2)

This Competency Standard Unit is intended to augment formally acquired competencies. It is suitable for employment-based programs under an approved contract of training.

1)Scope:

1.1) Descriptor

This Competency Standard Unit covers the preparation of a basic switching schedule for interconnected HV network plant. It includes planning basic outages and taking into account loading of network components. It also includes the calculation of network loading conditions to ensure the network is operating within designed parameters.

You may want to include more information here about the target group and the purpose of the assessments (eg formative, summative, recognition)

Prerequisites

Prerequisite Unit(s)

4)

Competencies

4.1)

Granting of competency in this unit shall be made only after competency in the following unit(s) has/have been confirmed.

Where pre-requisite pathways have been identified. All competencies in the Common Unit Group must be have been completed plus all the competencies in one (1) of the identified Pathway Unit Group(s):

Transmission Overhead

Distribution Overhead

Rail Traction

Distribution Cable Jointing

Electrical

Common Unit Group

Unit Code

Unit Title

UEENEEE101A

Apply Occupational Health and Safety regulations, codes and practices in the workplace

UEENEEE102A

Fabricate, assemble and dismantle utilities industry components

UEENEEE104A

Solve problems in d.c. Circuits

UEENEEE105A

Fix and secure electrotechnology equipment

UEENEEE107A

Use drawings, diagrams, schedules, standards, codes and specifications

UEENEEG101A

Solve problems in electromagnetic devices and related circuits

UEENEEG102A

Solve problems in low voltage a.c. Circuits

UETTDREL16A

Working safely near live electrical apparatus

UETTDRIS44A

Perform HV field switching operation to a given schedule

Transmission Overhead Pathway Group

Unit Code

Unit Title

UETTDREL11A

Apply sustainable energy and environmental procedures

UETTDREL12A

Operate plant and equipment near live electrical conductors and apparatus

UETTDRIS54A

Install and maintain poles, structures, overhead conductors and cables

UETTDRTP26A

Install transmission structures and associated hardware

UETTDRTP27A

Maintain transmission structures and associated hardware

UETTDRTP29A

Install and maintain transmission overhead conductors and cables

Distribution Overhead Pathway Group

Unit Code

Unit Title

UETTDREL11A

Apply sustainable energy and environmental procedures

UETTDRDP12A

Maintain overhead energised low voltage conductors and cables

UETTDREL12A

Operate plant and equipment near live electrical conductors and apparatus

UETTDRIS41A

Install network infrastructure electrical equipment

UETTDRIS42A

Maintain network infrastructure electrical equipment

UETTDRIS52A

Install and maintain poles, structures and associated hardware

UETTDRIS54A

Install and maintain poles, structures, overhead conductors and cables

UETTDRIS56A

Install and maintain low voltage overhead services

Rail Traction Pathway Group

Unit Code

Unit Title

UETTDREL11A

Apply sustainable energy and environmental procedures

UETTDREL12A

Operate plant and equipment near live electrical conductors and apparatus

UETTDRIS52A

Install and maintain poles, structures and associated hardware

UETTDRIS54A

Install and maintain poles, structures, overhead conductors and cables

UETTDRRT21A

Install traction overhead wiring systems

UETTDRRT22A

Maintain traction overhead wiring systems

UETTDRRT23A

Install rail traction bonds

UETTDRRT27A

Install overhead traction components and equipment

UETTDRRT28A

Maintain overhead traction components and equipment

Distribution Cable Jointing Pathway Group

Unit Code

Unit Title

UETTDRCJ21A

Lay ESI electrical cables

UETTDRCJ26A

Install and maintain de-energised low voltage underground polymeric cables.

UETTDRCJ27A

Install and maintain de-energised high voltage underground polymeric cables.

UETTDREL11A

Apply sustainable energy and environmental procedures

UETTDREL12A

Operate plant and equipment near live electrical conductors and apparatus

UETTDRIS41A

Install network infrastructure electrical equipment

UETTDRIS42A

Maintain network infrastructure electrical equipment

UETTDRIS55A

Install and maintain low voltage underground services

Electrical Pathway Group

Unit Code

Unit Title

UEENEEE137A

Document and apply measures to control OHS risks associated with electrotechnology work

UEENEEG006A

Solve problems in single and three phase low voltage machines

UEENEEG033A

Solve problems in single and three phase electrical apparatus and circuits

UEENEEG063A

Arrange circuits, control and protection for general electrical installations

UEENEEG106A

Terminate cables, cords and accessories for low voltage circuits

UEENEEG108A

Trouble-shoot and repair faults in low voltage electrical apparatus and circuits

UEENEEG109A

Develop and connect electrical control circuits

UEENEEK142A

Apply environmentally and sustainable energy procedures in the energy sector

UETTDRIS67A

Solve problems in energy supply network equipment

Literacy and numeracy skills

4.2)

Participants are best equipped to achieve this unit if they have reading, writing and numeracy skills indicated by the following scales. Description of each scale is given in Volume 2, Part 3 “Literacy and Numeracy”

Reading

4

Writing

4

Numeracy

4


Employability Skills

5)

The required outcomes described in this unit of competency contain applicable facets of Employability Skills. The Employability Skills Summary of the qualification in which this unit of competency is packaged will assist in identifying Employability Skill requirements.




Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

9) This provides essential advice for assessment of the unit of competency and must be read in conjunction with the Performance Criteria and the range statement of the unit of competency and the Training Package Assessment Guidelines.

The Evidence Guide forms an integral part of this Competency Standard Unit and shall be used in conjunction with all component parts of this unit and, performed in accordance with the Assessment Guidelines of this Training Package.

Overview of Assessment

9.1)

Longitudinal competency development approaches to assessment, such as Profiling, require data to be reliably gathered in a form that can be consistently interpreted over time. This approach is best utilised in Apprenticeship programs and reduces assessment intervention. It is the Industry’s preferred model for apprenticeships. However, where summative (or final) assessment is used it is to include the application of the competency in the normal work environment or, at a minimum, the application of the competency in a realistically simulated work environment. It is recognised that, in some circumstances, assessment in part or full can occur outside the workplace. However, it must be in accord with Industry and, Regulatory policy in this regard.

Methods chosen for a particular assessment will be influenced by various factors. These include the extent of the assessment, the most effective locations for the assessment activities to take place, access to physical resources, additional safety measures that may be required and the critical nature of the competencies being assessed.

The critical safety nature of working with electricity, electrical equipment, gas or any other hazardous substance/material carries risk in deeming a person competent. Hence, sources of evidence need to be ‘rich’ in nature so as to minimise error in judgment.

Activities associated with normal every day work have a bearing on the decision as to how much and how detailed the data gathered will contribute to its ‘richness’. Some skills are more critical to safety and operational requirements while the same skills may be more or less frequently practiced. These points are raised for the assessors to consider when choosing an assessment method and developing assessment instruments. Sample assessment instruments are included for Assessors in the Assessment Guidelines of this Training Package.

Critical aspects of evidence required to demonstrate competency in this unit

9.2)

Before the critical aspects of evidence are considered all prerequisites shall be met.

Evidence for competence in this unit shall be considered holistically. Each element and associated Performance Criteria shall be demonstrated on at least two occasions in accordance with the “Assessment Guidelines – UET12”. Evidence shall also comprise:

A representative body of Performance Criteria demonstrated within the timeframes typically expected of the discipline, work function and industrial environment. In particular this shall incorporate evidence that shows a candidate is able to:

Implement Occupational Health and Safety workplace procedures and practices including the use of risk control measures as specified in the Performance Criteria and range; and

Apply sustainable energy principles and practices as specified in the Performance Criteria and range; and

Demonstrate an understanding of the essential knowledge and associated skills as described in this unit to such an extent that the learner’s performance outcome is reported in accordance with the preferred approach; namely a percentile graded result, where required by the regulated environment; and

Demonstrate an appropriate level of employability skills; and

Conduct work observing the relevant Anti Discrimination legislation, regulations, policies and workplace procedures; and

Demonstrated performance across a representative range of contexts from the prescribed items below:

Range of tools/equipment/materials/procedures/workplaces/other variables

Group No

The minimum number of items on which skill is to be demonstrated

Item List

A

All of the following:

Approvals/clearances

Access authorities

B

At least one of the following:

Development of an interconnected switching schedule

Development of a radial switching schedule

C

All of the following:

Planning of loading of network components, including standby generation.

Evaluate load parameters and effects on system, including paralleling and off-loading.

Identify unexpected sources of energisation, e.g. generators, UPS, etc.

Implementing earthing procedures to reduce induced voltages.

Authorising issuance of work-permits.

D

At least one occasion:

Dealing with an unplanned event by drawing on essential knowledge and associated skills to provide appropriate solutions incorporated in the holistic assessment with the above listed items.

Context of and specific resources for assessment

9.3)

This unit should be assessed as it relates to normal work practice using procedures, information and resources typical of a workplace. This should include:

OHS policy and work procedures and instructions.

Suitable work environment, facilities, equipment and materials to undertake actual development of HV switching schedules.

In addition to the resources listed above, in Context of and specific resources for assessment, evidence should show demonstrated competency working at realistic heights above ground i.e. above 3 metres, in limited spaces, with different structural/construction types and method and in a variety of environments.

Method of assessment

9.4)

This Competency Standard Unit shall be assessed by methods given in Volume 1, Part 3 “Assessment Guidelines”.

Note:

Competent performance with inherent safe working practices is expected in the Industry to which this Competency Standard Unit applies. This requires that the specified essential knowledge and associated skills are assessed in a structured environment which is primarily intended for learning/assessment and incorporates all necessary equipment and facilities for learners to develop and demonstrate the essential knowledge and associated skills described in this unit.

Concurrent assessment and relationship with other units

9.5)

For optimisation of training and assessment effort, competence in this unit may be assessed concurrently with the following units:

UETTDRIS49A Develop low voltage switching schedule


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assingnment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

8) Essential Knowledge and Associated Skills (EKAS): This describes the essential skills and knowledge and their level, required for this unit.

Evidence shall show that knowledge has been acquired of developing an HV switching schedule.

All knowledge and skills detailed in this unit should be contextualised to current industry practices and technologies.

KS01-TIS48A High voltage switching schedules

Evidence shall show an understanding of developing high voltage switching schedules to an extent indicated by the following aspects:

T1 Electrical equipment fundamentals used in the powerline industry encompassing:

Legislation, Standards, codes, legislation, supply authority regulations and specific enterprise regulations pertaining to the use and care of electrical equipment - HV and LV equipment

Characteristics, capabilities and application of powerline electrical equipment

Safety precautions with regards to using electrical equipment

Techniques in pre-use inspection on the serviceability of electrical equipment

Techniques in the general maintenance, and care and storage of electrical equipment

Identifying hazards, assessing and controlling risks associated with their the use of electrical equipment

T2 High voltage switching principles encompassing:

Standards, codes, legislation, supply authority regulations and or enterprise requirements applicable to switching of high voltage to a given schedule

Requirements for the use of manuals, system diagrams/plans and drawings - types, characteristics and capabilities of electrical apparatus, use, characteristics and capabilities of specialised tools and testing equipment, network interconnectors source of possible backfeed

Role of the HV switching operator

Operational forms, access authorities and permits associated with HV switching - types of operational forms, access authorities and permits, purpose and procedure for operational forms, access authorities and permits.

Use and operation of equipment associated with HV overhead and substation equipment - test instruments, sticks, interrupters, arc stranglers.

Types and categories of HV switchgear

Application, function and operating capabilities of switchgear

Restrictions pertaining to HV switching equipment

Procedures for the isolation of HV transmission main and working earths

Earthing HV electrical apparatus practices and procedures for access - purposes of “Operational” and additional work part “on-site” earths, factors determining the location and effectiveness of “Operational” earthing, acceptable industry procedures, personal protective equipment, high voltage switching techniques.

Operate switching apparatus - identifying hazards, assessing and controlling risks associated with HV switchgear operation, systematic and defensive techniques, mobile radio procedures, double isolation procedures.

T3 High voltage distribution transformer principles encompassing:

Operation of HV distribution transformers - principle governing factors for transformer ratings, protection and alarms, operating limitations and the relationship between transformer and HV fuse rating, purpose and principle operation of HV distribution transformer tap changers, HV distribution transformer and transformer — cable combination switching practices, paralleling requirements, isolation and earthing procedures for access, common distribution transformer and associated electrical apparatus faults.

HV underground switching equipment - arc stranglers, switch operation, load break elbows, switching cubicles, canister fuses, bayonet fuses, F and G switching cubicles, voltage indicators and phasing testers.

T4 High voltage SWER system encompassing:

Application and function of SWER system components

Circuit arrangement

Principle of operation

Hazards and procedures associated with faulty SWER earth systems

Procedure to isolate, energise and commission SWER substations

T5 Feeder automation system encompassing:

Function of feeder automation system and the main components

Operation procedure for a remote field device from a local control station

Functions of “System Control and Date Acquisition” (SCADA) (or any other relevant Data Acquisition and Control) systems and its main components

SCADA system security interlocks and access restrictions

SCADA system operation when switching apparatus or retrieving data via a remote access device such as; Remote Access Terminal (RAT), Dial Up Voice Annunciated System and Local Control Station

Function of the main components of a local/remote control system

Operation of a field devices using SCADA systems via a Remote Access Terminal (RAT), Dial Up Annunciated System and Local Control Station.

T6 HV system switching principles including switching authorisation procedures encompassing:

Legislation, Standards, codes, legislation, supply authority regulations and or enterprise requirements applicable to system switching

Requirements for the use of manuals, system diagrams/plans and drawings

Types and characteristics of HV systems and equipment to be switched

Procedures for obtaining correct HV switching authorisation - identification of OHS hazards, assessing and controlling risks, safety procedures and precautions, safe approach distances, responsibilities and protocols, identifying switching resources, procedures for obtaining electrical access permits authorities, requirements for team switching, procedures for coordination of operations.

Techniques in HV system switching - pre-switching checks, switching operational procedures, isolation procedures and proving dead de-energised, earthing procedures, emergency fault procedures, energisation procedures.

T7 HV overhead and substation switching principles encompassing:

Legislation, Standards, codes, legislation, supply authority regulations and or enterprise requirements applicable to HV overhead and substation switching

Requirements for the use of manuals, system diagrams/plans and drawings - types, characteristics and capabilities of HV electrical equipment to be switched, use, characteristics and capabilities of specialised tools and testing equipment.

Role and responsibilities of the HV switching operator

Operational forms, access authorities and permits hazard/risk assessments associated with HV switching - types of operational forms, access authorities and permits hazard/risk assessments, purpose and procedure for operational forms, access authorities and hazard/risk assessments.

Use and operation of equipment associated with HV overhead and substation equipment - test instruments, sticks, interrupters, arc stranglers.

HV switchgear – types, categories, application, operating capabilities.

Operation of HV overhead switching or indicating devices - fuses; disconnect fuses; load switching; live line indicators; capacitors; reclosers; sectionalisers, underslung links, airbreaks; switches, disconnects; live line clamps; phasing sticks; phasing tester

Operation of protection systems and substation equipment - fault levels and settings; types and applications; protection systems and substation equipment fault levels and settings; types and applications.

Restrictions pertaining to HV switching equipment

Procedures for the isolation of HV mains and working earths - earthing HV electrical apparatus practices and procedures for access authority issuing; HV switching techniques.

Operate switching apparatus - identifying hazards, assessing and controlling risks associated with HV switchgear operation, systematic and defensive techniques, mobile radio procedures, double isolation procedures.

T8 Preparation of a HV switching instruction schedule encompassing:

Legislation, Standards, codes, legislation, supply authority regulations and or enterprise requirements applicable to switching instruction schedules

Requirements for the use of manuals, system diagrams/plans and drawings - types, characteristics and capabilities of HV electrical equipment to be switched, points of isolation and earthing locations (safety and working earths), responsibilities of the switching operator.

Techniques in writing switching instructions - sequence of switching operations, isolation procedures, earthing procedures, switching completion notification procedures.

T9 Enterprise specific — policy and procedure instructions encompassing:

Responsibilities and duty of care of employer and employee relationship

Methods of obtaining the up-to-date information on enterprise policy and procedures

Rules and regulations

Induction into workplace - location of work area and storage area, timetable, uniform, personal well-being, housekeeping rules, emergency procedures, evacuation procedures

Techniques when deal with others - working in teams, customer relation, complaint and issues procedures.

Overview of enterprise professional development - fire fighting procedures, fatigue management, training and competency development - understanding and promotion

T10 Enterprises specific — OHS instructions encompassing:

Standards, codes, legislation, supply authority regulations and specific enterprise regulations pertaining to the OHS policies and procedures

Methods of obtaining the up-to-date information on enterprise OHS policy and procedures

Specific enterprise personal protection equipment - type and application, where and when to be used, method of replacement, responsibility of maintenance including cleaning inspection and testing, emergency response, rescue, evacuation and First Aid procedures

Personal well-being – hygiene, fatigue/stress management, drugs/alcohol

OHS training - induction training, specific hazard training, specific task or equipment training, emergency and evacuation training, training as part of broader programs such as equipment operation

OHS records including audits, inspection reports, workplace health and environmental monitoring records, training and instruction records, manufacturers and suppliers information such as MSDSs, registers, maintenance reports, workers compensation and rehabilitation records and First Aid/medical records

T11 Enterprises specific — technical drawing and documents encompassing:

Types and application of enterprise specific drawings and documents - electrical and electronic drawings, mechanical drawings, project charts, schedules, graphs, technical manuals and catalogues

Instruction/worksheets sheets - types and application of enterprise specific symbols and diagrams

Title box - description of parts and version control

T12 Enterprise specific switching diagrams and drawing encompassing:

Types and application of enterprise specific switching drawings and documents - wiring and schematic diagrams and switching symbols, mechanical drawings dealing with switching operations, project charts, switching schedules, graphs, technical manuals and catalogues, instruction/work sheets.

Interpretation of different system switching diagrams - LV system switching diagrams, DC traction supply sectioning diagrams, HV transmission and distribution system symbols and feeder plans, processes of updating switching diagrams

10) This relates to the unit of competency as a whole providing the range of contexts and conditions to which the Performance Criteria apply. It allows for different work environments and situations that will affect performance.

This Competency Standard Unit shall be demonstrated in relation to the development of HV switching schedules and include the use of system diagrams, data schedules, system loading data and use of computer based systems.

The following constants and variables included in the element/Performance Criteria in this unit are fully described in the Definitions Section 1 of this volume and form an integral part of the Range Statement of this unit:

Appropriate and relevant persons (see Personnel)

Appropriate authorities

Assessing risk

Assessment

Authorisation

Confined space

Documenting detail work events, record keeping and or storage of information

Drawings and specifications

Emergency

Environmental and sustainable energy procedures

Environmental legislation

Environmental management documentation

Established procedures

Hazards

Identifying hazards

Inspect

Legislation

Notification

OHS practices

OHS issues

Permits and/or permits to work

Personnel

Quality assurance systems

Requirements

Testing procedures

Work clearance systems

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Works schedule(s), including drawings, plans, requirements, established procedures, and material lists, are obtained, analysed, if necessary, by site inspection and the extent of the preparation of the work determined for planning and coordination. 
Work is prioritised and sequenced for the most efficient and effective outcome following consultation with others for completion within acceptable timeframes, to a quality standard and in accordance with established procedures. 
Risk control measures are identified, prioritised and evaluated against the work schedule. 
Relevant requirements and established procedures for the work are communicated to all personnel and identified for all work sites. 
Hazards are identified, OHS risks assessed and control measures are prioritised, implemented and monitored including emergency exits kept clear, to ensure safe systems of work are followed and according to established procedures. 
Relevant work permits are secured to coordinate the performance of work according to requirements and/or established procedures. 
Resources including personnel, equipment, tools and personal protective equipment required for the job are identified, scheduled and coordinated and confirmed in a safe and technical working order. 
Clients/Customers are provided with possible solutions and/or options within the scope, acceptable cost and requirements. 
Personnel participating in the work, including plant operators and contractors, are fully briefed and respective responsibilities coordinated and authorised where applicable in accordance with established procedures. 
Liaison and communication issues with other/authorised personnel, authorities, clients and land owners are resolved and activities coordinated to carry out work. 
OHS and sustainable energy principles and practices to reduce the incidents of accidents and minimise waste are monitored and actioned in accordance with requirements and/or established procedures. 
Hazard warnings and safety signs are recognised and hazards and assessed OHS risks are reported to the immediate authorised persons for directions according to established procedures. 
Remedial actions are taken to overcome any shortfalls encountered in the work schedule according to requirements and/or established procedures. 
Development of HV switching schedules is carried out, in accordance with the work schedule and requirements and/or established procedures. 
Essential knowledge and associated skills are applied in the safe development of HV switching schedules to ensure completion in an agreed timeframe and, to quality standards with a minimum of waste according to requirements. 
Solutions to non-routine problems are identified and actioned using acquired essential knowledge and associated skills according to requirements. 
Ongoing checks of quality of the work are undertaken in accordance with requirements and established procedures to ensure a quality like outcome is achieved for the client/customer and to a community/industry standard. 
Work undertaken is checked against works schedule for conformance with requirements, anomalies reported and solutions identified in accordance with established procedures. 
Accidents and/or injuries are reported and followed up in accordance with requirements/established procedures. 
Ensure Relevant work permit(s) are signed off and plant is returned to service and advised to client/customer in accordance with requirements. 
Works completion records, reports, as installed /modified drawing(s) and/or documentation and information are confirmed, processed and appropriate personnel notified. 

Forms

Assessment Cover Sheet

UETTDRIS48A - Develop high voltage switching schedule
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

UETTDRIS48A - Develop high voltage switching schedule

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: