Elements and Performance Criteria
- Plan and prepare
- Activities are carried out according to OHS and organisation requirements
- Work instructions, including relevant inspection reports and forms and quality requirements are obtained, confirmed with appropriate personnel and applied
- Tools and equipment selected to carry out tasks are consistent with the requirements of the job, checked for serviceability and any faults are rectified or reported prior to commencement
- Materials appropriate to the work application are identified, obtained, prepared, safely handled and located ready for use
- Disassemble and inspect die
- Die is safely located to the coating area
- Die coating insulation material is inspected for wear and removed as appropriate
- Die is inspected and analysed for defects
- Defects found are assessed for remedial solution
- Minor rectification is applied, dependent on the defect and in accordance with engineering specifications
- Die is tested to ensure rework has eliminated the fault and any final adjustments made
- Documentation is completed outlining nature of the problem, work conducted and outcome, in accordance with organisation requirements
- Coat and assemble die
- Die coating insulation material is selected and prepared for the die
- Die is cleaned in preparation for coating
- Heating processes are completed in accordance with organisation requirements and available heating equipment
- Die coating insulation material is applied to the die
- Die is assembled and checked in preparation for pressing
- Die is returned to production sequence
- Clean up