UETTDRDS16B Mapping and Delivery Guide
Develop planned outage strategies

Version 1.0
Issue Date: April 2024


Qualification -
Unit of Competency UETTDRDS16B - Develop planned outage strategies
Description 1) 1.1) This Competency Standard Unit covers the competency required to assess, and manage the impact on the network and customers with regards to planned outages. This includes customer outage times, network and plant loading issues and regulatory requirements. A detailed knowledge of Network performance indicators is included.
Employability Skills 3)The required outcomes described in this unit of competency contain applicable facets of Employability Skills. The Employability Skills Summary of the qualification in which this unit of competency is packaged will assist in identifying Employability Skill requirements.
Learning Outcomes and Application 4) This Competency Standard Unit is intended to augment formally acquired competencies. It is suitable for employment-based programs under an approved contract of training.
Duration and Setting X weeks, nominally xx hours, delivered in a classroom/online/blended learning setting.
Prerequisites/co-requisites Prerequisite Unit(s) 2) 2.1) CompetenciesGranting of competency in this unit shall be made only after competency in the following unit(s) has/have been confirmed: UEENEED004B Use Engineering Application Software and UETTDRIS22B Implement and monitor the organisation's OHS policies, procedures and programs. For the full prerequisite chain details for this unit please refer to Table 3 in Volume 1, Part 2
Competency Field
Development and validation strategy and guide for assessors and learners Student Learning Resources Handouts
Activities
Slides
PPT
Assessment 1 Assessment 2 Assessment 3 Assessment 4
Elements of Competency Performance Criteria              
Element: Plan and coordinate for the development of outage strategies
  • OHS practices/procedures and environmental and sustainable energy procedures, which may influence the outage strategies, are reviewed and determined.
  • Purpose of the strategies is established and expected outcomes of the work are confirmed with the appropriate personnel.
  • Organisational established procedures on policies and specifications for the strategies are obtained or established with the appropriate personnel.
  • Equipment/tools and personnel protective equipment are selected and coordinated based on specified requirements and established procedures
  • Work is prioritised and sequenced for the most efficient and effective outcome following consultation with others for completion within acceptable timeframes, to a quality standard and in accordance with established procedures
  • Risk control measures are identified, prioritised and evaluated against the work schedule
  • Relevant work permits are secured to coordinate the performance of work according to requirements and/or established procedures
  • Resources including personnel, equipment, tools and personal protective equipment required for the job are identified, scheduled and coordinated and confirmed in a safe and technical working order
  • Liaison and communication issues with other/authorised personnel, authorities, clients and land-owners are resolved and activities coordinated to carry out work
  • Personnel participating in the work, including plant operators and contractors, are fully briefed and respective responsibilities coordinated and authorised where applicable in accordance with established procedures
       
Element: Carry out and coordinate outage strategies
  • Circuit/systems modelling is used to evaluate alternative proposals as per established procedures.
  • OHS and sustainable energy principles, functionality and practices to reduce the incidents of accidents and minimise waste are incorporated into the strategy in accordance with requirements and/or established procedures
  • Strategy decisions are made on the basis of safety and effective outcomes according to requirements and/or established procedures
  • Mathematical models of the outage strategies are used to analyse the effectiveness of the finished project as per requirements and established procedures
  • Technical advice is given to potential hazards, safety risks and control measures so that monitoring and preventative action can be undertaken and/or appropriate authorities consulted, where necessary, in accordance with requirements and established procedures
  • Essential knowledge and associated skills are applied to analyse specific data and compare it with compliance specifications to ensure completion of the strategy within an agreed timeframe according to requirements.
  • Solutions to non-routine problems are identified and actioned using acquired essential knowledge and associated skills according to requirements
  • Quality of work is monitored against personal performance agreement and/or established organisational and professional standards.
       
Element: Complete and coordinate outage strategies
  • Final review of the strategy is undertaken to ensure it complies with all requirements and include all specifications and documentations needed to complete the project.
  • Reports and/or completion documents are submitted to relevant personnel/organisations for approval and, where applicable, statutory or regulatory approval
  • Approved copies of outage strategy documents are issued and records are updated in accordance with established procedures.
       


Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

9) This provides essential advice for assessment of the unit of competency and must be read in conjunction with the Performance Criteria and the range statement of the unit of competency and the Training Package Assessment Guidelines.

The Evidence Guide forms an integral part of this Competency Standard Unit and shall be used in conjunction with all component parts of this unit and, performed in accordance with the Assessment Guidelines of this Training Package.

Overview of Assessment

9.1)

Longitudinal competency development approaches to assessment, such as Profiling, require data to be reliably gathered in a form that can be consistently interpreted over time. This approach is best utilised in Apprenticeship programs and reduces assessment intervention. It is the Industry's preferred model for apprenticeships. However, where summative (or final) assessment is used it is to include the application of the competency in the normal work environment or, at a minimum, the application of the competency in a realistically simulated work environment. It is recognised that, in some circumstances, assessment in part or full can occur outside the workplace. However, it must be in accord with Industry and, Regulatory policy in this regard.

Methods chosen for a particular assessment will be influenced by various factors. These include the extent of the assessment, the most effective locations for the assessment activities to take place, access to physical resources, additional safety measures that may be required and the critical nature of the competencies being assessed.

The critical safety nature of working with electricity, electrical equipment, gas or any other hazardous substance/material carries risk in deeming a person competent. Hence, sources of evidence need to be 'rich' in nature so as to minimise error in judgment.

Activities associated with normal every day work have a bearing on the decision as to how much and how detailed the data gathered will contribute to its 'richness'. Some skills are more critical to safety and operational requirements while the same skills may be more or less frequently practiced. These points are raised for the assessors to consider when choosing an assessment method and developing assessment instruments. Sample assessment instruments are included for Assessors in the Assessment Guidelines of this Training Package.

Critical aspects of evidence required to demonstrate competency in this unit

9.2)

Before the critical aspects of evidence are considered all prerequisites shall be met.

Evidence for competence in this unit is based, shall be considered holistically. Each element and associated Performance Criteria shall be demonstrated on at least two occasions in accordance with the "Assessment Guidelines - UET09". Evidence shall also comprise:

A representative body of Performance Criteria demonstrated within the timeframes typically expected of the discipline, work function and industrial environment. In particular this shall incorporate evidence that shows a candidate is able to:

Implement Occupational Health and Safety workplace procedures and practices including the use of risk control measures as specified in the Performance Criteria and range; and

Apply sustainable energy principles and practices as specified in the Performance Criteria and range; and

Demonstrate an understanding of the essential knowledge and associated skills as described in this unit to such an extent that the learner's performance outcome is reported in accordance with the preferred approach; namely a percentile graded result, where required by the regulated environment; and

Demonstrate an appropriate level of employability skills; and

Conduct work observing the relevant Anti Discrimination legislation, regulations, policies and workplace procedures; and

Demonstrated performance across a representative range of contexts from the prescribed items below:

Range of tools/equipment/materials/procedures/workplaces/other variables

Group No

The minimum number of items on which skill is to be demonstrated

Item List

A

Writing of three (3) switching instructions that relate to each of the following network types:

LV networks

HV networks

B

Each of the above switching instructions to include the following:

Switching instructions laid out according to enterprise requirements for layout

A documented process to indicate methods used to check switching instructions

Documentation of coordination process of switching schedules

Documentation of plant loading calculation

Entry of data for collection of 'minute of supply' records into relevant systems

C

At least one occasion

Dealing with an unplanned event by drawing on essential knowledge and associated skills to provide appropriate solutions incorporated in the holistic assessment with the above listed items.

Context of and specific resources for assessment

9.3)

This unit should be assessed as it relates to normal work practice using procedures, information and resources typical of a workplace. This should include:

OHS policy and work procedures and instructions.

Suitable work environment, facilities, equipment and materials to undertake actual development of Planned Outage Strategies

In addition to the resources listed above, in Context of and specific resources for assessment, evidence should show demonstrated competency working realistic environment and a variety of conditions.

Method of assessment

9.4)

This Competency Standard Unit shall be assessed by methods given in Volume 1, Part 3 "Assessment Guidelines".

Note:
Competent performance with inherent safe working practices is expected in the Industry to which this Competency Standard Unit applies. This requires that the specified essential knowledge and associated skills are assessed in a structured environment which is primarily intended for learning/assessment and incorporates all necessary equipment and facilities for learners to develop and demonstrate the essential knowledge and associated skills described in this unit.

Concurrent assessment and relationship with other units

9.5)

There are no recommended concurrent assessments with this unit, however in some cases efficiencies may be gained in terms of learning and assessment effort being concurrently managed.


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assignment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

7) Essential Knowledge and Associated Skills (EKAS): This describes the essential skills and knowledge and their level, required for this unit.

Evidence shall show that knowledge has been acquired of designing distribution substations.

All knowledge and skills detailed in this unit should be contextualised to current industry practices and technologies.

The extent of the essential knowledge and associated skills (EKAS) required is given in Volume 2 - Part 2.2 EKAS. It forms an integral part of this unit.

E2.18.1

Occupational Health and Safety principles

E2.18.2

Electrical safe working practice

E2.18.8.2

Occupational health and safety , enterprise responsibilities

T2.2.49

Co-ordinating permit access authority procedures.

T2.3.8

Safe design principles

T2.4.1

Switchgear installation

T2.4.2

Low voltage switching principles

T2.4.3

High voltage switching principles

T2.4.11

High voltage overhead and substation switching principles

8) This relates to the unit of competency as a whole providing the range of contexts and conditions to which the Performance Criteria apply. It allows for different work environments and situations that will affect performance.

This Competency Standard Unit shall/may be demonstrated in relation to the development of planned outage strategies and may include the following equipment:

Distribution feeders/networks, zone substation networks, substations , transformers, HV switchgear, LV switchgear, relevant protection systems, (fuses and circuit breakers), switching instructions (applicable to enterprise equipment), computers (applicable to enterprise equipment), network diagrams.

The following constants and variables included in the element/Performance Criteria in this unit are fully described in the Definitions Section 1 of this volume and form an integral part of the Range Statement of this unit:

Appropriate and relevant persons (see Personnel

Appropriate authorities

Appropriate work platform.

Assessing risk

Assessment

Authorisation

Confined space

Diagnostic, testing and restoration.

Documenting detail work events, record keeping and or storage of information.

Drawings and specifications

Emergency

Environmental and sustainable energy procedures

Environmental legislation.

Environmental management documentation.

Established procedures.

Fall prevention

Hazards

Identifying hazards

Inspect

Legislation

MSDS

Notification.

OHS practices

OHS issues

Permits and / or permits to work

Personnel.

Quality assurance systems.

Requirements.

Safe design principles

Testing procedure

Work clearance systems

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
OHS practices/procedures and environmental and sustainable energy procedures, which may influence the outage strategies, are reviewed and determined. 
Purpose of the strategies is established and expected outcomes of the work are confirmed with the appropriate personnel. 
Organisational established procedures on policies and specifications for the strategies are obtained or established with the appropriate personnel. 
Equipment/tools and personnel protective equipment are selected and coordinated based on specified requirements and established procedures 
Work is prioritised and sequenced for the most efficient and effective outcome following consultation with others for completion within acceptable timeframes, to a quality standard and in accordance with established procedures 
Risk control measures are identified, prioritised and evaluated against the work schedule 
Relevant work permits are secured to coordinate the performance of work according to requirements and/or established procedures 
Resources including personnel, equipment, tools and personal protective equipment required for the job are identified, scheduled and coordinated and confirmed in a safe and technical working order 
Liaison and communication issues with other/authorised personnel, authorities, clients and land-owners are resolved and activities coordinated to carry out work 
Personnel participating in the work, including plant operators and contractors, are fully briefed and respective responsibilities coordinated and authorised where applicable in accordance with established procedures 
Circuit/systems modelling is used to evaluate alternative proposals as per established procedures. 
OHS and sustainable energy principles, functionality and practices to reduce the incidents of accidents and minimise waste are incorporated into the strategy in accordance with requirements and/or established procedures 
Strategy decisions are made on the basis of safety and effective outcomes according to requirements and/or established procedures 
Mathematical models of the outage strategies are used to analyse the effectiveness of the finished project as per requirements and established procedures 
Technical advice is given to potential hazards, safety risks and control measures so that monitoring and preventative action can be undertaken and/or appropriate authorities consulted, where necessary, in accordance with requirements and established procedures 
Essential knowledge and associated skills are applied to analyse specific data and compare it with compliance specifications to ensure completion of the strategy within an agreed timeframe according to requirements. 
Solutions to non-routine problems are identified and actioned using acquired essential knowledge and associated skills according to requirements 
Quality of work is monitored against personal performance agreement and/or established organisational and professional standards. 
Final review of the strategy is undertaken to ensure it complies with all requirements and include all specifications and documentations needed to complete the project. 
Reports and/or completion documents are submitted to relevant personnel/organisations for approval and, where applicable, statutory or regulatory approval 
Approved copies of outage strategy documents are issued and records are updated in accordance with established procedures. 

Forms

Assessment Cover Sheet

UETTDRDS16B - Develop planned outage strategies
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

UETTDRDS16B - Develop planned outage strategies

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: