Elements and Performance Criteria
- Determine job requirements
- Work requirements are determined for new ballast work and/or repair of existing ballast
- Obstacles in work area are identified and removal or protection are organised as necessary to ensure smooth workflow following workplace procedures
- Resources are organised to meet the scope of the job and work methods selected
- Ballast quantities are determined
- Undertake ballast unloading
- Appropriate site communications are established and agreed to ensure safe and efficient working conditions
- Ballast unloading operation is implemented to ensure appropriate flow rates and extent
- Ballast is distribution by manual and/or mechanical methods to allow safe operation of trains
- Ballast is removed from sensitive infrastructure to ensure safe operation of trains and safety of public
- Complete documentation