Assessor Resource

RIICPL303A
Install sewer pipelines

Assessment tool

Version 1.0
Issue Date: April 2024


This unit is appropriate for those working in an operational role at worksites within:

Civil construction

This unit covers the installation of sewer pipelines in the civil construction industry. It includes planning and preparing, setting out and excavating, installing sewer pipeline, testing sewer pipeline, and cleaning up. Licensing, legislative, regulatory and certification requirements that apply to this unit can vary between states, territories, and industry sectors. Relevant information must be sourced prior to application of the unit.

You may want to include more information here about the target group and the purpose of the assessments (eg formative, summative, recognition)

Prerequisites

Not applicable.


Co-Requisites

Not applicable.


Employability Skills

This unit contains employability skills.




Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.

Overview of assessment

Critical aspects for assessment and evidence required to demonstrate competency in this unit

The evidence required to demonstrate competency in this unit must be relevant to worksite operations and satisfy all of the requirements of the performance criteria, required skills and knowledge and the range statement of this unit and include evidence of the following:

knowledge of the requirements, procedures and instructions for installing sewer pipelines

implementation of requirements, procedures and techniques for the safe, effective and efficient completion of installation of sewer pipelines

working with others to undertake and complete the installation of sewer pipelines that meets all of the required outcomes

consistent timely completion of installation of sewer pipelines that safely, effectively and efficiently meets the required outcomes

Context of and specific resources for assessment

This unit must be assessed in the context of the work environment. Where personal safety or environmental damage are limiting factors, assessment may occur in a simulated environment provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills.

Assessment of this competency requires typical resources normally used in a resources and infrastructure sector environment. Selection and use of resources for particular worksites may differ due to the site circumstances.

The assessment environment should not disadvantage the participant. For example, language, literacy and numeracy demands of assessment should not be greater than those required on the job.

Customisation of assessment and delivery environment to sensitively accommodate cultural diversity.

Aboriginal people and other people from a non English speaking background may have second language issues.

Where applicable, physical resources should include equipment modified for people with disabilities. Access must be provided to appropriate learning and/or assessment support when required.

Method of assessment

This unit may be assessed in a holistic way with other units of competency. The assessment strategy for this unit must verify required knowledge and skill and practical application using more than one of the following assessment methods:

written and/or oral assessment of the candidate's required knowledge

observed, documented and/or first hand testimonial evidence of the candidate's:

implementation of appropriate requirement, procedures and techniques for the safe, effective and efficient achievement of required outcomes

consistent achievement of required outcomes

first hand testimonial evidence of the candidate's:

working with others to undertake and complete the installation of sewer pipelines

Guidance information for assessment

Consult the SkillsDMC User Guide for further information on assessment including access and equity issues.


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assingnment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

Required skills

Specific skills are required to achieve the Performance Criteria of this unit, particularly for its application in the various circumstances in which this unit may be used. This includes the ability to carry out the following, as required to install sewer pipelines:

apply legislative, organisation and site requirements and procedures for installation of sewer pipelines

organise work activities

select and use relevant tools and equipment safely

identify and report on hazards related to the worksite and work activity

communicate effectively to receive and clarify work instructions

Required knowledge

Specific knowledge is required to achieve the Performance Criteria of this unit, particularly for its application in the various circumstances in which this unit may be used. This includes knowledge of the following, as required to install sewer pipelines:

site and equipment safety requirements

sewer pipelines and installation procedures

civil construction terminology

processes for the calculation of pipeline grades and percentages

sedimentation and erosion control

excavation/trench safety

confined space entry requirements

dewatering

concrete and concrete fabrication

processes for interpreting engineering drawings

equipment types, characteristics, technical capabilities and limitations

operational, maintenance and basic diagnostic procedures including testing procedures

valves and flow control devices

site isolation and traffic control responsibilities and authorities

materials safety data sheets and materials handling methods

project quality requirements

JSAs/safe work method statement

The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Relevant compliance documentation may include:

legislative, organisational and site requirements and procedures

manufacturer's guidelines and specifications

Australian standards

Employment and workplace relations legislation

Equal Employment Opportunity and Disability Discrimination legislation

Safety requirements include:

OHS requirements in accordance with state or territory legislation and regulations, organisational safety policies and procedures, and project safety plan including: protective clothing and equipment, use of tools and equipment, workplace environment and safety, handling of materials, use of fire fighting equipment, use of First Aid equipment, hazard control, and hazardous materials and substances

safe operating procedures including recognising and preventing hazards associated with underground services, other machines, personnel, restricted access barriers, traffic control, working in proximity to others, worksite visitors and the public

recognising hazards and risks including uneven/unstable terrain, trees, underground services, buildings, excavations, traffic, embankments, cuttings, structures and hazardous materials

safe parking practices including ensuring access ways are clear, equipment/machinery is away from overhangs and refuelling sites, safe distance from excavations, and secured from unauthorised access or movement

emergency procedures including emergency shutdown and stopping, extinguishing equipment fires, organisational First Aid requirements and evacuation

Signage for traffic control may include:

escort vehicles

highway traffic signs

site safety signage

temporary signage for the benefit of motorists and pedestrians

barricades

traffic conditions signage

Traffic conditions may include:

congested urban environments

low traffic rural areas

off-road un-trafficked areas

buildings

parking sites

pedestrian areas

Tools and equipment may include:

levelling equipment

shovels

lifting equipment

crow bars

hammers

grinders

jointing equipment

oxy-acetylene equipment

scaffolding

saws

Environmental protection requirements may include:

organisational/project environmental management plan

waste management

water quality protection

noise

vibration

dust and clean-up management

Materials may include:

pipes

concrete

backfill

bedding materials

Installation procedures may include:

selecting size, type and material of pipe

bedding down pipes

positioning pipes

checking alignment, level and grade

repair work

Pipe may include:

DICL

UPVC

clay

Sewer pipeline are to include:

only in-ground

Bedding may include:

Aggregate

sand

Join may include:

rubber ring

solvent welded

arc welded

mechanical joint

Valves, fittings and flow control devices may include:

stop valves

non return valves

flow control valves

air release valves

waste and leak detection meters

Test procedures may include:

visual straightness

ovality

tolerance

air

water

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Access, interpret and apply compliance documentation relevant to the work activity 
Obtain safety requirements from the site safety plan 
Identify, obtain and implement signage requirements from the project traffic management plan 
Select plant, tools and equipment to carry out tasks consistent with the requirements of the job, check for serviceability and rectify or report any faults 
Identify, confirm and apply environmental protection requirements from the project environmental management plan 
Prepare work area and materials to support the efficient installation of the pipe work 
Determine and apply dewatering requirements 
Determine location, alignment direction, level and grade of sewer pipeline from job drawings/specifications 
Set out works to specification 
Advise plant operator of excavation requirements and monitor levels 
Install sewer pipeline bedding in accordance with plans, specifications and standards 
Lower pipes and place in position to design specifications 
Join pipes in accordance with manufacturer's specifications 
Place pipes and fit valves, fittings and flow control devices in accordance with drawings and specifications 
Check alignment level and grade continuously for conformance with design plans and specifications 
Position side support and/or overlay beside the pipes 
Check sewer pipeline system support structure 
Monitor backfill procedure to ensure work is completed to specification, where required 
Construct manholes, inspection and valve chambers, minor structures and thrust blocks 
Perform test to relevant authority requirements as determined by the specifications 
Perform sewer system test procedures establishing functionality and serviceability 
Record and report test results 
Clear work area and dispose of or recycle materials in accordance with project environmental management plan 
Clean, check, maintain and store plant, tools and equipment 

Forms

Assessment Cover Sheet

RIICPL303A - Install sewer pipelines
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

RIICPL303A - Install sewer pipelines

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: