Elements and Performance Criteria
- Prepare for planning.
- Nature and scope of planning task are identified and confirmed.
- Safety (OHS) requirements associated with planning, sizing and documenting the layout of heated, tempered and cold water services and systems, and workplace environmental requirements, are adhered to throughout the work.
- Work is organised and sequenced in conjunction with others involved in or affected by the work and statutory and regulatory authority requirements.
- Tools and equipment required for planning, sizing and documenting the layout of heated, tempered and cold water services and systems, including personal protective equipment, are selected and checked for serviceability.
- Work area in which planning process is to be conducted is prepared.
- Identify system requirements.
- Information and specifications for required work are obtained and confirmed, if necessary by site inspection using relevant information.
- Regulations and Australian standards relevant to the work are consulted and applied to all aspects of the work.
- Quantity, location and type of take off points and fixtures are determined from plans and specifications.
- Heated, tempered and cold water services and systems are sized in accordance with relevant Australian standards and regulatory authorities' and workplace requirements.
- Plan service and system layout.
- Layout of heated, tempered and cold water services and systems to point of discharge are planned in accordance with building plans, relevant Australian standards and workplace procedures.
- Materials required are specified and optimised in accordance with relevant Australian standards from the proposed design.
- Plans are recorded in accordance with regulatory authorities' and workplace requirements.
- Sustainability principles and concepts are applied to work preparation and application.
- Restore work area.