Elements and Performance Criteria
- Prepare to rewind single phase machines.
- OHS procedures for a given work area are identified, obtained and understood.
- Established OHS risk control measures for work preparation are followed.
- Work instructions are identified, obtained and understood.
- Advice is sought from the work supervisor to ensure the work is coordinated effectively with others.
- Single phase machine is dismantled and parts tagged and stored to prevent loss or damage.
- Winding data is obtained from record or from work supervisor in accordance with established routines.
- Winding is stripped from stator in accordance with established routines.
- Materials required for the work are obtained in accordance with established routines and procedures.
- Tools, equipment and testing devices needed to carry out the work are obtained and checked for correct operation and safety.
- Rewind single phase machines.
- Established OHS risk control work measures are followed.
- Machines/equipment are checked as being isolated where necessary in strict accordance OHS requirements and procedures.
- Single phase machine is dismantled and parts tagged and stored to prevent loss or damage.
- Winding is stripped from stator in accordance with established routines.
- Stator is wound and insulated in accordance with winding data and established routines.
- Machine is assembled and prepares for testing.
- Prescribed solutions are used to resolve work completion issues.
- Routine quality checks are conducted to ensure coils are correctly wound with correct wire, number of turns and shape.
- Work is completed in acceptable timeframe given environment and workplace conditions.
- Complete work report.