  1. Plan and prepare to place and compact concrete
  2. Define and prepare work area
  3. Place concrete and compact
  4. Screed/level concrete
  5. Clean up
  6. Plan and prepare to place and compact concrete
  7. Define and prepare work area
  8. Place concrete and compact
  9. Screed/level concrete

Performance Evidence

Evidence is required to be collected that demonstrates a candidate’s competency in this unit. Evidence must be relevant to the roles within this sector’s work operations and satisfy all of the requirements of the performance criteria of this unit and include evidence that the candidate:

locates and applies applicable documentation, policies and procedures

implements the requirements, procedures and techniques for the safe, effective and efficient placement and compaction of concrete including:

accessing, interpreting and applying documentation for placing and compacting concrete

identifying and applying relevant specifications to all work activities

identifying, addressing and reporting potential hazards and risks

identifying, obtaining, confirming and implementing signage requirements

selecting and checking for faults all plant, tools and equipment to carry out tasks

identifying, addressing and reporting environmental issues

works effectively with others to undertake the placement and compaction of concrete that meets all of the required outcomes including:

preparing for and organising work activities to meet all task requirements

communicating clearly and concisely with others to receive and clarify work instructions

using a range of communication techniques and aids to advise others of work activity and exclusion zones

monitoring movements and hazards and identifying and communicating changes to the work environment during the work process

demonstrates completion of placing and compacting concrete that safely, effectively and efficiently meets all of the required outcomes on more than one (1) occasion including:

defining and preparing work, locating plant, tools and equipment to suit planned placement and undertaking pre-pour inspections

placing concrete using a minimum of two (2) of the following techniques

kibble

pumping equipment

shovelling

tremmies

truck placed

vibrating

wheelbarrows

using method/s used to avoid segregation of concrete

compacting or vibrating concrete to specifications

using techniques to finish concrete

screeding concrete to correct levels and grades

clearing work area and disposing of, recycling or storing materials

cleaning, checking, maintaining and storing plant, tools and equipment


Knowledge Evidence

The candidate must demonstrate knowledge in placing and compacting concrete through:

accessing, interpreting and applying the organisation and site requirements and procedures for:

identifying and managing risks

identifying, addressing and reporting environmental issues

setting up work activity

site isolation, signage, erecting barriers and traffic control

work health and safety

managing waste

selecting and checking for faults, all tools and equipment to carry out tasks

carrying out work to specifications

manufacturer’s design specifications

applying effective techniques for placing and compacting concrete