Follow the links below to find material targeted to the unit's elements, performance criteria, required skills and knowledge

Elements and Performance Criteria

  1. Prepare to commission/decommission gas distribution pipelines
  2. Job requirements and workplace procedures for the work are discussed with relevant person/s to confirm the work schedule
  3. WHS/OHS, environmental and sustainable energy policies and procedures are obtained and applied in accordance with workplace procedures
  4. Work is prioritised and sequenced for completion within acceptable timeframes following consultation with relevant person/s in accordance with workplace procedures
  5. Hazards are identified, WHS/OHS risks are assessed and control measures prioritised, implemented, and monitored in accordance with workplace procedures
  6. Scope of work and level of responsibility under the relevant work permit and/or notification is confirmed with relevant person/s in accordance with job requirements and workplace procedures
  7. Person/s, equipment, tools and personal protective equipment (PPE) required for the work are identified, scheduled, obtained and checked for correct operation and safety in accordance with workplace procedures
  8. Materials, plans, diagrams, drawings and resources required for the work are scheduled and obtained in accordance with workplace procedures
  9. Safety and emergency procedures and responsibilities for first aid and incidents at the worksite are checked and confirmed with relevant person/s in accordance with workplace procedures
  10. Third-party issues are referred to relevant person/s in accordance with workplace procedures
  11. Pipeline is cleaned, pigged, bypassed and check for commissioning/decommissioning readiness in accordance with workplace procedures
  12. Site preparation, safety plan and work schedule are confirmed with relevant person/s in accordance with workplace procedures
  13. Person/s participating in the work are briefed and responsibilities confirmed in accordance with job requirements and workplace procedures
  14. Road signs, barriers and warning devices are positioned in accordance with job requirements and traffic management plan
  15. Commission/decommission gas distribution pipelines
  16. Materials, tools, equipment and testing and measuring devices required for the work are selected and used correctly and safely in accordance with manufacturer instructions and workplace procedures
  17. Hazardous activities are conducted safely in accordance with WHS/OHS workplace procedures, job instructions and regulatory requirements
  18. Pipeline purging/flaring is undertaken in accordance with job requirements, industry standards and workplace procedures
  19. Commissioning/decommissioning of gas distribution pipelines is performed to industry standards without waste of materials or damage to apparatus, circuits, and the surrounding environment or services using sustainable energy principles
  20. Gas is tested for compliance with pressure, concentration and odourant level requirements in accordance with industry standards and workplace procedures
  21. WHS/OHS risks are assessed and incidents reported to authorised person/s for directions in accordance with workplace procedures
  22. Unplanned events and non-routine problems are referred to authorised person/s for directions in accordance with workplace procedures
  23. Relevant reports and quality and safety checks of the work are conducted in accordance with job requirements and workplace procedures
  24. Complete work and relevant documentation
  25. Testing is conducted using relevant tools/equipment and work checked against work schedule for conformance with job requirements and anomalies reported in accordance with workplace procedures
  26. Accidents and injuries are reported in accordance with requirements and workplace procedures
  27. Work site is rehabilitated, cleaned up and made safe in accordance with workplace procedures
  28. Tools, equipment and any surplus resources and materials are cleaned, checked and securely stored in accordance with workplace procedures
  29. Relevant work permit/s are signed off and equipment returned to service in accordance with workplace procedures, job and regulatory requirements
  30. Appropriate person/s are notified of work completion in accordance with workplace procedures
  31. Final inspections are undertaken and work completion documentation is finalised, processed and provided to appropriate person/s in accordance with workplace procedures

Range Statement

Range is restricted to essential operating conditions and any other variables essential to the work environment.

Non-essential conditions may be found in the UEG Gas Industry Training Package Companion Volume Implementation Guide.

commissioning/decommissioning gas distribution pipelines must include:

carrying out job safety analysis (JSA)

commissioning and recommissioning workplace procedures

isolating venting and purging gas pipeline systems

obtaining the required work permit/authorisation

purging and venting calculations

testing for correct pressure, concentration and odourant level

using gas detectors

isolation methods must include at least two (2) of the following:

bagtube

high pressure stop off

hot tap and stopple

squash off jacks/pliers