Unit of Competency Mapping – Information for Teachers/Assessors – Information for Learners
UETTDRCJ25 Mapping and Delivery Guide
Perform straight through high voltage paper insulated to polymeric transition joint
Version 1.0
Issue Date: June 2024
Qualification | - |
Unit of Competency | UETTDRCJ25 - Perform straight through high voltage paper insulated to polymeric transition joint |
---|---|---|---|
Description | |||
Employability Skills | |||
Learning Outcomes and Application | This unit involves the skills and knowledge required to perform straight through high voltage (HV) paper insulated cable to polymeric transition joint cable in the electricity supply industry (ESI).It includes the formation of a HV/low voltage (LV) transition joint(s) from paper insulated to polymeric cable on belted and screened cables, the determination of electrical values of belt papers and core insulation, protection of core and belt papers prior to setting, core setting, termination of belt papers, construction of bell mouth and moisture testing. It also includes isolation of systems and circuits, the procedures of issuing/accepting electrical access permits, undertaking pre-commissioning and/or re-commissioning tests and updating system data/maintenance records.The application of the skills and knowledge described in this unit may require a licence/registration to practice in the workplace.Other conditions may apply under state and territory legislative and regulatory licensing requirements which must be confirmed prior to commencing this unit. | ||
Duration and Setting | X weeks, nominally xx hours, delivered in a classroom/online/blended learning setting. |
||
Prerequisites/co-requisites | |||
Competency Field | Cable Jointing |
Development and validation strategy and guide for assessors and learners | Student Learning Resources | Handouts Activities |
Slides PPT |
Assessment 1 | Assessment 2 | Assessment 3 | Assessment 4 | |
---|---|---|---|---|---|---|---|---|
Elements of Competency | Performance Criteria | |||||||
Element: Prepare to joint HV paper insulated cables to HV polymeric cables |
| |||||||
Element: Job requirements and workplace procedures are identified and communicated with relevant personnel | ||||||||
Element: Work health and safety (WHS)/occupational health and safety (OHS), environmental and workplace procedures for the formation of a paper insulated to polymeric transition joint are obtained and confirmed for the purposes of the work to be performed | ||||||||
Element: Work is prioritised and sequenced for completion within acceptable timeframes following consultation with relevant personnel and in accordance with workplace procedures | ||||||||
Element: WHS/OHS and environmental hazards are identified, risks are assessed and control measures identified in accordance with workplace procedures | ||||||||
Element: Relevant work permits are obtained, understood and signed in accordance with workplace procedures | ||||||||
Element: Plant, equipment, tools and personal protective equipment (PPE) required for work are identified, obtained and confirmed in working order | ||||||||
Element: Worksite is prepared to minimise risk, damage to property, commerce and individuals in accordance with workplace procedures | ||||||||
Element: Traffic management plan is confirmed as being applied in accordance with workplace procedures | ||||||||
Element: Carry out jointing of HV paper insulated cable to HV polymeric cable |
| |||||||
Element: Requirements for lifting and/or climbing and/or working at heights and the use of power tools/equipment are followed in accordance with workplace procedures | ||||||||
Element: Systems and circuits are isolated as required, proved safe to work on in accordance with workplace procedures | ||||||||
Element: Cables are prepared for jointing, terminating or maintaining in accordance with construction drawings, manufacturer instructions and workplace procedures | ||||||||
Element: Cables are jointed, terminated or maintained in accordance with construction drawings, manufacturer instructions and workplace procedures | ||||||||
Element: Unplanned events are responded to in accordance with workplace procedures | ||||||||
Element: Quality checks of work are undertaken in accordance with workplace procedures | ||||||||
Element: Complete jointing of HV paper insulated cable to HV polymeric cable |
| |||||||
Element: WHS/OHS and environmental incidents are reported in accordance with workplace procedures, as required | ||||||||
Element: Worksite is rehabilitated, cleaned up and made safe in accordance with workplace procedures | ||||||||
Element: Tools, equipment and surplus resources are, where appropriate, cleaned, checked and returned to storage in accordance with workplace procedures | ||||||||
Element: Relevant work permits are signed off and HV/LV underground paper insulated/polymeric cables are returned to service in accordance with workplace procedures | ||||||||
Element: Work records, reports and/or documentation are completed in accordance with workplace procedures |