Elements and Performance Criteria
- Prepare to maintain and power station compound and monitor performance.
- OHS procedures for a remote area power station facility is identified, obtained and understood through established routines and procedures
- Established OHS risk control measures and procedures in preparation for the work are followed
- Safety hazards which have not previously been identified are reported and advice on risk control measures is sought from the work supervisor
- The nature and location of remote area power station facility is obtained from documentation or from work supervisor to establish the scope of work to be undertaken
- Advice is sought from the work supervisor to ensure the work is coordinated effectively with fellow workers and the local community
- Sources of materials that may be required for the work are identified and accessed in accordance with established routines and procedures
- Tools, equipment and testing devices needed to carry out the work are obtained and checked for correct operation and safety.
- Established procedures are followed to repair or replace defective and unsafe tools and service equipment.
- Maintain power station compound and monitor performance
- Established OHS risk control measures and procedures for carrying out the work are followed
- Circuits/machines/plant are checked as being isolated where necessary in strict accordance OHS requirements and procedures
- Established procedures are followed to clean and tidy power station building, generating equipment and compound to maintain safe and efficient plant area.
- Inspection and reporting is conducted on suitability, location and legibility of safety signage.
- Inspection and reporting is conducted on location, suitability and condition of fighting equipment
- Performance, status and fuel and oil use of generation equipment is monitored and logged from information displayed instruments, meters and measuring devices.
- Procedures are followed for referring non-routine events to immediate supervisor for directions
- Routine quality checks are carried out in accordance with work instructions
- Develop basic maintenance schedule and complete work report
- OHS work completion risk control measures and procedures are followed.
- Maintenance schedule is developed from logged information on power station performance, status and condition of compound.
- Procedures are followed for referring maintenance issues beyond the scope of prescribed work to persons of higher authority.
- Work carried out is reported to the work supervisor through the established maintenance reporting procedures.