• BSBPMG609A - Direct procurement and contracting for a project program

Unit of Competency Mapping – Information for Teachers/Assessors – Information for Learners

BSBPMG609A Mapping and Delivery Guide
Direct procurement and contracting for a project program

Version 1.0
Issue Date: April 2024


Qualification -
Unit of Competency BSBPMG609A - Direct procurement and contracting for a project program
Description This unit describes the performance outcomes, skills and knowledge required to direct the management of contracting and procurement activities across projects and programs. It covers setting up the contracting process, directing the management of contract and procurement processes and finalising contracts for projects across the program.No licensing, legislative, regulatory or certification requirements apply to this unit at the time of endorsement.
Employability Skills This unit contains employability skills.
Learning Outcomes and Application A program is defined as a set of interrelated projects, each of which has a project manager. Multiple projects (sometimes called a portfolio of projects) refers to a number of projects related in some way and managed by the same person as a program to achieve a common organisational objective/s.For the purposes of this unit someone who manages a suite of projects (a program) will be referred to as a program manager.The functions performed by a project manager to manage procurement within individual projects are addressed in BSBPMG509A Manage project procurement.It should be noted that conflicting priorities between projects are managed with higher project authority support, in this case project governance committees or senior management.
Duration and Setting X weeks, nominally xx hours, delivered in a classroom/online/blended learning setting.
Prerequisites/co-requisites
Competency Field Management and Leadership - Project Management
Development and validation strategy and guide for assessors and learners Student Learning Resources Handouts
Activities
Slides
PPT
Assessment 1 Assessment 2 Assessment 3 Assessment 4
Elements of Competency Performance Criteria              
Element: Direct planning for project contracting and procurement
  • Direct product specifications and procurement requirements for procurement and contract planning, in consultation with appropriate stakeholders
  • Direct development of procurement strategies, methods and management plans in line with project objectives across the program
       
Element: Direct set up of contract and procurement process
  • Direct project managers to source organisations that meet procurement requirements
  • Establish selection processes and selection criteria, in consultation with stakeholders, and arrange for communication to prospective contractors
  • Ensure contract and procurement actions accord with organisation and program objectives
       
Element: Direct management of contract and procurement process
  • Provide direction for requirements of proposals and arrange communication to prospective contractors
  • Ensure responses are evaluated and preferred contractors are selected in accordance with agreed selection processes
  • Direct negotiation of contract terms and conditions between client and preferred contractor
       
Element: Direct management of contracts
  • Direct management of contract and procurement activities in accordance with program contract and procurement management guidelines
  • Provide direction for regular reviews from available records and information, and ensure variances are analysed and changes are agreed for implementation
  • Ensure project managers work within the legal and organisational framework for contracts
  • Identify potential, perceived and actual contractual conflicts and approve remedial actions to minimise disruption
       
Element: Direct finalisation of contracts
  • Direct finalisation activities for management of contract deliverables in accordance with contractual project and program requirements
  • Direct review and analysis of project outcomes to determine the effectiveness of contract and procurement processes and procedures
  • Aggregate and use lessons learned for application in planning and implementation of later projects within the program and, where appropriate, pass on to organisational management for use in strategic planning
       


Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

The Evidence Guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.

Overview of assessment

Critical aspects for assessment and evidence required to demonstrate competency in this unit

Evidence of the following is essential:

demonstrated experience in successfully directing procurement and contract management processes across a range of concurrent projects

knowledge of contract management and legal obligations.

Context of and specific resources for assessment

Assessment must ensure:

access to workplace contractual and procurement documentation

consideration of feedback from project team and stakeholders as to how procurement and contractual processes were handled.

Method of assessment

A range of assessment methods should be used to assess practical skill and knowledge. The following examples are appropriate for this unit:

direct questioning combined with review of portfolios of evidence and third party workplace reports of on-the-job performance of scope management techniques by the candidate

analysis of responses addressing different project scope management case studies and scenarios

oral or written questioning to assess knowledge of strategies for managing project procurement and contracts, and their application to different situations

review of established selection processes and selection criteria and how they were communicated to prospective contractors

assessment of identified potential, perceived and actual contractual conflicts and remedial actions taken to minimise disruption.

Guidance information for assessment

Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended, for example:

other units in the Advanced Diploma of Project Management.


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assignment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

Required skills

literacy skills to communicate decisions, to comprehend complex contractual provisions and to write quality reports

negotiation skills to set up contracts, to agree prices and terms, and to resolve disputes

planning and organising skills to ensure procurement processes are properly established and sequenced

analytical skills to review program performance and to recommend improvements.

Required knowledge

contract management and legal obligations of both parties

procurement processes and options.

The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Procurement strategies, methods and management plans may include:

conflict resolution processes

contract performance plans and an associated performance monitoring processes

contractor and sub-contractor responsibilities, controls and reporting relationships

explanatory information (for example background, restrictions or expectations) relating to special terms and conditions, planning for long lead-time items and critical program components, and transition plans

procurement, test and acceptance procedures and payment schedules

Proposals may take the form of:

expressions of interest

quotations

submissions

tenders

Records may take the form of:

contract analysis, evaluation of options and strategy development

contract discharge procedures and outcomes

contract negotiation documentation, for example contract negotiation strategies, plans, team and individual directives

contractor identification, evaluation and selection records

development and management of contract change procedures

procurement management lessons learned

procurement management plans

product specifications

progress measurement and conflict resolution process records

test and acceptance procedures

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Direct product specifications and procurement requirements for procurement and contract planning, in consultation with appropriate stakeholders 
Direct development of procurement strategies, methods and management plans in line with project objectives across the program 
Direct project managers to source organisations that meet procurement requirements 
Establish selection processes and selection criteria, in consultation with stakeholders, and arrange for communication to prospective contractors 
Ensure contract and procurement actions accord with organisation and program objectives 
Provide direction for requirements of proposals and arrange communication to prospective contractors 
Ensure responses are evaluated and preferred contractors are selected in accordance with agreed selection processes 
Direct negotiation of contract terms and conditions between client and preferred contractor 
Direct management of contract and procurement activities in accordance with program contract and procurement management guidelines 
Provide direction for regular reviews from available records and information, and ensure variances are analysed and changes are agreed for implementation 
Ensure project managers work within the legal and organisational framework for contracts 
Identify potential, perceived and actual contractual conflicts and approve remedial actions to minimise disruption 
Direct finalisation activities for management of contract deliverables in accordance with contractual project and program requirements 
Direct review and analysis of project outcomes to determine the effectiveness of contract and procurement processes and procedures 
Aggregate and use lessons learned for application in planning and implementation of later projects within the program and, where appropriate, pass on to organisational management for use in strategic planning 

Forms

Assessment Cover Sheet

BSBPMG609A - Direct procurement and contracting for a project program
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

BSBPMG609A - Direct procurement and contracting for a project program

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: