They will need to be alert to potential problems and areas for improvement.

This unit requires the application of skills associated with gathering, analysing and communicating information to facilitate implementation of the JIT system. It requires planning and organising skills and has a strong emphasis on communication and teamwork skills to ensure the JIT system is being effectively implemented. This unit also requires an ability to problem solve and take the initiative to consider performance issues and learn from experience to improve future performance.

This unit covers knowledge and skills required to facilitate the implementation/operation of a Just in Time (JIT)/kanban system in the organisation.

You may want to include more information here about the target group and the purpose of the assessments (eg formative, summative, recognition)

Employability Skills

This unit contains employability skills




Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

The Evidence Guide provides advice on assessment and must be read in conjunction with the Performance Criteria, required skills and knowledge, the Range Statement and the Assessment Guidelines for this Training Package.

Overview of assessment requirements

The person will at all times know the state of the JIT system in their area and will take actions to ensure its smooth operation on a day to day basis as well as recommend/undertake actions to improve it long term.

What critical aspects of evidence are required to demonstrate competency in this unit?

Evidence should be available of the person's facilitation of the operation of the JIT system and their making of recommendations for/making improvements

In what context should assessment occur?

This unit will need to be assessed in an organisation operating JIT.

Are there any other units which could or should be assessed with this unit or which relate directly to this unit?

This unit is related to:

MSACMT221A Apply Just in Time (JIT) procedures, and

MSACMT621A Develop a Just in Time (JIT) system which cover the lower and higher skill levels in CMI respectively.

What method of assessment should apply?

Assessors must be satisfied that the person can consistently perform the unit as a whole, as defined by the elements, performance criteria, skills and knowledge. A holistic approach should be taken to the assessment.

Assessors should gather sufficient, fair, valid, reliable, authentic and current evidence from a range of sources. Sources of evidence may include direct observation, reports from supervisors, peers and colleagues, project work, samples, organisation records and questioning. Assessment should not require language, literacy or numeracy skills beyond those required for the unit.

The assessee will have access to all techniques, procedures, information, resources and aids which would normally be available in the workplace.

The method of assessment should be discussed and agreed with the assessee prior to the commencement of the assessment.

What evidence is required for demonstration of consistent performance?

Evidence should be gathered from an extended period showing routine support for the JIT system and regular improvements made/suggested.

What are the specific resource requirements for this unit?

Access to an organisation using JIT.


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assingnment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

Required skills:

reading

recording

communicating

planning

analysing

problem solving

negotiating.

Required knowledge:

JIT principles relevant to jobs

procedures for making/recommending improvements

reasons for delays/storages/inventories in that section of the value chain under their control and methods of reducing/eliminating them

skill gap analysis and methods of filling skill gaps

principles of the manufacturing process relevant to the section/team

production data generated by the process and its application to JIT.

The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Just in time (JIT)

Just in time (JIT) is a production scheduling concept that calls for any item needed at a production operation - whether raw material, finished item, or anything in between, to be produced and available precisely when needed, neither a moment earlier nor a moment later.

Kanban

Kanban is a card or sheet used to authorise production or movement of an item; when fully implemented, kanban (the plural is the same as the singular) operates according to the following rules:

all production and movement of parts and material take place only as required by a downstream operation, i.e. all manufacturing and procurement are ultimately driven by the requirements of final assembly or the equivalent

the specific tool which authorizes production or movement is called a kanban. The word literally means card or sign, but it can legitimately refer to a container or other authorizing device. Kanban have various formats and content as appropriate for their usage (e.g. a kanban for a vendor is different than a kanban for an internal machining operation).

Kanban is typically applied to batch type operation and the production is measured in units produced. In continuous manufacturing organisations, production is measured in terms of production rate (e.g. kg/h, tonne/day) and rate is increased/decreased according to the flow authorisation which may be a kanban (e.g. ticket, order from a supplier) or may be a SCADA signal from a remote facility (e.g. customer tank) saying that resupply is required or similar.

SCADA

System Control and Data Acquisition (SCADA) is a general term applied to a number of systems which automatically collect critical process data, perform required mathematical manipulations on it and then make control decisions and/or give required information personnel for action.

Key measures

Key measures may include inventory levels, lead time, IFOTIS delivery, productivity/production rate, other measures of pull through the value chain, quality.

IFOTIS refers to delivery of product In Full, On Time and In Specification.

Quick fix

Quick fix is action taken to immediately and cheaply control a problem, prevent it getting worse and/or ameliorate its impact, but which does not necessarily solve it long term.

Pull system

Pull is a system of making to demand rather than for stock or to a forecast.

Value chain

Competitive manufacturing organisations encompass the entire production system, beginning with the customer, and includes the product sales outlet, the final assembler, product design, raw material mining and processing and all tiers of the value chain (sometimes called the supply chain). Any truly 'competitive' system is highly dependent on the demands of its customers and the reliability of its suppliers. No implementation of competitive manufacturing can reach its full potential without including the entire 'enterprise' in its planning .

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Track value of key measures 
Recognise indicators of poor performance 
Take appropriate quick fix action 
Regularly communicate with team members regarding the operation of the JIT system 
Review JIT performance indicators with team members 
Communicate with relevant personnel up and down the value chain regarding the operation of the JIT system 
Identify issues with stakeholders and take appropriate quick fix action 
Identify areas requiring improvement in the JIT system 
Review value of key measures 
Recognise skill gaps in team members and other stakeholders 
Determine any other issues in team members, other stakeholders and JIT system leading to poor performance indicators 
Develop appropriate improvement solutions 
Liaise with relevant people regarding these solutions 
Implement/assist with the implementation of the solutions 

Forms

Assessment Cover Sheet

MSACMT421A - Facilitate a Just in Time (JIT) system
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

MSACMT421A - Facilitate a Just in Time (JIT) system

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent