Elements and Performance Criteria
- Plan and prepare
- Disassemble and inspect dies
- Die is safely located in the coating area
- Die coating insulation materials are inspected for wear, and removed if required
- Dies are inspected and analysed for defects, and identified defects are rectified according to workplace procedures
- Dies are tested to ensure rectification has eliminated the fault, and adjustments are made if required
- Coat and assemble dies
- Die coating insulation material is selected and prepared according to workplace procedures
- Die is cleaned in preparation for coating and heated according to workplace and equipment manufacturer recommendations and work health and safety (WHS) requirements
- Die coating insulation material is applied to the die, and die is assembled and checked in preparation for pressing according to workplace and equipment manufacturer recommendations
- Die is returned to production sequence
- Complete work processes