Unit of Competency Mapping – Information for Teachers/Assessors – Information for Learners

ICTCBL334 Mapping and Delivery Guide
Install underground enclosures and conduit

Version 1.0
Issue Date: May 2024


Qualification -
Unit of Competency ICTCBL334 - Install underground enclosures and conduit
Description
Employability Skills
Learning Outcomes and Application This unit describes the skills and knowledge required to install underground enclosures and conduit, either direct buried or in pits, for new or cable maintenance tasks in access networks for outdoor installations within customer premises or in public locations permitted by the Australian Communications and Media Authority (ACMA).It applies to technical staff who install underground infrastructure for new and upgraded telecommunications cabling for domestic, commercial or industrial customers. Licensing, legislative, regulatory and certification requirements apply to telecommunications systems. Work functions in the occupational areas where this unit may be used are subject to regulatory requirements. All customer cabling work in the telecommunications, fire, security and data industries must be performed by a registered cabler. All cablers are required to register with an Australian Communications and Media Authority (ACMA) accredited registrar. Refer to the ICT Information and Communications Technology Training Package Companion Volume Implementation Guide or the relevant regulator for specific guidance on requirements.
Duration and Setting X weeks, nominally xx hours, delivered in a classroom/online/blended learning setting.
Prerequisites/co-requisites
Competency Field
Development and validation strategy and guide for assessors and learners Student Learning Resources Handouts
Activities
Slides
PPT
Assessment 1 Assessment 2 Assessment 3 Assessment 4
Elements of Competency Performance Criteria              
Element: Prepare for installation of underground enclosure and conduit
  • Obtain construction design plan from appropriate personnel and determine and obtain type of underground enclosure specified
  • Arrange access to site according to required enterprise procedure
  • Inform appropriate personnel of existing and potential worksite hazards
  • Verify location of proposed installation according to appropriate plans obtained from authorised personnel
  • Obtain information about location of other services from relevant authorities
  • Organise plant, tools and equipment for given work and safe work practice
  • Place recognised barriers during construction according to safety and enterprise requirements
       
Element: Install enclosure and conduit
  • Excavate site, maintaining stability and allowing ease of access
  • Install enclosure or pit according to design specifications, and work health and safety (WHS) and environmental requirements
  • Install conduit according to specifications and manufacturer requirements, ensuring internal surfaces are free from impediments and sharp edges for cable hauling
  • Seal conduit entry into enclosure against foreign matter
  • Install cable support structure and access facilities in pits according to specifications
       
Element: Restore site and complete documentation
  • Complete backfill safely using suitable soil and materials that ensure conduit protection
  • Recover obsolete materials and equipment and return to appropriate point for disposal
  • Restore site according to requirements of enterprise or approving authority and customer satisfaction
  • Complete reports on installation and design amendments accurately and file promptly according to enterprise requirements
  • Notify appropriate personnel of job completion and obtain sign-off
       

Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assignment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.
Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Obtain construction design plan from appropriate personnel and determine and obtain type of underground enclosure specified 
Arrange access to site according to required enterprise procedure 
Inform appropriate personnel of existing and potential worksite hazards 
Verify location of proposed installation according to appropriate plans obtained from authorised personnel 
Obtain information about location of other services from relevant authorities 
Organise plant, tools and equipment for given work and safe work practice 
Place recognised barriers during construction according to safety and enterprise requirements 
Excavate site, maintaining stability and allowing ease of access 
Install enclosure or pit according to design specifications, and work health and safety (WHS) and environmental requirements 
Install conduit according to specifications and manufacturer requirements, ensuring internal surfaces are free from impediments and sharp edges for cable hauling 
Seal conduit entry into enclosure against foreign matter 
Install cable support structure and access facilities in pits according to specifications 
Complete backfill safely using suitable soil and materials that ensure conduit protection 
Recover obsolete materials and equipment and return to appropriate point for disposal 
Restore site according to requirements of enterprise or approving authority and customer satisfaction 
Complete reports on installation and design amendments accurately and file promptly according to enterprise requirements 
Notify appropriate personnel of job completion and obtain sign-off 

Forms

Assessment Cover Sheet

ICTCBL334 - Install underground enclosures and conduit
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

ICTCBL334 - Install underground enclosures and conduit

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: