AHCIRG406A Mapping and Delivery Guide
Plan on-site irrigation system installation and construction work

Version 1.0
Issue Date: March 2024


Qualification -
Unit of Competency AHCIRG406A - Plan on-site irrigation system installation and construction work
Description This unit covers planning on-site irrigation system installations and construction work and defines the standard required to: identify operational requirements from contract documentation; develop strategies and plan procedures for installation and construction; develop a project plan with tasks, responsibilities, timelines and costs.
Employability Skills This unit contains employability skills.
Learning Outcomes and Application This unit applies to irrigation installers who plan on-site irrigation system installation and construction work.
Duration and Setting X weeks, nominally xx hours, delivered in a classroom/online/blended learning setting.
Prerequisites/co-requisites
Competency Field
Development and validation strategy and guide for assessors and learners Student Learning Resources Handouts
Activities
Slides
PPT
Assessment 1 Assessment 2 Assessment 3 Assessment 4
Elements of Competency Performance Criteria              
Element: Appraise contract documentation and translate into operational requirements
  • Copy of building approval and conditions is obtained as required.
  • Contract documentation is reviewed for any unusual aspects of construction, use of materials and penalties.
  • Availability of sub-contractors is ascertained and selected to suit job requirements.
  • Availability of materials is checked with suppliers.
  • Site access limitations are assessed.
  • Relevant authorities controlling construction work advised of commencement date for project as required.
       
Element: Develop strategies for implementing the construction operations
  • Procedures for controlling and recording site deliveries are established.
  • Procedures for recording the hire of plant and equipment are determined.
  • Occupational Health and Safety (OHS) procedures are established, including hazard/risk management.
  • Procedures are established for dealing with environmental issues associated with irrigation construction work.
  • Procedures required for the control of multiple projects are determined.
       
Element: Prepare project schedule for irrigation installation and construction
  • Construction operations are prepared in sequence.
  • Operations are entered into a manually prepared schedule or computer based software package.
  • 'Critical path' is identified and schedule revised with new activities/projects, as needed, and documented.
  • Timeframe is adjusted to take account of anticipated delays.
       
Element: Determine all the required resources for project
  • Temporary services and site accommodation is determined as required.
  • Plant requirements and dates are selected and accessed.
  • On site labour requirements are determined.
       
Element: Prepare dilapidation report
  • Records are made of the condition of existing building(s) to be retained and structures on the adjacent site boundaries.
  • Copies of reports are submitted to adjacent building owners prior to commencing construction.
       


Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.

Overview of assessment

Critical aspects for assessment and evidence required to demonstrate competency in this unit

The evidence required to demonstrate competency in this unit must be relevant to workplace operations and satisfy holistically all of the requirements of the performance criteria and required skills and knowledge and include achievement of the following:

identify operational requirements from contract documentation

develop strategies and plan procedures for installation and construction

develop a project plan with tasks, responsibilities, timelines and costs.

Context of and specific resources for assessment

Competency requires the application of work practices under work conditions. Selection and use of resources for some worksites may differ due to the regional or enterprise circumstances.


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assignment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

Required skills

analyse contract conditions

develop strategies

schedule projects

determine resources

identify adverse environmental impacts of irrigation activities and appropriate remedial/preventative action

incorporate legislative and enterprise OHS and environmental procedures into planning

use literacy skills to read, interpret and follow organisational policies and procedures, develop sequenced written instructions, record accurately and legibly information collected and select and apply procedures to a range of tasks

use oral communication skills/language competence to fulfil the job role as specified by the organisation including questioning, active listening, asking for clarification, negotiating solutions and responding to a range of views

use numeracy skills to estimate, calculate and record routine and more complex workplace measures and data

use interpersonal skills to work with others and relate to people from a range of cultural, social and religious backgrounds and with a range of physical and mental abilities.

Required knowledge

installation and construction processes for on-site irrigation systems

logical construction sequence for the system

analysis of the required project resources

environmental impacts of irrigation using water from any ground or underground source

relevant enterprise OHS and environmental procedures

relevant Australian Standards (e.g. AS3500)

effect of main soil types on approach to excavation work and installation of irrigation components.

The range statement relates to the unit of competency as a whole.

Planning may include:

the planning of installation and construction work for both gravity fed and pressurised irrigation systems.

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Copy of building approval and conditions is obtained as required. 
Contract documentation is reviewed for any unusual aspects of construction, use of materials and penalties. 
Availability of sub-contractors is ascertained and selected to suit job requirements. 
Availability of materials is checked with suppliers. 
Site access limitations are assessed. 
Relevant authorities controlling construction work advised of commencement date for project as required. 
Procedures for controlling and recording site deliveries are established. 
Procedures for recording the hire of plant and equipment are determined. 
Occupational Health and Safety (OHS) procedures are established, including hazard/risk management. 
Procedures are established for dealing with environmental issues associated with irrigation construction work. 
Procedures required for the control of multiple projects are determined. 
Construction operations are prepared in sequence. 
Operations are entered into a manually prepared schedule or computer based software package. 
'Critical path' is identified and schedule revised with new activities/projects, as needed, and documented. 
Timeframe is adjusted to take account of anticipated delays. 
Temporary services and site accommodation is determined as required. 
Plant requirements and dates are selected and accessed. 
On site labour requirements are determined. 
Records are made of the condition of existing building(s) to be retained and structures on the adjacent site boundaries. 
Copies of reports are submitted to adjacent building owners prior to commencing construction. 

Forms

Assessment Cover Sheet

AHCIRG406A - Plan on-site irrigation system installation and construction work
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

AHCIRG406A - Plan on-site irrigation system installation and construction work

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: