Elements and Performance Criteria
- Prepare to diagnose and rectify faults.
- OHS procedures for a given work area are identified, obtained and understood.
- OHS risk control measures and procedures in preparation for the work are followed.
- The likely extend of work to be undertaken is envisaged from maintain procedures or fault/breakdown reports and/or discussions with appropriate person(s).
- Advice is sought from the work supervisor to ensure the work is coordinated effectively with others.
- Tools, equipment and testing devices needed to carry out the work are obtained in accordance with established procedures and checked for correct operation and safety.
- Diagnose and rectify faults.
- OHS risk control measures and procedures for carrying out the work are followed.
- The need to test or measure live is determined in strict accordance with OHS requirements and when necessary conducted within established safety procedures.
- Circuits/machines/plant are checked as being isolated where necessary in strict accordance OHS requirements and procedures.
- Safety hazards resulting from the fault or breakdown are documented and risk control measured and devised and implemented in consultation with appropriate personnel.
- Logical diagnostic methods are applied to diagnose lift system apparatus faults employing measurements and estimations of system operating parameters referenced to system operational requirements.
- Suspected fault scenarios are tested as being the cause(s) of system fault.
- Cause of the fault is identified and appropriately competent persons are engaged to rectify the fault where it is outside the scope of the lift systems.
- Faults in the lift components of the system are rectified to raise apparatus and system to its operational standard.
- System is tested to verify that the system operates as intended and to specified requirements
- Methods for dealing with unexpected situations are selected on the basis of safety and specified work outcomes.
- Diagnosis and rectification activities are carried out efficiently without unnecessary waste of materials or damage to apparatus and the surrounding environment or services and using sustainable energy practices.
- Completion and report fault diagnosis and rectification activities
- Note.Examples of documentation are components fault reports, test results, authorisations, permits, parts/component dispatch and store records