Google Links

Follow the links below to find material targeted to the unit's elements, performance criteria, required skills and knowledge

Required Skills

Required skills

Required skills include

efficient and effective operation of plantequipment

recognising conditions which will lead to out of specification operation

implementing enterprise procedures within time constraints and in a manner relevant to the correct use of the equipment

conveying information relevant to the operation clearly and effectively

maintaining appropriate levels of quality assurance

reading and numeracy to interpret workplace documents and technical information

Required knowledge

Required knowledge of solvent extraction equipment principles and typical problems to a level needed to control the operation includes

principles of operation of solvent extraction plantequipment

process parameters and limits

duty of care obligations

hierarchy of control

communication protocols eg radio phone computer paper and permissionsauthorities

typical issues causing problems and the resolution of those problems

routine problems faults and their symptoms and the corrective action to be taken

relevant alarms and actions

plant process idiosyncrasies

all items on a schematic of the plant item and the functionprinciples of operation and problem solving of each

physics and chemistry relevant to each unit and the processes used

function and troubleshooting of major internal components and their problems such as internals supports pumps or agitators

relevant environmental and heritage requirements

Evidence Required

The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria required skills and knowledge range statement and the Assessment Guidelines for the Training Package

Critical aspects for assessment and evidence required to demonstrate competency in this unit

Critical aspects for assessment and evidence are

early warning signs of equipmentprocesses needing attention or with potential problems are recognised

the range of possible causes can be identified and analysed and the most likely cause determined

appropriate action is taken to ensure a timely return to full performance

obvious problems in related plant areas are recognised and an appropriate contribution made to their solution

Context of and specific resources for assessment

Assessment of this competency will occur over a range of situations which will include typical disruptions to normal smooth operation This will require access to an operating plant over an extended period of time or a suitable method of gathering evidence of operating ability Where safety lack of opportunity or significant cost is an issue an industrybased simulation may be employed to assist the process

Guidance information for assessment

Assessment processes and techniques must be appropriate to the language competency and safety requirements of the site and consistent with workplace systems or procedures


Range Statement

The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Context

This competency includes all types of solvent extraction equipment, including, but not limited to:

mixer/settlers

organic treatment units

Procedures

Procedures may be written, verbal, computer-based or in some other form. They may include, but are not limited to:

all work instructions

standard operating procedures

formulas/recipes

batch sheets

temporary instructions

any similar instructions provided for the smooth running of the plant

good operating practice as may be defined by industry codes of practice

Procedures would be expected to comply with any relevant government regulations.

Logs and reports

Logs and reports may include:

paper or electronic-based logs and reports

verbal/radio reports

reporting items found which require action

Ancillary equipment variables

Ancillary equipment variables may include, but are not limited to:

temperature

amps

pressure

vibration

Appropriate action

Appropriate action includes, but is not limited to:

determining problems needing action

accessing and applying relevant technical and plant data

applying appropriate problem solving techniques to determine possible fault causes

rectifying problem using appropriate solution within area of responsibility

following through items initiated until final resolution has occurred

reporting problems outside area of responsibility/ability to designated person

Typical problems

Typical problems may include, but are not limited to:

process leaks

variations in throughput or feed

blockages/build-up/fouling

erosion/wear

driver problems

Remedial actions

Remedial actions may include, but are not limited to:

making adjustments to the equipment

carrying out minor maintenance within operator's skill level

identifying and reporting problems outside operator's scope of ability

identifying and controlling hazards related to solvent extraction equipment and surrounding areas

Start up and shut down as required

Start up and shut down as required includes:

start up and shut down to/from normal operating conditions

start up and shut down to/from isolated, cold or empty

all other conditions experienced on the plant (i.e. from any condition to any condition experienced on the plant)

Health, safety and environment (HSE)

All operations to which this unit applies are subject to stringent HSE requirements, which may be imposed through state or federal legislation, and these must not be compromised at any time. Where there is an apparent conflict between Performance Criteria and HSE requirements, the HSE requirements take precedence.

Work requirements

Work requirements may come from briefings, handovers and work orders and may include:

• compliance documentation

• product specifications

• nature and scope of tasks

• achievement targets

• operational conditions

• lighting conditions

• plant or equipment defects

• hazards and potential hazards

• coordination requirements or issues