Elements and Performance Criteria
- Plan installation of cathodic protection system
- Job requirements and workplace procedures for the work are identified for all work sites and communicated to all relevant person/s
- Relevant work health and safety (WHS)/occupational health and safety (OHS) workplace procedures and environmental and sustainable energy policies and procedures are obtained, applied and communicated to relevant person/s
- Data from completed cathodic protection surveys is analysed and work prioritised and sequenced for completion within acceptable timeframes following consultation with relevant person/s in accordance with workplace procedures and industry standards
- WHS/OHS risk control measures for identified hazards are prioritised, implemented and monitored against the work schedule in accordance with workplace procedures
- Relevant work permit/s are obtained to access and perform the installation work, in accordance with job requirements, workplace procedures and industry standards
- Technical specifications and drawings are prepared from the analysed cathodic protection survey data and approved in accordance with job requirements and workplace procedures
- Person/s, equipment, tools and personal protective equipment (PPE) required for the job are identified, scheduled, obtained and checked for correct operation and safety in accordance with workplace procedures
- Communication is established with relevant stakeholders to carry out the installation work in accordance with work schedule and workplace procedures
- Site is prepared to minimise risk and damage to property, commerce and individuals in accordance with the work schedule and workplace procedures
- Third-party issues are referred to appropriate person/s in accordance with workplace procedures
- Person/s participating in the work are briefed and responsibilities coordinated and confirmed in accordance with job requirements and workplace procedures
- Road signs, barriers and warning devices are positioned in accordance with job requirements, workplace procedures and traffic management plans
- Install cathodic protection system
- Hazardous activities are conducted safely in accordance with workplace procedures and job requirements
- Approved specifications and drawings are reviewed and the cathodic protection system installed in accordance with the work schedule, workplace procedures and industry standards
- Hazard warnings and safety signs are recognised, hazards and WHS/OHS risks assessed and reported to authorised person/s for directions in accordance with workplace procedures
- Unplanned events and non-routine problems in the installation are identified and actioned in accordance with workplace procedures
- Fault-finding and troubleshooting techniques are applied to identify any problems with the installation in accordance with job requirements and workplace procedures
- Quality and safety checks of the work are conducted in accordance with job requirements, industry standards and workplace procedures
- Test and commission cathodicprotectionsystem and complete relevant documentation
- Accidents, injuries and non-conformances are reported, as required, in accordance with workplace procedures
- Work site is rehabilitated, cleaned up and made safe in accordance with workplace procedures
- Tools, equipment and any surplus resources and materials are cleaned, checked and stored in accordance with workplace procedures
- Relevant work permit/s are signed off and equipment is returned to service in accordance with job requirements and workplace procedures
- Cathodic protection system is tested and adjusted, additional survey data collected, and work completion records and documentation completed, processed and appropriate person/s notified in accordance with workplace procedures
- As built/as installed drawings are checked, updated and returned to the relevant cathodic protection engineering person/s in accordance with workplace procedures