Elements and Performance Criteria
- Identify scope of landscape project works
- Nature of landscape project works and extent of responsibilities are identified and checked against relevant landscape documentation.
- Personnel and other resources required to undertake landscape project works are identified according to the scope of the project and relevant landscape documentation.
- A work program is developed according to the needs of management and/or the client to ensure that project outcomes are reached within designated time lines.
- The environmental impact of the proposed landscape project works is considered.
- Occupational Health and Safety (OHS) hazards are identified, risks assessed and controls implemented.
- Coordinate the supply of materials/ equipment
- Material quantities and equipment requirements are calculated to ensure an on-going work program is maintained according to the scope of the project.
- Material quantities are ordered, checked for quantity and quality, and stockpiled where required.
- Any specific delivery instructions are conveyed and confirmed with suppliers to ensure materials are delivered according to the work program.
- Any material rejected is sent back to supplier and re-ordered.
- Monitor project works
- Work program is monitored and adjusted to ensure the site is developed according to the needs of management and/or the client, and to ensure that project outcomes are reached within designated time lines
- Variations to the work program, issues likely to cause delays, and contingencies beyond the scope of the project are identified, recorded and reported to management and/or the client.
- The work site is monitored to ensure it remains in a clean, tidy and safe condition throughout and on completion of landscape project works.
- Complete site works
- Site is inspected prior to practical completion to ensure all works have been undertaken according to management and/or client needs and the relevant landscape documentation.
- Any works not complying are noted and rectified.
- A completed landscape project works report is produced, recorded and communicated to management and/or the client.