Elements and Performance Criteria
- Plan for local possession authority
- Worksite protection plan is developed to determine LPA worksite protection arrangements
- Work group supervisor is advised of advertised approval
- Resources are organised to provide adequate protection for infrastructure and work group during rail work activity
- Implement local possession authority
- Permission to implement LPA is requested from Network Control Officer
- Resources to provide protection for LPA are deployed in accordance with worksite protection plan
- Work group supervisor is advised that LPA has been issued
- Adjustments to LPA are negotiated with Network Control Officer, as required
- Each worksite within the LPA is provided with a protection officer while work is being performed
- Multiple worksites are protected in accordance with worksite protection plan
- Rail traffic movements between worksites and within LPA limits are coordinated
- Authorisation is given to rail traffic entering the LPA
- Fulfil local possession authority
- Confirmation is obtained from work group supervisor that work activity is completed and track is safe for rail traffic
- Resources used to provide protection are removed in accordance with advertised approval
- LPA is fulfilled for entire portion of track included within the LPA or is fulfilled progressively for one or more portions of track included in the LPA
- Arrangements are made for work to continue under another work on track authority, as required
- Manage unsafe situations or emergencies
- Unsafe situations and/or emergencies are identified
- Work group is instructed to move to a safe place
- Appropriate action is taken to minimise risk and/or injury in accordance with workplace procedures
- Emergencies and/or incidents are recorded and reported to relevant personnel in accordance with workplace procedures