Elements and Performance Criteria
- Plan and prepare to coordinate repairs
- Appropriate persons are consulted to ensure the work is coordinated effectively with others involved in the worksite against work schedule(s), including drawings, plans and established procedures
- Relevant requirements and established procedures for the work are communicated to all persons and identified for all work sites
- OHS, environmental and sustainable energy policies and procedures, related to coordinating the repair of faults in gas processing/storage facilities and equipment, are obtained and confirmed for the purposes of the work performed and communicated
- Work is prioritised and sequenced following consultation with others for completion within acceptable timeframes and in accordance with established procedures
- Risk control measures for identified hazards are prioritised, implemented and monitored against the work schedule
- Relevant work permits are obtained to access, isolate/de-energise systems and perform work according to requirements and established procedures
- Resources including appropriately licensed persons, equipment, tools and personal protective equipment required for the job are identified, scheduled and obtained and confirmed in working order
- Relevant persons at worksite are confirmed to be current in First Aid and other related work procedures according to requirements
- Liaison and communication issues with authorised persons, authorities, clients and land owners are resolved and activities coordinated to carry out work
- Site is prepared according to the work schedule and to minimise risk and damage to property, commerce and individuals in accordance with established procedures
- Persons participating in the work, including plant operators and contractors are fully briefed and respective responsibilities confirmed where applicable in accordance with established procedures
- Coordinate repair of faults in gas processing/storage facilities and equipment
- OHS policies and procedures and safe work practices are followed to eliminate or minimise incidents and hazards
- Lifting, climbing, working in confined spaces or aloft, and use of power tools, techniques and practices are safely followed and currency according to requirements confirmed
- Apply Essential Knowledge and Associated Skills to coordinate repair of faults in gas processing/storage facilities and equipment to ensure completion in an agreed timeframe and to quality standards with a minimum of waste according to requirements
- Repair work and the replacement of faulty work equipment is monitored to ensure activities are carried out to standard operating procedures, permit to work, and minimal impact occurs on existing operations and environment
- Hazard warnings and safety signs are recognised and hazards and assessed OHS risks are reported to the immediate authorised persons for directions according to established procedures
- Unplanned events in the coordination and repair of faults in gas processing/storage facilities and equipment are undertaken with the scope of established procedures
- Known solutions to a variety of problems are applied using Essential Knowledge and Associated Skills
- Ongoing checks of quality of the work are undertaken in accordance with given instructions and established procedures
- Recommission systems and equipment
- Systems are monitored or activated to ensure they are operating both safely and effectively and permit to work is closed out and the system is restored to normal operation
- Accidents and injuries are reported in accordance with established procedures where applicable
- Work site is rehabilitated, cleaned up and made safe in accordance with given instructions and established procedures
- Tools, equipment and any surplus resources and materials are, where appropriate, cleaned, checked and returned to storage in accordance with established procedures
- Relevant work permit(s) are signed off and equipment is returned to service in accordance with requirements
- Repaired and installed equipment is brought back on line in accordance with standard operating procedures
- Work completion records, reports as installed and modified, drawings and documentation and information are finalised and processed and appropriate persons notified