Google Links

Follow the links below to find material targeted to the unit's elements, performance criteria, required skills and knowledge

Elements and Performance Criteria

  1. Prepare for hydro-testing for transmission pipeline construction
  2. Job requirements and workplace procedures for the site are obtained and discussed with relevant person/s to confirm the work schedule
  3. WHS/OHS, environmental and sustainable energy policies and procedures are obtained and applied in accordance with workplace procedures
  4. Easement is inspected and testing procedures determined in accordance with workplace procedures and job requirements
  5. Recommendations to assist with testing of the construction pipeline are made to others involved in the work in accordance with workplace procedures
  6. Work site hazards are identified, WHS/OHS risks are assessed and control measures prioritised, implemented and monitored in accordance with workplace procedures
  7. Scope of work and level of responsibility under the relevant work permit/authorisation is obtained and confirmed with relevant person/s in accordance with job requirements and workplace procedures
  8. Tools, plant, equipment and personal protective equipment (PPE) required for the work are identified, scheduled, obtained and checked for operation and safety in accordance with workplace procedures and manufacturer instructions
  9. Materials, plans, diagrams, drawings and resources required for the work are confirmed, scheduled and obtained in accordance with workplace procedures
  10. Responsibilities for first aid, emergencies and other related work safety procedures for an incident at the work site are checked and confirmed with relevant person/s
  11. Third-party issues are referred to relevant person/s in accordance with workplace procedures
  12. Site preparation, safety plan and work schedule are confirmed with relevant person/s in accordance with workplace procedures
  13. Hydro test transmission pipeline construction
  14. Materials, tools, plant, equipment and measuring devices required for the testing are selected and used correctly and safely in accordance with manufacturer instructions and workplace procedures
  15. Hazardous activities are conducted safely in accordance with WHS/OHS workplace procedures and job instructions
  16. Work area is isolated, made safe and hydro-testing of pipeline construction is carried out in accordance job instructions, industry standards and workplace procedures
  17. Hydro-testing of pipeline construction is conducted in agreed timeframe and to industry standards, without waste of materials or damage to apparatus, and the surrounding environment or services using sustainable energy principals
  18. WHS/OHS risks and incidents are reported to authorised person/s for directions in accordance with workplace procedures
  19. Unplanned events are referred to authorised person/s for directions in accordance with workplace procedures
  20. Remedial action required when hydro-testing transmission pipeline construction is dealt with in accordance with workplace procedures
  21. Quality and safety checks are carried out in accordance with work instructions and workplace procedures
  22. Complete hydro-testing activities and relevant documentation
  23. Work site is rehabilitated, cleaned up and made safe in accordance with workplace procedures
  24. Tools, equipment and any surplus resources and materials are, cleaned, checked and securely stored in accordance with workplace procedures
  25. Relevant person/s are notified of work completion in accordance with workplace procedures
  26. Work completion records, report forms and data sheets are completed accurately and provided to appropriate person/s in accordance with workplace procedures