Elements and Performance Criteria
- Prepare to work on multiple path ELV a.c. electrical circuits
- WHS/OHS risk control measures and workplace procedures in preparation for the work are followed
- Scope of circuit problem is obtained from documentation and/or work supervisor
- Advice is sought from work supervisor to ensure work is coordinated effectively with others
- Sources of materials required for work are identified and accessed in accordance with workplace procedures
- Tools, equipment and testing devices required for work are obtained and checked for correct operation and safety
- Solve multiple path ELV a.c circuit problems
- Need to test and measure live work is determined in accordance with WHS/OHS requirements and workplace procedures
- Circuits are checked and isolated, as required, in accordance with WHS/OHS requirements and workplace procedures
- Methods are used to solve a.c circuit problems from measured and calculated values as they apply to multiple path electrical circuits
- Unplanned situations are dealt with safely in accordance with workplace procedures and approval of relevant person/s
- Problems are solved without damage to apparatus, circuits, the surrounding environment or services using sustainable energy practices
- Complete work and document problem-solving activities
- Worksite is cleaned and made safe in accordance with workplace procedures
- Justification for solutions used to solve circuit problems is documented
- Work completion is documented and relevant person/s notified in accordance with workplace procedures