Elements and Performance Criteria
- Prepare to use crane, gantry or forklift to launch vessel
- Conduct pre-launch safety inspection
- Weather, tides and launch site are checked for safe launch conditions
- Vessel safety equipment is audited
- Vessel systems and components are checked for seaworthiness, and compliance with manufacturer specifications and applicable state and territory regulations
- Systems and components that fail the vessel check are recorded, and supervisor and owner are notified
- Launch vessel
- Slings and lifting equipment are attached and positioned to hull according to manufacturer and workplace procedures and safety requirements
- Crane, gantry or forklift is operated and manoeuvred to place vessel in suitable depth of water at launch site, according to manufacturer and workplace procedures and safety requirements, and without causing damage to vessel or the environment
- Slings and lifting equipment are removed from vessel according to manufacturer and workplace procedures and safety requirements
- Vessel is moved from launch site to safe area in water according to state and territory marine safety laws
- Crane, gantry or forklift is moved from launch site according to manufacturer and workplace procedures and safety requirements
- Recover vessel
- Crane, gantry or forklift is positioned at lift point ensuring suitable depth of water is present according to manufacturer and workplace procedures and safety requirements
- Vessel is manoeuvred into recovery area according to state and territory marine safety laws, and aligned with lifting equipment
- Slings and lifting equipment are attached and positioned to hull according to manufacturer and workplace procedures and safety requirements
- Crane, gantry or forklift is operated and manoeuvred to remove vessel from water according to manufacturer and workplace procedures and safety requirements, and without causing damage to vessel, lifting equipment or physical surrounds
- Vessel is secured in storage or transport location and slings and lifting equipment are removed from vessel according to manufacturer and workplace procedures and safety requirements
- Prepare to use crane, gantry or forklift to launch vessel
- Conduct pre-launch safety inspection
- Weather, tides and launch site are checked for safe launch conditions
- Vessel safety equipment is audited
- Vessel systems and components are checked for seaworthiness, and compliance with manufacturer specifications and applicable state and territory regulations
- Systems and components that fail the vessel check are recorded, and supervisor and owner are notified
- Launch vessel
- Slings and lifting equipment are attached and positioned to hull according to manufacturer and workplace procedures and safety requirements
- Crane, gantry or forklift is operated and manoeuvred to place vessel in suitable depth of water at launch site, according to manufacturer and workplace procedures and safety requirements, and without causing damage to vessel or the environment
- Slings and lifting equipment are removed from vessel according to manufacturer and workplace procedures and safety requirements
- Vessel is moved from launch site to safe area in water according to state and territory marine safety laws
- Crane, gantry or forklift is moved from launch site according to manufacturer and workplace procedures and safety requirements
- Recover vessel
- Crane, gantry or forklift is positioned at lift point ensuring suitable depth of water is present according to manufacturer and workplace procedures and safety requirements
- Vessel is manoeuvred into recovery area according to state and territory marine safety laws, and aligned with lifting equipment
- Slings and lifting equipment are attached and positioned to hull according to manufacturer and workplace procedures and safety requirements
- Crane, gantry or forklift is operated and manoeuvred to remove vessel from water according to manufacturer and workplace procedures and safety requirements, and without causing damage to vessel, lifting equipment or physical surrounds
- Vessel is secured in storage or transport location and slings and lifting equipment are removed from vessel according to manufacturer and workplace procedures and safety requirements