Elements and Performance Criteria
- Prepare to conduct electrical tests on three phase induction machines.
- OHS procedures for a given work area are identified, obtained and understood.
- Established OHS risk control measures for work preparation are followed.
- The extent of the work is determined from job sheets, specifications and regulatory requirements.
- Advice is sought from the work supervisor to ensure the work is coordinated effectively with others.
- Winding data is obtained from winding data records or directly from measurements of stator and recorded in accordance with established procedures.
- Winding is stripped from stator in accordance with established procedures.
- Materials required for the work are obtained in accordance with established procedures.
- Tools, equipment and testing devices needed to carry out the work are obtained and checked for correct operation and safety.
- Conduct electrical tests on three phase induction machines.
- Established OHS risk control work measures are followed.
- Machines/equipment are checked as being isolated where necessary in strict accordance OHS requirements and procedures. (See Note 1)
- All necessary HV electrical tests are conducted to established cause of faults or operational condition of the machine.
- Status of the machine is determined from test results and recorded.
- Prescribed solutions are used to resolve work completion issues.
- Routine quality checks are conducted to ensure coils are correctly wound with correct wire, number of turns and shape.
- Work is completed in acceptable timeframe given environment and workplace conditions.
- Complete work report.