Elements and Performance Criteria
- Prepare to install and commission stationary gas fuelled reciprocating engine
- OHS procedures for a given work area are identified, obtained and understood.
- Health and safety risks are identified and established risk control measures and procedures in preparation for the work are followed.
- Safety hazards that have not previously been identified are noted and established risk control measures are implemented.
- Design specification for gas fuelled reciprocating engines to be installed and commissioned is accessed, analysed, interpreted and confirmed through a detailed site inspection.
- Design specification matters requiring clarification are resolved through liaison with designer and gas authorities.
- Formal authority to proceed with installation and commissioning is obtained before commencing work, in accordance with regulatory and code of practice requirements.
- Installation is prepared in consultation with others affected by the work and sequenced appropriately in line with quality assurance requirements.
- The nature and location of the work is determined from documentation or appropriate person to establish the scope of work to be undertaken.
- Plant, equipment and component specifications and manufacturer manuals are obtained for planned work activity.
- Locations of plant, equipment, fuel train pipe-work and components are planned within the constraints of work site, significants and requirements.
- Materials needed for the installation work are obtained in accordance with design specification and established procedures
- Tools, equipment, including personal protective equipment, and testing devices needed to for the installation and commissioning work are obtained in accordance with established procedures and checked for correct operation and safety.
- Work area is prepared to support efficient installation and commissioning of the plant and equipment.
- Preparatory work is checked to ensure no damage has occurred and complies with requirements.
- Install stationary gas fuelled reciprocating engine
- OHS risk control measures and procedures for carrying out the work are followed.
- Regulatory and code of practice recording and reporting requirements are satisfied at appropriate times throughout the work sequence.
- Gas and electrical circuits/machines/plant are checked as being isolated where necessary in strict accordance OHS requirements and procedures.
- Stationary gas fuelled reciprocating engine components, including fuel train and associated pipe-work and flue/exhaust systems are installed in accordance with approved design specification and comply with technical standards and regulatory requirements, with sufficient access to affect terminations, adjustment and maintenance.
- Ventilation systems are installed in accordance with approved design specifications
- Electrical components, wiring enclosures and wiring, including terminations are installed in accordance with design and manufacturer’s specifications, and functional and regulatory requirements.
- Ongoing compliance and safety inspections of the installed reciprocating engine , equipment, pipe-work, components and accessories are undertaken and defects are rectified
- Installation is carried out efficiently without unnecessary waste of materials or damage to plant, equipment, pipe-work, components, accessories, the surrounding environment or services and using sustainable energy principles.
- Unexpected situations are dealt with safely and with the approval of an authorised person.
- Commission stationary gas fuelled reciprocating engine
- OHS risk control measures and procedures for carrying out the work are followed.
- Regulatory and code of practice recording and reporting requirements are satisfied at appropriate times throughout the work sequence.
- Gas and electrical safety checks and isolation procedures, including purging are completed and recorded to manufacturer and other authority requirements before testing and commissioning are commenced.
- Operational parameters of individual components are tested and adjusted to conform to specifications
- The reciprocating engine operations are tested first without and then with fuel, adjustments are completed as necessary and results recorded in accordance with approving authority requirements.
- Exhaust gases are analysed in accordance with recognised industry practice and other authority requirements.
- Unexpected situations are dealt with safely and with the approval of an authorised person
- Commissioning is conducted efficiently without waste of materials or damage to apparatus and the surrounding environment or services and using sustainable energy practices
- Completion and report installation and commissioning activities.
- OHS work completion risk control measures and procedures are followed.
- Final check of the installed reciprocating engine is made to verify that it complies with all requirements, including any certification required by local authorities.
- Work area is cleared and materials disposed of or recycled in accordance with federal, state and territory legislation and workplace procedures.
- Tools and equipment are cleaned, checked, serviced and stored in accordance with manufacturer recommendations and workplace procedures
- Work site is cleaned and made safe in accordance with established procedures.
- ‘As-installed’ reciprocating engine equipment components, pipe-work, flue/exhaust systems and accessories are documented, accessed and an appropriate person or persons notified in accordance with established procedures.