Elements and Performance Criteria
- Establish integrated system scenario
- Customer requirements for scenes, events and controls in the integrated system are established from job specifications and discussion with appropriate persons
- The types and location of integrated system loads are determined from job specifications and customer requirements.
- Types and location of control (input) devices of integrated system are determining from job specifications and customer requirements.
- Budget for the integrated system is established from customer requirements and discussion with appropriate persons.
- Plan integrated system
- OHS procedures and risk control work measures are followed.
- Knowledge of integrated system devices and their capabilities is applied in the plan.
- Number and types of output devices to suit the established scenario are chosen for compatibility with the system loads
- Number and types of control (input) devices to suit the established system scenario are chosen.
- Integrated systems are planned to comply with bus system and supply voltage parameters.
- Other control methods are considered in planning the integrated system plan.
- Integrated systems are planned within the given budget.
- Final plan is documented and submitted to an appropriate person for approval.
- Note. Documentation includes explanations of how the customers’ requirement will be achieved; a material list with costs and a marked up floor plan showing relationship of load groups to input devices.
- Implement an integrated system installation plan
- OHS risk control work measures and procedures are followed.
- Integrated systems are arranged using an acceptable topology.
- A connection chart/diagram between all device in the integrated system is developed
- Appropriate cable for the bus system is selected and connected at devices and accessories using the methods and the polarity specified by the manufacturer.