Elements and Performance Criteria
- Prepare to install ammonia refrigeration system
- Safety hazards not previously identified are reported, assessed and advice on risk control measures sought from the project engineer
- Nature of work is obtained from documentation or from project engineer to determine the scope of work to be undertaken
- Advice is sought from the project engineer to ensure refrigeration work is coordinated effectively with others
- Sources of materials required for work are determined in accordance with workplace procedures
- Tools, equipment and testing devices needed to carry out refrigeration work are obtained and checked for correct operation and safety
- Install and commission ammonia refrigeration system
- Major components and pipe work are installed in accordance with relevant industry standards, codes of practice and regulations
- Pressure testing is conducted at a pressure compatible with ammonia and in accordance with industry standards and practices
- Precautions are taken to prevent damage to components while pressure testing the system
- Leaks are located and rectified using testing methods appropriate to the refrigeration system and in accordance with industry standards and practices
- Refrigeration system is evacuated in accordance with industry standards and practices
- Refrigeration system is charged safely with ammonia and lubricants in accordance with industry standards and practices
- Refrigeration pre-operational checks are carried out on operating and safety controls in accordance with manufacturer specifications
- Refrigeration system is commissioned and adjustments made to operating and safety controls
- Temperature reduction of cool rooms and freezers are undertaken in accordance with industry standards and practices
- Refrigeration maintenance is carried out and includes inspection and cleaning of strainers and filters and collection of oil sample for analysis
- Training is conducted for person/s responsible for the refrigeration system operation and maintenance
- Complete and report on commissioning of ammonia refrigeration system
- Contaminated refrigerant and lubricant are dealt with in accordance with legislative/regulatory requirements
- Refrigeration operation condition and commissioning data are documented and includes parameters not within the specified range for the system
- Refrigeration mechanical and electrical commissioning documentation is completed in accordance with workplace procedures