In a typical scenario, an organisation is selecting or reviewing its proactive maintenance strategy. While technical factors are significant in the choice of maintenance strategy and tools, cost factors will also impact on the selection of a maintenance strategy. This unit covers the cost analysis of maintenance strategies and complements the technical analysis covered in MSACMT681A Develop a proactive maintenance strategy. The technical analysis may be performed by the same or a different person to the person undertaking the cost analysis.

This unit primarily requires the application of skills associated with communication in gathering, analysing and applying costing information and consulting with maintenance personnel. Problem solving, initiative and enterprise, and planning and organising are required to analyse and estimate the cost of maintenance strategies.

This unit covers the knowledge and skills needed to analyse the cost implications of different maintenance strategies and to adjust adopt the strategy to minimise or eliminate unnecessary costs.

You may want to include more information here about the target group and the purpose of the assessments (eg formative, summative, recognition)

Employability Skills

This unit contains employability skills.




Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

The Evidence Guide describes the underpinning knowledge and skills that must be demonstrated to prove competence. it is essential for assessment and must be read in conjunction with the performance criteria, the range statement and the assessment guidelines of the relevant training package

Overview of assessment requirements

The person will analyse and determine cost components for maintenance strategies. The strategies implemented will be cost effective.

What are the specific resource requirements for this unit?

Access to a workplace implementing competitive manufacturing strategies. No other specific resources are required.

In what context should assessment occur?

Assessment will need to occur in a workplace.

Are there any other units which could or should be assessed with this unit or which relate directly to this unit?

This unit may be assessed concurrently with appropriate units.

What method of assessment should apply?

Assessors must be satisfied that the person can consistently perform the unit as a whole, as defined by the Elements, Performance Criteria, skills and knowledge. A holistic approach should be taken to the assessment.

Assessors should gather sufficient, fair, valid, reliable, authentic and current evidence from a range of sources. Sources of evidence may include direct observation, reports from supervisors, peers and colleagues, project work, samples, organisation records and questioning. Assessment should not require language, literacy or numeracy skills beyond those required for the unit.

The assessee will have access to all techniques, procedures, information, resources and aids which would normally be available in the workplace.

The method of assessment should be discussed and agreed with the assessee prior to the commencement of the assessment.

What evidence is required for demonstration of consistent performance?

Evidence from a single optimisation may be adequate, although generally analyses of a few products with different cost structures or customer benefit structures would be required.


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assingnment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

Required skills

calculation

analysis

problem solving

Required knowledge

cost components of maintenance

interrelationship of cost components and maintenance activities

The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Maintenance strategies and techniques may include:

Total Productive Maintenance (TPM)

Reliability Centred Maintenance (RCM)

Root Cause Analysis (RCA)

Mean Time Between Failures (MBTF)

Failure Mode and Effects Analysis (FMEA)

Condition monitoring

Total Preventative Maintenance/Total Productive Maintenance (TPM) is an application of total quality management to maintenance with the intention of increasing reliability, getting it right first time and increasing OEE.

Reliability Centred Maintenance (RCM) moves maintenance from reactive, or even planned/programmed towards a focus on uptime and OEE

RCA There are many possible causes of any problem. Eliminating some will have no impact, others will ameliorate the problem. However elimination of the root cause will eliminate the problem. There should only be one root cause for any problem and so the analysis should continue until this one cause is found. Elimination of the root cause permanently eliminates the problem.

Uptime refers to the overall availability of the plant - it is the inverse of downtime - or the unavailability of the plant. Ideal uptime is 100%.

Overall equipment efficiency (OEE) is the combination of the main factors causing loss of productive capacity from equipment/plant and is:

OEE = availability x performance x quality rate

where:

availability takes into account losses due to breakdown, set up and adjustments

performance takes into account losses due to minor stoppages, reduced speed and idling

quality rate takes into account losses due to rejects, re-works and start up waste.

Mean time between failure (MBTF) is one key measure of the effectiveness of a maintenance procedure, and is an indicator as to whether root causes are being found and resolved. If MBTF is reducing, then it is an indicator that the maintenance regime is failing.

Failure Mode and Effects Analysis (FMEA) is a systematic approach that identifies potential failure modes in a system, product, or manufacturing/assembly operation caused by either design or manufacturing/assembly process deficiencies. It also identifies critical or significant design or process characteristics that require special controls to prevent or detect failure modes. FMEA is a tool used to prevent problems from occurring.

Some industry sectors have highly adapted forms of FMEA and may practice traditional FMEA in say their routine maintenance while using another technique (such as HAZOP) for design and modification.

Hazard and Operability Studies (HAZOP) is a form of FMEA which has been practiced by the process industries for over 30 years and examines the implications of changes in process conditions to process stability.

Condition monitoring involves often quite sophisticated monitoring of equipment including such things as vibration monitoring, instrumental analysis of lubricating oil etc to determine the current state of the equipment, monitor the change in this condition and predict when it needs servicing/maintenance to maintain reliability.

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Determine cost of failure of plant/equipment 
Determine cost of a planned shut down, maintain, start up activity 
Determine cost of maintenance activity for a planned activity 
Determine cost of maintenance activity for an unplanned activity 
Determine costs of condition monitoring 
Identify cost implications for maintenance strategy 
Determine initial capital cost 
Estimate servicing, maintenance and repair costs 
Estimate production and other costs associated with service, maintenance and repair 
Determine depreciation and other applicable allowances 
Estimate ancillary costs such as training, commissioning, productivity loss 
Estimate technological life and costs of changing to current technology/costs of retaining obsolete equipment 
Estimate annualised costs in present value terms. 
Identify life cycle cost implications for strategy. 
Identify cost implications for different strategies 
Negotiate a strategy which minimises total costs 
Monitor the implementation of the strategy to ensure the costs are minimised 
Make required adjustments 

Forms

Assessment Cover Sheet

MSACMT632A - Analyse cost implications of maintenance strategy
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

MSACMT632A - Analyse cost implications of maintenance strategy

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: