Elements and Performance Criteria
- Plan and prepare to muck out tunnel earthworks
- Access, interpret and apply muck out tunnel earthworks documentation and ensure the work activity is compliant
- Obtain, interpret, clarify and confirm work instructions before proceeding Identify, obtain and implement traffic signage requirements
- Select and wear personal protective equipment appropriate for work activities
- Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
- Select and check for faults plant, tools and equipment to carry out tasks
- Identify, address and report environmental issues, potential hazards and risks
- Bar/scale down loose material
- Remove spoil by hand
- Load spoil by machine
- Remove spoil
- Conduct housekeeping activities
- Plan and prepare to muck out tunnel earthworks
- Access, interpret and apply muck out tunnel earthworks documentation and ensure the work activity is compliant
- Obtain, interpret, clarify and confirm work instructions before proceeding Identify, obtain and implement traffic signage requirements
- Select and wear personal protective equipment appropriate for work activities
- Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
- Select and check for faults plant, tools and equipment to carry out tasks
- Identify, address and report environmental issues, potential hazards and risks
- Bar/scale down loose material
- Remove spoil by hand
- Load spoil by machine
- Remove spoil
- Conduct housekeeping activities