Assessor Resource

UETTDRDS55A
Design power system transmission and sub-transmission substation earthing

Assessment tool

Version 1.0
Issue Date: April 2024


2)

This competency standard Unit is intended to augment formally acquired competencies. It is suitable for employment-based programs under an approved contract of training.

1)Scope:

1.1) Descriptor

This Competency Standard Unit covers the design of transmission and sub-transmission zone substation earthing. This may include earth resistivity tests coordination, design of the earth grid, electrodes, grid connections, equipment connections and remote earthing connections to conduct maximum earth fault currents without exceeding the maximum allowable earth potential rise. The design does include earthing engineering aspects and must conform to safety regulations and environmental standards and incorporate the principles of safe design. However, it excludes the certification of earthing design.

You may want to include more information here about the target group and the purpose of the assessments (eg formative, summative, recognition)

Prerequisites

Prerequisite Unit(s)

4)

Competencies

4.1)

Granting of competency in this unit shall be made only after competency in the following unit(s) has/have been confirmed.

Where pre-requisite pathways have been identified. All competencies in the Common Unit Group must be have been completed plus all the competencies in one (1) of the identified Pathway Unit Group(s):

Common Unit Group

Unit Code

Unit Title

UEENEEE101A

Apply Occupational Health and Safety regulations, codes and practices in the workplace

UEENEEE104A

Solve problems in d.c. Circuits

UEENEEE107A

Use drawings, diagrams, schedules, standards, codes and specifications

UEENEEG101A

Solve problems in electromagnetic devices and related circuits

UEENEEG102A

Solve problems in electromagnetic devices and related circuits

UETTDRDS39A

Prepare and manage detailed construction plans for electrical power system infrastructure

UETTDRDS44A

Design power system substations modifications

UETTDREL11A

Apply sustainable energy and environmental procedures

UETTDREL16A

Working safely near live electrical apparatus

UETTDRIS62A

Implement and monitor the power system organisational OHS policies, procedures and programs

UETTDRIS63A

Implement and monitor the power system environmental and sustainable energy management policies and procedures

Literacy and numeracy skills

4.2)

Participants are best equipped to achieve this unit if they have reading, writing and numeracy skills indicated by the following scales. Description of each scale is given in Volume 2, Part 3 “Literacy and Numeracy”

Reading

5

Writing

5

Numeracy

5


Employability Skills

5)

The required outcomes described in this unit of competency contain applicable facets of Employability Skills. The Employability Skills Summary of the qualification in which this unit of competency is packaged will assist in identifying Employability Skill requirements.




Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

9) This provides essential advice for assessment of the unit of competency and must be read in conjunction with the Performance Criteria and the range statement of the unit of competency and the Training Package Assessment Guidelines.

The Evidence Guide forms an integral part of this Competency Standard Unit and shall be used in conjunction with all component parts of this unit and, performed in accordance with the Assessment Guidelines of this Training Package.

Overview of Assessment

9.1)

Longitudinal competency development approaches to assessment, such as Profiling, require data to be reliably gathered in a form that can be consistently interpreted over time. This approach is best utilised in Apprenticeship programs and reduces assessment intervention. It is the Industry’s preferred model for apprenticeships. However, where summative (or final) assessment is used it is to include the application of the competency in the normal work environment or, at a minimum, the application of the competency in a realistically simulated work environment. It is recognised that, in some circumstances, assessment in part or full can occur outside the workplace. However, it must be in accord with Industry and, Regulatory policy in this regard.

Methods chosen for a particular assessment will be influenced by various factors. These include the extent of the assessment, the most effective locations for the assessment activities to take place, access to physical resources, additional safety measures that may be required and the critical nature of the competencies being assessed.

The critical safety nature of working with electricity, electrical equipment, gas or any other hazardous substance/material carries risk in deeming a person competent. Hence, sources of evidence need to be ‘rich’ in nature so as to minimise error in judgment.

Activities associated with normal every day work have a bearing on the decision as to how much and how detailed the data gathered will contribute to its ‘richness’. Some skills are more critical to safety and operational requirements while the same skills may be more or less frequently practiced. These points are raised for the assessors to consider when choosing an assessment method and developing assessment instruments. Sample assessment instruments are included for Assessors in the Assessment Guidelines of this Training Package.

Critical aspects of evidence required to demonstrate competency in this unit

9.2)

Before the critical aspects of evidence are considered all prerequisites shall be met.

Evidence for competence in this unit is based, shall be considered holistically. Each element and associated Performance Criteria shall be demonstrated on at least two occasions in accordance with the “Assessment Guidelines – UET12UET12”. Evidence shall also comprise:

A representative body of Performance Criteria demonstrated within the timeframes typically expected of the discipline, work function and industrial environment. In particular this shall incorporate evidence that shows a candidate is able to:

Implement Occupational Health and Safety workplace procedures and practices including the use of risk control measures as specified in the Performance Criteria and range; and

Apply sustainable energy principles and practices as specified in the Performance Criteria and range; and

Demonstrate an understanding of the essential knowledge and associated skills as described in this unit to such an extent that the learner’s performance outcome is reported in accordance with the preferred approach; namely a percentile graded result, where required by the regulated environment; and

Demonstrate an appropriate level of employability skills; and

Conduct work observing the relevant Anti Discrimination legislation, regulations, policies and workplace procedures; and

Demonstrated performance across a representative range of contexts from the prescribed items below:

Range of tools/equipment/materials/procedures/workplaces/other variables

Group No

The minimum number of items on which skill is to be demonstrated

Item List

A

Completion of two (2) compliant technical designs including each of the following:

Coordination and analysis of earth resistivity tests.

Design and drafting of earth grid including electrodes, grid connections, equipment connections and remote earthing connections to conduct maximum earth fault currents without exceeding the maximum allowable earth potential rise (EPR).

Confirmation of acceptable step and touch potentials including attenuation or hazard control measures.

Confirmation of control of transfer of EPR.

B

Designs should also include all the following:

Activities that address the correction of errors in the process.

Application of a design control checklist which lists all of the required design activities to be carried out in this process.

C

At least one occasion

Dealing with an unplanned event by drawing on essential knowledge and associated skills to provide appropriate solutions incorporated in the holistic assessment with the above listed items.

Context of and specific resources for assessment

9.3)

This unit should be assessed as it relates to normal work practice using procedures, information and resources typical of a workplace. This should include:

OHS policy and work procedures and instructions.

Suitable work environment, facilities, equipment and materials to undertake actual design of transmission, sub-transmission and zone substation earthing.

In addition to the resources listed above, in Context of and specific resources for assessment, evidence should show demonstrated competency working realistic environment and a variety of conditions.

Method of assessment

9.4)

This Competency Standard Unit shall be assessed by methods given in Volume 1, Part 3 “Assessment Guidelines”.

Note:

Competent performance with inherent safe working practices is expected in the Industry to which this Competency Standard Unit applies. This requires that the specified essential knowledge and associated skills are assessed in a structured environment which is primarily intended for learning/assessment and incorporates all necessary equipment and facilities for learners to develop and demonstrate the essential knowledge and associated skills described in this unit.

Concurrent assessment and relationship with other units

9.5)

There are no recommended concurrent assessments with this unit, however in some cases efficiencies may be gained in terms of learning and assessment effort being concurrently managed.


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assingnment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

8) Essential Knowledge and Associated Skills (EKAS): This describes the essential skills and knowledge and their level, required for this unit.

Evidence shall show that knowledge has been acquired of designing transmission, sub-transmission and zone substation earthing.

All knowledge and skills detailed in this unit should be contextualised to current industry practices and technologies.

KS01-TDS55A Power system transmission and sub-transmission substation earthing

Evidence shall show an understanding of designing power system transmission and sub-transmission earthing to an extent indicated by the following aspects:

T1 Distribution earthing system encompassing:

Standards, codes, legislation, supply authority regulations and or enterprise requirements applicable to the distribution earthing system

Reason and types of distribution earthing systems

Terminologies used in the earth systems including, touch and step potential

Conditions associated when an active HV conductor fails to earth

Selection of earthing electrodes and grids

Determination of the earthing resistance of copper clad rods using earthing monograms

T2 Principles of transmission, sub-transmission and zone substation earthing designs encompassing:

Commonwealth, State/Territory and local government legislation, Standards, codes, supply authority regulations and or enterprise requirements applicable to the substation design management principles

Requirements for the use of the substation system construction manuals, system diagrams/plans and drawings and for plans such as work method statements for the control of OHS risks

Types of activities to be carried out - earth resistivity tests coordination, design of the earth grid, confirmation of control of transfer of EPR

Types of earthing design parameters - coordination and analysis of earth resistivity tests, design and drafting of earth grid including electrodes, grid connections, equipment connections and remote earthing connections to conduct maximum earth fault currents without exceeding the maximum allowable earth potential rise (EPR), confirmation of acceptable step and touch potentials including attenuation or hazard control measures, water, telephone service and LV neutral supplies isolation to isolate local EPR

10) This relates to the unit of competency as a whole providing the range of contexts and conditions to which the Performance Criteria apply. It allows for different work environments and situations that will affect performance.

This Competency Standard Unit shall be demonstrated in relation to the design of transmission, sub-transmission and zone substation earthing and may include the following:

Concerns associated with the earthing design should take into account: Grid designed for max fault current, maximum allowable earth potential rise, step potentials, touch potentials, fence separately earthed or bonded to station grid, fence isolation from all items bonded to station grid, e.g. building, grading ring outside fence, two connections to every switchyard device, disconnector earth mats bonded directly to handle, disconnectors earthed correctly, control building(s) earthed in two places, switchgear building (s) earthed in two places, two connections to switchgear earth bar (s), two connections to control panel earth bar (s), sufficient portable earth connection points, gates earthed via flexible connections, equipotential conductor between all gate posts, grading ring extends to extremity of gate radius, fence earthed adequately, earthing of sheath at substation end of power cables and earthing of sheath at remote end of power cables

The following constants and variables included in the element/Performance Criteria in this unit are fully described in the Definitions Section 1 of this volume and form an integral part of the Range Statement of this unit:

Appropriate and relevant persons (see Personnel)

Appropriate authorities

Appropriate work platform.

Assessing risk

Assessment

Authorisation

Confined space

Diagnostic, testing and restoration.

Documenting detail work events, record keeping and or storage of information.

Drawings and specifications

Emergency

Environmental and sustainable energy procedures

Environmental legislation.

Environmental management documentation.

Established procedures.

Fall prevention

Hazards

Identifying hazards

Inspect

Legislation

MSDS

Notification.

OHS practices

OHS issues

Permits and / or permits to work

Personnel.

Quality assurance systems.

Requirements.

Safe design principles

Testing procedures

Work clearance systems

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
OHS practices/procedures and environmental and sustainable energy procedures, which may influence the design of substations, are reviewed and determined. 
Purpose of the design is established and expected outcomes of the work are confirmed with the appropriate personnel. 
Established policies, procedures and specifications for the design are obtained or established with the appropriate personnel. 
Equipment/tools and personal protective equipment are selected and coordinated based on specified requirements and established procedures 
Work is prioritised and sequenced for the most efficient and effective outcome following consultation with others for completion within acceptable timeframes, to a quality standard and in accordance with established procedures 
Risk control measures are identified, prioritised and evaluated against the work schedule 
Relevant work permits are secured to coordinate the performance of work according to requirements and/or established procedures 
Resources including personnel, equipment, tools and personal protective equipment required for the job are identified, scheduled and coordinated and confirmed in a safe and technical working order 
Liaison and communication issues with other/authorised personnel, authorities, clients and land-owners are resolved and activities coordinated to carry out work 
Site is prepared according to the work schedule and to minimise risk and damage to property, commerce, and individuals in accordance with established procedures 
Personnel participating in the work, including plant operators and contractors, are fully briefed and respective responsibilities coordinated and authorised where applicable in accordance with established procedures 
Circuit/systems modelling is used to evaluate alternative proposals as per established procedures. 
OHS and sustainable energy principles, functionality and practices to avoid incidence and accidents and minimise waste are incorporated into the project in accordance with requirements and/or established procedures 
System design decisions are made on the basis of safety and effective outcomes according to requirements and/or established procedures 
Mathematical models of the earth grid are used to analyse the effectiveness of the finished project as per requirements and established procedures 
Technical advice is given regarding potential hazards, safety risks and control measures so that monitoring and preventative action can be undertaken and/or appropriate authorities consulted, where necessary, in accordance with requirements and established procedures 
Essential knowledge and associated skills are applied to analyse specific data and compare it with compliance specifications to ensure completion of the project within an agreed timeframe according to requirements. 
Solutions to non-routine problems are identified and actioned using acquired essential knowledge and associated skills according to requirements 
Quality of work is monitored against personal performance agreement and/or established organisational and professional standards. 
Final checks of the design are undertaken to ensure they comply with all requirements and include all specifications and documentations needed to complete the design brief. 
Appropriate personnel are notified of completion and reports and/or completion documents are finalised. 
Reports and/or completion documents are submitted to relevant personnel/organisations for approval and, where applicable, statutory or regulatory approval 
Approved copies of design documents are issued and records are updated in accordance with established procedures. 

Forms

Assessment Cover Sheet

UETTDRDS55A - Design power system transmission and sub-transmission substation earthing
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

UETTDRDS55A - Design power system transmission and sub-transmission substation earthing

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: