Elements and Performance Criteria
- Prepare for hydrotesting for transmission pipeline construction
- Work instructions are received and confirmed.
- OHS, environmental and sustainable energy policies and procedures to be followed for the work to be performed are received and confirmed.
- Easement is inspected and testing procedures determined in accordance with standard operating procedures relevant requirements.
- Discussion occurs with all persons to establish and confirm work schedule.
- Suggestions to assist with testing for construction of pipeline are made to others involved in the work.
- Hazards are identified, OHS risks assessed and control measures are prioritised, implemented and monitored including emergency exits kept clear according to established procedures.
- Scope of responsibility under the relevant work permit is received and confirmed according to requirements and established procedures with relevant persons.
- Resources including equipment requirements, tools and personal protective equipment required for the job are obtained and in working order according to established procedures.
- Relevant responsibilities associated with first aid and other related work safety procedures at the worksite are confirmed in accordance with requirements and established procedures to ensure safety measures and followed in the instance of an incident.
- Third party issues are referred to appropriate persons in accordance with industry and community standards
- Carry out relevant testing for transmission pipeline construction
- OHS policies and procedures and safe work practices are followed to eliminate or minimise incidents and hazards.
- Lifting, climbing, working in confined spaces, excavations, trenches, or aloft, and use of power tools, techniques and practices are safely followed in accordance with given instructions and according to requirements confirmed to eliminate the prospects of incidents.
- Work area is isolated and made safe and civil activities and testing of pipeline for construction is carried out in accordance with given instructions and established procedures.
- Easement is confirmed for testing of pipeline construction to ensure completion in an agreed timeframe and to quality standards with a minimum of waste according to requirements and established procedures
- Operational knowledge as applied to potential hazards and safety risks are reported to the immediate authorised persons for directions according to established procedures
- Non-routine events are referred to the immediate authorised persons for directions according to established procedures.
- Remedial action associated with testing for construction of transmission pipeline is dealt with using acquired known solutions and skills related to routine procedures to ensure work instructions and established procedures are met.
- Ongoing checks of quality of the work are undertaken in accordance with given instructions and established procedures.
- Complete procedures for testing of transmission pipeline construction
- The work undertaken is checked against work schedule and anomalies reported to authorised persons in accordance with established procedures.
- Accidents and incidents are actioned and reported to authorised persons in accordance with established procedures.
- Work site is rehabilitated, cleaned up and made safe in accordance with given instructions and established procedures.
- Tools, equipment and any surplus resources and materials are, where appropriate, cleaned, checked and returned to storage in accordance with established procedures.
- Appropriate persons are notified of work completion according to established procedures.
- Work completion records, report forms and data sheets are completed accurately in accordance with given instructions and established procedures.