Elements and Performance Criteria
- Plan and prepare for the work
- Work requirements are identified from request/work orders or equivalent and clarified/confirmed with appropriate parties or by site inspection
- Occupational Health and Safety standards, statutory requirements, relevant Australian standards, codes of practice, manufacturers' specifications, environmental requirements and enterprise procedures are identified, applied and monitored throughout the work procedure
- Resources required to satisfy the work plan are identified, obtained and inspected for compliance with the job specifications
- Relevant plans, drawings and texts are selected and interpreted in accordance with the work plan
- Correct size, type and quantity of materials/components are determined, obtained and inspected for compliance with the job specifications
- Work is planned in detail including sequencing and prioritising and considerations made, where appropriate, for the maintenance of plant security and capacity in accordance with system/site requirements
- Co-ordination requirements, including requests for isolations where appropriate, are resolved with others involved, affected or required by the work
- Potential hazards are identified and prevention and/or control measures are selected in accordance with the work plan and site procedures
- Work area is prepared in accordance with work requirements and site procedures
- Conduct minor maintenance
- Required isolations are confirmed where appropriate in accordance with enterprise requirements
- Minor maintenance is conducted in accordance with the work plan and site requirements
- Minor adjustments are undertaken in accordance with prescribed procedures and schedules and site requirements
- Faults are reported to the relevant parties in accordance with site/enterprise procedures
- Complete the work
- Work is completed and appropriate personnel notified in accordance with site/enterprise requirements
- Work area is cleared of waste, cleaned, restored and secured in accordance with site/enterprise procedures
- Plant, tools and equipment are maintained and stored in accordance with site/enterprise procedures
- Work completion details are finalised in accordance with site/enterprise procedures