This unit involves the skills and knowledge required to coordinate construction, laying and testing of gas distribution pipelines and associated equipment.

It includes notifying other services, communicating with appropriate person/s, ensuring the correct materials, tools and equipment are used and completing relevant documentation.

No licensing, legislative or certification requirements apply to this unit at the time of publication.

You may want to include more information here about the target group and the purpose of the assessments (eg formative, summative, recognition)

Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assingnment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

Range is restricted to essential operating conditions and any other variables essential to the work environment.

Non-essential conditions may be found in the UEG Gas Industry Training Package Companion Volume Implementation Guide.

tools and equipment must include at least three (3) of the following:

excavation

trenching

shoring

stitch bore

horizontal drilling

directional drilling

pipe connections must include at least four (4) of the following: :

nylon (polymide) pipeline laying techniques

nylon gluing

connection of nylon to other materials

nylon stop off

unplasticised polyvinyl chloride (uPVC) pipeline laying techniques

uPVC solvent cemented joints

uPVC moulded joints

uPVC stop off

uPVC couplings or flanges

connection of uPVC to other material

procedures must include at least five (5) of the following:

polyethylene (PE) pipeline laying techniques

large diameter PE

PE electro fusion

PE butt fusion

saddle fusion

socket fusion

PE stop off

compression couplings or flanges

connection of PE to other materials

practical application of installation and maintenance of plastic pipe systems

procedures must include at least two (2) of the following:

steel pipeline coating repair

steel pipeline coating testing (jeeper)

steel, field joint coating

procedures must include at least three (3) of the following:

connection of PE to steel mains

steel mains welding

steel mains repair

sleeve application

clamp application

hot tap and stopple

isolation methods must include at least two (2) of the following:

high pressure stop off

bagtube

squash off jacks

squash off pliers

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Location of services are verified and alignment of gas main and associated equipment are confirmed, as necessary, by site inspection in accordance with work schedule and workplace procedures 
 
 
 
 
 
 
 
 
 
 
WHS/OHS and environment risk control measures, schedule of work and workplace procedures for carrying out work are followed 
 
 
 
 
 
Final inspections of work are undertaken, checked against work schedule for conformance and anomalies reported in accordance with workplace procedures 
 
 
 
 
 

Forms

Assessment Cover Sheet

UEGNSG207 - Coordinate construction, laying and testing of gas distribution pipelines
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

UEGNSG207 - Coordinate construction, laying and testing of gas distribution pipelines

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: