Elements and Performance Criteria
- Prepare to conduct electrical tests on a three phase induction machine
- WHS/OHS risk control measures and workplace procedures for work preparation are followed
- Scope of work is determined from job sheets, specifications and regulatory requirements
- Advice is sought from work supervisor to ensure work activity is coordinated effectively with others
- Materials required for work are obtained in accordance with workplace procedures
- Tools, equipment and testing devices required for work are obtained and checked for operation and safety
- Conduct electrical tests on a three phase induction machine
- Machines/equipment are isolated in accordance with WHS/OHS requirements and workplace procedures
- HV electrical inspection and tests are conducted to determine cause of faults and/or operational condition of the machine
- Status of the machine is determined from inspection and test results and recorded in accordance with workplace procedures
- Problem-solving techniques are used to resolve unplanned events
- Quality of work checks are conducted to ensure coils are correctly wound with correct wire, number of turns and shape in accordance with workplace procedures and work instructions
- Work is completed in accordance with given timeframe, environment and workplace procedures
- Status of HV electrical machine is documented in accordance with workplace procedures and relevant person/s notified