Follow the links below to find material targeted to the unit's elements, performance criteria, required skills and knowledge

Elements and Performance Criteria

  1. Prepare for work
  2. Prepare the pipeline system for pigging (launching/ receiving)
  3. Launch, monitor progress and/or receive pig
  4. Interpret pigging data

Range Statement

This field allows for different work environments and conditions that may affect performance. Essential operating conditions that may be present (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) are included.

Regulatory framework

The latest version of all legislation, regulations, industry codes of practice and Australian/international standards, or the version specified by the local regulatory authority, must be used, and include one or more of the following:

legislative requirements, including work health and safety (WHS)

industry codes of practice and guidelines

environmental regulations and guidelines

Australian and other standards

licence and certification requirements

All operations to which this unit applies are subject to stringent health, safety and environment (HSE) requirements, which may be imposed through state/territory or federal legislation, and these must not be compromised at any time. Where there is an apparent conflict between performance criteria and HSE requirements, the HSE requirements take precedence.

Hazards

Hazards include one or more of the following:

gases and liquids under pressure

velocity of pig

structural hazards

structural collapse

equipment failures

industrial (machinery, equipment and product)

equipment or product mass

plant services (steam, condensate and cooling water)

working at heights, in restricted or confined spaces, or in environments subjected to heat, noise, dusts or vapours

flammability and explosivity

hazardous products and materials

unauthorised personnel

sharp edges, protrusions or obstructions

slippery surfaces, spills or leaks

extreme weather

other hazards that might arise

Routine problems

Routine problems are predictable problems with known solutions and include one or more of the following:

closure seal failure resulting in hydrocarbon release and possible explosion

closure fastening mechanism fails and results in door striking technician

stuck pig

delayed pig

scraper enclosure leaks

leaking valves

damaged pig

Non-routine problems

Non-routine problems are unexpected problems, or variations of previous problems and must be resolved by applying operational knowledge to develop new solutions, either individually or in collaboration with relevant experts, to:

determine problems needing action

determine possible fault causes

develop solutions to problems which do not have a known solution

follow through items initiated until final resolution has occurred

report problems outside area of responsibility to designated person

Operational knowledge includes one or more of the following:

procedures

training

technical information, such as journals and engineering specifications

remembered experience

relevant knowledge obtained from appropriate people

Procedures

All operations must be performed in accordance with relevant procedures.

Procedures are written, verbal, visual, computer-based or in some other form, include one or more of the following:

emergency procedures

work instructions

standard operating procedures (SOPs)

safe work method statements (SWMS)

formulas/recipes

batch sheets

temporary instructions

any similar instructions provided for the smooth running of the plant

Product

Product includes anything produced by a process step and so includes:

intermediate products, such as the product from one process step, which then becomes the feed for another



Knowledge Evidence

Evidence must be provided that demonstrates knowledge of:

all items on a schematic of the pigging system and functions of each

systems’ operating parameters and integrity limits

reasons for pipeline pigging and the type of pig used for each application

prevention/mitigation measures for closure risks

the nature/condition of materials/flows entering and leaving the scraper barrels during the launching and receiving operations

correct valve sequences

expected system pressures for launching/receiving operations

principles of pigging

hierarchy of control

hazards that may arise in the job/work environment, and:

their possible causes

potential consequences

appropriate risk controls.