Install and maintain de-energised low voltage underground paper insulated cables
Version 1.0
Issue Date: June 2024
Qualification | - |
Unit of Competency | UETTDRCJ22 - Install and maintain de-energised low voltage underground paper insulated cables |
---|---|---|---|
Description | |||
Employability Skills | |||
Learning Outcomes and Application | This unit involves the skills and knowledge required to install and maintain de-energised low voltage (LV) underground paper insulated cables in the electricity supply industry (ESI).It includes jointing and terminating cables using a range of equipment, tools and materials. It also includes testing, isolating, obtaining electrical access permits and completing relevant documentation.The application of the skills and knowledge described in this unit may require a licence/registration to practice in the workplace.Other conditions may apply under state and territory legislative and regulatory licensing requirements which must be confirmed prior to commencing this unit. | ||
Duration and Setting | X weeks, nominally xx hours, delivered in a classroom/online/blended learning setting. |
||
Prerequisites/co-requisites | |||
Competency Field | Cable Jointing |
Development and validation strategy and guide for assessors and learners | Student Learning Resources | Handouts Activities |
Slides PPT |
Assessment 1 | Assessment 2 | Assessment 3 | Assessment 4 | |
---|---|---|---|---|---|---|---|---|
Elements of Competency | Performance Criteria | |||||||
Element: Prepare to joint and maintain de-energised LV underground paper insulated cables |
| |||||||
Element: Job requirements and workplace procedures are identified and communicated with relevant personnel | ||||||||
Element: Work health and safety (WHS)/occupational health and safety (OHS), environmental and workplace procedures for the installation and maintenance of de-energised LV underground paper insulated cables are obtained and confirmed for the purposes of the work to be performed | ||||||||
Element: Work is prioritised and sequenced for completion within acceptable timeframes following consultation with relevant personnel and in accordance with workplace procedures | ||||||||
Element: WHS/OHS and environmental hazards are identified, risks are assessed and control measures identified in accordance with workplace procedures | ||||||||
Element: Relevant work permits are confirmed and signed in accordance with workplace procedures | ||||||||
Element: Plant, equipment, tools and personal protective equipment (PPE) required for work are identified, obtained and confirmed in working order | ||||||||
Element: Worksite is prepared to minimise risk, damage to property, commerce and individuals in accordance with workplace procedures | ||||||||
Element: Traffic management plan is confirmed as being applied in accordance with workplace procedures | ||||||||
Element: Carry out installation and maintenance of de-energised LV underground paper insulated cables |
| |||||||
Element: Requirements for lifting and/or climbing and/or working at heights and the use of power tools/equipment are followed in accordance with workplace procedures | ||||||||
Element: Cables are tested in accordance with workplace procedures | ||||||||
Element: Cables are prepared for jointing, terminating or maintaining in accordance with construction drawings, manufacturer instructions and workplace procedures | ||||||||
Element: Cables are jointed, terminated or maintained in accordance with construction drawings, manufacturer instructions and workplace procedures | ||||||||
Element: De-energised LV underground paper insulated cables are maintained, repaired or replaced in accordance with job schedule, work requirements and workplace procedures | ||||||||
Element: Unplanned events are responded to in accordance with workplace procedures | ||||||||
Element: Quality checks of work are undertaken in accordance with workplace procedures | ||||||||
Element: Complete the installation and maintenance of de-energised LV underground paper insulated cables |
| |||||||
Element: WHS/OHS and environmental incidents are reported in accordance with workplace procedures as required | ||||||||
Element: Worksite is rehabilitated, cleaned up and made safe in accordance with workplace procedures | ||||||||
Element: Tools, equipment and surplus resources are, where appropriate, cleaned, checked and returned to storage or disposed of in accordance with workplace procedures | ||||||||
Element: Relevant work permits are signed off and LV underground paper insulated cables are returned to service in accordance with workplace procedures | ||||||||
Element: Work records, reports and/or documentation are completed in accordance with workplace procedures |