Elements and Performance Criteria
- Identify and plan installation requirements
- Applicable OHS, legislative and organisational requirements relevant to lead light and stained glass operations are verified and complied with
- Location of the lead light and stained glass panel to be installed is established confirmed and clarified with appropriate personnel
- Installation sequence is identified and a work plan is developed
- Tools and equipment required for the installation are identified
- Approval of installation plan is obtained as required by agreed procedures
- Prepare for the installation
- Tools and equipment are positioned and checked prior to use to ensure that they are appropriate for the installation, serviceable and in a safe condition
- Inspection of the opening where the panel is to be installed is conducted
- Lead light and stained glass panel is inspected to ensure its integrity while being installed
- Plans and other documents are positioned to allow for confirmation of the panel structure and placement
- Photographs are taken of the panel for later reference
- Install the panel
- Finalise and report on the installation