Elements and Performance Criteria
- Plan and prepare for the work
- Work requirements are identified from request/work orders or equivalent and clarified/confirmed with appropriate parties or by site inspection
- Occupational Health and Safety standards, statutory requirements, relevant Australian standards, codes of practice, manufacturers' specifications, environmental requirements and enterprise procedures are identified, applied and monitored throughout the work procedure
- Resources required to satisfy the work plan are identified, obtained and inspected for compliance with the job specifications
- Relevant plans, drawings and texts are selected and interpreted in accordance with the work plan
- Correct size, type and quantity of materials/components are determined, obtained and inspected for compliance with the job specifications
- Work is planned in detail including sequencing and prioritising and considerations made, where appropriate, for the maintenance of plant security and capacity in accordance with system/site requirements
- Coordination requirements, including requests for isolations where appropriate, are resolved with others involved, affected or required by the work
- Potential hazards are identified and prevention and/or control measures are selected in accordance with the work plan and site procedures
- Work area is prepared in accordance with work requirements and site procedures
- Where appropriate, the teams and individuals roles and responsibilities within the team are identified and, where required, assist in the provision of the on-the-job training
- Test wiring systems
- Required isolations are confirmed where appropriate in accordance with site requirements
- Wiring systems are tested using appropriate plans, drawings and texts in accordance with the work plan
- Wiring systems are tested in conjunction with others involved in, or affected by, the work in accordance with the work plan
- Wiring systems, including enclosures/ supports, are inspected prior to testing to ensure absence of any damage, defects and/or signs of deterioration in accordance with the work plan
- Fixed wiring is tested as appropriate and results/observations are interpreted and documented to confirm compliance with job specifications
- Test piping and tubing systems
- Required isolations are confirmed where appropriate in accordance with site requirements
- Piping and tubing systems are tested using appropriate plans, drawings and text in accordance with the work plan
- Piping and tubing systems are tested in conjunction with other involved in or affected by the work in accordance with the work plan
- Piping and tubing systems, including enclosures/supports, are inspected prior to testing to ensure absence of any damage, defects and/or signs of deterioration in accordance with the work plan
- Fixed piping and tubing is tested as appropriate and results/observations are interpreted and documented to confirm compliance with job specifications and the work plan
- Test the equipment
- Required isolations are confirmed where appropriate in accordance with site requirements
- Equipment is tested using appropriate plans, drawings and text in accordance with the work plan
- Equipment is tested in conjunction with other involved in or affected by the work in accordance with the work plan
- Required test conditions are confirmed and the equipment is inspected to ensure absence of any damage, defects and/or signs of deterioration in accordance with the work plan
- Equipment is tested using appropriate test techniques in accordance with the work plan
- Equipment test results/observations are interpreted and documented to confirm compliance with job specifications.
- Commission the equipment
- Required isolations are confirmed where appropriate in accordance with site requirements
- Equipment is commissioned using appropriate plans, drawings and text in accordance with the work plan
- Equipment is commissioned in conjunction with others involved in, or affected by, the work in accordance with the work plan
- Equipment is set up in accordance with operational requirements/manufacturer's specifications
- Testing and monitoring procedures are followed and results monitored, interpreted and documented to ensure equipment operates/functions within specifications