Elements and Performance Criteria
- Plan and prepare
- Access, interpret and apply compliance documentation relevant to the work activity
- Identify and apply relevant drawings and job specifications to all work activities
- Obtain and confirm safety requirements from the site safety plan and organisational policies and procedures, and apply to the allotted task
- Identify, obtain and implement signage requirements from the project traffic management plan
- Select plant, tools and equipment to carry out tasks consistent with the requirements of the job, check for serviceability and rectify or report any faults
- Identify environmental protection requirements from the project environmental management plan, and confirm and apply to the allotted task
- Set out and excavate trenches
- Install bedding materials
- Install sub-soil drainage
- Place geo-textile according to specifications
- Prepare drain sections and fittings
- Lay subsoil drain
- Provide inspection opening and flush out points according to plans
- Fit out and/or connect end structures/outlets/clean outs to culverts, storm water or subsoil drain systems
- Install packing and prepare system for backfilling
- Monitor backfill procedure to ensure work completed to specification
- Clean up