Elements and Performance Criteria
- Prepare to find and repair signalling system faults
- OHS procedures for a given work area are identified, obtained and understood.
- Established OHS risk control measures and procedures are followed in preparation for the work.
- Safety hazards that have not previously been identified are documented and risk control measures devised and implemented in consultation with appropriate personnel.
- Appropriate persons are consulted to establish the nature of the fault and to coordinate effectively with others affected by the fault.
- Likely causes of the fault and order of probability are determined from system data and historical trend.
- Impact of the fault on system is ascertained and appropriate personnel notified in accordance with established procedures.
- Materials needed to find and repair the fault are obtained in accordance with established procedures and checked against job requirements
- Tools, equipment and testing devices needed to find and repair the fault are obtained in accordance with established procedures and checked for correct operation and safety.
- Circuits/equipment are checked as being isolated where necessary in strict accordance operational procedures and OHS requirements.
- Find and repair signalling system faults
- OHS risk control measures and procedures for carrying out the work are followed.
- Knowledge of signalling system performance parameters is applied to appropriate fault finding techniques.
- Tests are conducted to determine the type and location of the fault.
- Wiring system is visually inspected for physical damage or installation defects where necessary.
- Methods for dealing with unexpected situations are selected on the basis of safety and specified work outcomes.
- Ongoing checks of the signalling system are undertaken to confirm the continued rectification of the fault.
- Faults are located and identified efficiently without waste of materials or damage to apparatus and the surrounding environment or services and using sustainable energy practices.
- Signalling system faults are rectified in accordance with established procedures
- Complete the finding and repair of the signalling system faults
- OHS risk control measures and procedures for carrying out the work are followed.
- Unresolved faults are reported to appropriate persons for further action in accordance with established procedures.
- Inspection and test results actions taken or recommended are documented and appropriate person(s) notified in accordance with established procedures.
- Documentation including component faults, test results, authorisations and permits is completed to provide an accurate database and facilitate follow up action, and relevant reports produced.